1 Lafayette New Terminal Program Update
April 11, 2018

2 Agenda Airside and Landside Site Analysis Terminal Facility Cost
Schedule CMAR Coordination Next 60 days Agenda

3 Overall Site Plan – April 2018

4 QTA Meeting with Rental Car Agencies to review design scheduled for May 3, 2018

5 QTA

6 Temporary RTR Cable October 2017 Temporary Cable
April 2018 Temporary Cable

7 Proposed RTR Facility Taxiway M Proposed RTR Facility ARFF Bell
Helicopter Taxiway M Proposed RTR Facility ARFF

8 1st Floor Layout – April 2018

9 1st Floor Layout – April 2018

10 2nd Floor Layout – April 2018

11 TSA, Security, LAC Office and Commission Rooms
2nd Floor Layout – April 2018 Concessions, SARA, Mother’s Room

12 Terminal Program Budget
Current Estimate Budget

13 Estimate Terminal Building – 2018 $80.3M*
Completed 30% design estimate reconciliation with the CMAR Difference is statistically insignificant QTA what changed? Need to see why things changed. *Terminal Building cost does not include Landside or Airside Civil Site or Costs associated with the Quick Turn Around Facility

14 Master Schedule Activity Start Finish Enabling Demo 27-Mar-17 A
06-Nov-18 Quick Turnaround (QTA) 12-Apr-17 A 15-May-19 RTR Cable Relocation 14-Feb-18 A 04-Mar-19 Civil Landside 15-Feb-18 A 07-Oct-21 Terminal Sitework 14-Dec-17 A 03-Apr-19 Terminal 13-Dec-17 A 25-Mar-21 Civil Airside 15-Jul-21 RTR Facility 15-Jan-18 A 12-Mar-20 Landscaping 04-Jan-21 13-Oct-21

15 CMAR Coordination 30% Cost Estimate Reconciliation Design Coordination
Constructability Reviews Progress Estimates GMP Multiple Packages to Coordinate with Funding Schedule Timing and Procedures Multiple GMPs based on bid packages IGMP at 90% design CMAR Coordination

16 Next 60 days Environmental Assessment - FONSI – May 1st
Release Enabling Demo and QTA Packages for bid Review Terminal Airside Package Review Terminal Building Package Schedule Funding Meeting with LADOTD Review QTA Design with Rental Car Agencies RTR Cable Relocation Bid by CMAR Estimate and Reconciliation with CMAR/RS&H Potential RFP Selection for short term financing Next 60 days