1 TGs Process, March Date: 2009-03-10 Author: March 2009 March 2009
doc.: IEEE /XXXr0 March 2009 TGs Process, March Date: Author: Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

2 March 2009 doc.: IEEE /XXXr0 March 2009 Abstract Slides for discussion of the IEEE TGs process in getting through Working Group Letter Ballot and Beyond. Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

3 Mesh Networking Task Group Process
March 2009 Mesh Networking Task Group Process TGs Motto: “Perfection is achieved not when there is nothing left to add but when there is nothing left to take away.” Donald E. Eastlake 3rd (Motorola) Donald Eastlake 3rd, Motorola

4 Process of Getting to Letter Ballot and Beyond
March 2009 doc.: IEEE /XXXr0 March 2009 Process of Getting to Letter Ballot and Beyond Completed Steps | Future Steps Adoption of PAR and 5 Criteria Technical Presentations and Discussions, Specify Any Additional Requirements, Comparison Criteria, or Other Documents Call For and Presentation of Proposals Select from Submitted Complete Proposals to Produce a Draft Refine Draft 1st Letter Ballot – November 2006 – Fails Resolve Comments 2nd Letter Ballot – March 2008 – Fails 3rd Letter Ballot – March 2009 Recirculation Sponsor Ballot – January 2010 (?) Final WG/EC Approval IEEE SB REVCOM Approval Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

5 Process for Refining Draft
March 2009 doc.: IEEE /XXXr0 March 2009 Process for Refining Draft Letter Ballot #93 on Draft D1.0 authorized at November 2006 meeting. Approval rate 48%. 5,713 comments, about ½ Editorial and ½ Technical. Letter Ballot #126 on Draft D2.0 authorized at the March 2008 meeting. Approval rate 61%. 1,964 comments, about 1/3 Editorial and 2/3 Technical. 75% approval required to pass. Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

6 Advantages/Disadvantages of Passing/Failing Letter Ballot
March 2009 doc.: IEEE /XXXr0 March 2009 Advantages/Disadvantages of Passing/Failing Letter Ballot Advantages Disadvantages Passing Letter Ballot You enter “re-circulation” so subsequent votes are 15 days and voters can only add comment each time on parts of the Draft that have changed or been affected by changes. The voting pool is fixed and no new people joining can vote. You must resolve every comment by a ¾ vote. You can only change the draft through the resolution of comments. Failing Letter Ballot You are free to make whatever changes in the Draft the task group wants. Your next Letter Ballot must be at least 30 days and will include everyone in the Working Group at that time and they can comment on any part of the Draft. Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

7 3 Cycles of Comments and Resolution
March 2009 3 Cycles of Comments and Resolution Call for Informal Comments Comment Resolution Comment Resolution WG Letter Ballot / Recirculation Sponsor Ballot / Recirculation Comment Resolution Donald Eastlake 3rd, Motorola

8 Summary of Comment Resolution
March 2009 Summary of Comment Resolution LB #126 Closed Thru Jacksonville Closed Thru Denver Closed Thru Waikoloa Closed Thru Dallas Closed Thru Los Angeles Total 1964 100% 474 24% 783 40% 1368 77% 1660 85% 1891 96% Editorial 656 33% 297 45% 450 69% 545 94% 577 592 99% Technical 1308 67% 177 14% 333 25% 823 1083 79% 1299 95% Donald Eastlake 3rd, Motorola

9 Summary of Comment Resolution
March 2009 Summary of Comment Resolution Current Status Overall Summary Total Open Closed % Closed Total Comments: 1964 73 1891 96.28% Editorial Comments: 600 8 592 98.67% Technical Comments: 1364 65 1299 95.23% General 618 14 604 97.73% MAC 527 10 517 98.10% Security 426 33 393 92.25% RFI 16 377 95.93% Donald Eastlake 3rd, Motorola

10 Schedule Projected at Los Angeles, California, (January) Meeting
March 2009 doc.: IEEE /XXXr0 March 2009 Schedule Projected at Los Angeles, California, (January) Meeting November 2008 (Dallas, Texas) Comment Resolution January 2009 (Los Angeles, California) March 2009 (Vancouver, British Columbia) Comment Resolution, Third Letter Ballot Authorized May 2009 (Montreal, Qubec) July 2009 (San Francisco, California) Comment Resolution, Letter Ballot Re-circulation September 2009 (Waikoloa, Hawai‘i) Comment Resolution, LB Recirculation November 2009 (Atlanta Georgia) January 2010 (Garden Grove, California) Comment Resolution, Sponsor Ballot Authorized Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

11 May– Montreal Meeting Schedule
March 2009 doc.: IEEE /XXXr0 March 2009 May– Montreal Meeting Schedule May is an Interim meeting. We will probably have 18 hours (9 regular 2 hour): 1 hr Opening Session: Administrivia, Minutes, Agenda, Process 16 hr Comment Resolution and Draft Improvement 1 hr Closing Session: Process, Teleconferences /Ad Hocs Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

12 Schedule Projected at Los Angeles, California, (January) Meeting
March 2009 doc.: IEEE /XXXr0 March 2009 Schedule Projected at Los Angeles, California, (January) Meeting January 2009 (Los Angeles, California) Comment Resolution March 2009 (Vancouver, British Columbia) Comment Resolution, Third Letter Ballot Authorized May 2009 (Montreal, Qubec) July 2009 (San Francisco, California) Comment Resolution, Letter Ballot Re-circulation September 2009 (Waikoloa, Hawai‘i) Comment Resolution, LB Recirculation November 2009 (Atlanta Georgia) January 2010 (Garden Grove, California) Comment Resolution, Sponsor Ballot Authorized March 2010 (Orlando, Florida) Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

13 TGs Activity Between Meetings
March 2009 doc.: IEEE /XXXr0 March 2009 TGs Activity Between Meetings TGs Activities Between Meetings Requiring Notice: One or more face to face ad hoc meetings, requires 30 days notice. One or multiple Teleconferences, requires 10 days notice, not more often than weekly. Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

14 TGs Activity Between Meetings
March 2009 doc.: IEEE /XXXr0 March 2009 TGs Activity Between Meetings Previously scheduled: Completed Teleconferences: 2009: Feb 4, 18 Canceled Teleconference: 2009: Mar 4 Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola

15 Future Inter 802.11 Meeting Activities
March 2009 Future Inter Meeting Activities Ad Hoc possibilities We could meet somewhere before Montreal (May) or San Francisco (July). However, travel budgets seem to be limited… Donald Eastlake 3rd, Motorola

16 References Earlier TGs Process Submissions Draft P802.11s D2.07
March 2009 doc.: IEEE /XXXr0 March 2009 References Earlier TGs Process Submissions January 2009, 11-09/175r1, Los Angeles, California November 2008, 11-08/1326r1, Dallas, Texas September 2008, 11-08/1049r2, Waikoloa, Hawai‘i July 2008, 11-08/831r2, Denver, Colorado May 2008, 11-08/570r2, Jacksonville, Florida March 2008, 11-08/320r1, Orlando, Florida January 2008, 11-08/82r1, Taipei, Taiwan November 2007, 11-07/2812, Atlanta, Georgia September 2007, 11-07/2398r1, Waikoloa, Hawai‘i September 2007, 11-07/2408r0, Līhu‘e, Kaua‘i, Hawai‘i (ad hoc) Draft P802.11s D2.07 11-08/493r39, LB#126 Comments Resolution Spreadsheet Donald Eastlake 3rd, Motorola Donald Eastlake 3rd, Motorola