1 On behalf of protection systems
Roadmap for PSS 2018/2019 Stuart Birch On behalf of protection systems

2 2017 2017 Today Infrastructure design Hardware design Installation
Cable containment design and BOM’s Purchase Materials (PK) Plan for installation (PK on framework) Hardware design Installation Commission System Design and BOM’s Purchase Materials (PK) 11 days Plan for installation (PK on framework) 100% 5 days 3 days 3 days 5/24 - 5/28 5/19 - 5/23 5/29 - 6/2 TS2 SRS Software design, Install & commission 10 days 65% 0 days 5 days 5 days 0 days Software Simulation 6/5 - 6/9 6/3 - 6/4 6/10 - 6/16 6/17 11 days 15% 2018 2019 2 days 4 days 5 days Week 48 Week 49 Week 5 Week 11 Week 14 Week 15 Week 16 Week 17 Week 18 6/18 - 6/23 6/30 - 7/3 6/24 - 6/29 4 days 1 day TS2 PDR TS2 CDR TS2 FAT TS2 SAT TS2 SIT TS2 FIT TS2 PSS DEMO TS2 SRR 2017 2017 1. ZHAW TS2 Documentation Today 2. ZHAW TS2 Documentation 3. ZHAW TS2 Documentation Documents for TS2 PDR TS2 Hazard and risk Analysis (ES&H) TS2 System description (AD) Safety Plan (PSS) TS2 Concept of Operations (PSS) TS2 SIL determination (PSS) V&V Plan (PSS) Documents for TS2 CDR TS2 PSS Electrical Drawings TS2 PSS Mechanical Drawings TS2 PSS Interface Control Documents TS2 PSS Installation and Commissioning plan TS2 PSS SIL Assessment TS2 Safety Requirements specification TS2 PSS Hardware design PSS Software planning document TS2 PSS Software design document Documents for TS2 SRR TS2 FAT Report TS2 SAT Report TS2 SIT Report TS2 FIT Report Procedures, Training documentation, presentations, etc.

3 2017 2017 Today Infrastructure design Hardware design
PSS1 SRS Software design, Install & commission Documents for PSS1 CDR PSS1 Electrical Drawings PSS1 Mechanical Drawings PSS1 Interface Control Documents PSS1 Installation and Commissioning plan PSS1 SIL Assessment PSS1 Safety Requirements specification PSS1 Hardware design PSS Software planning document PSS Software design document Documents for PSS1 PDR PSS1 Hazard and risk Analysis (ES&H) NC LInac System description (AD) Safety Plan (PSS) PSS1 Concept of Operations (PSS) PSS1 SIL determination (PSS) V&V Plan (PSS) 11 days 100% 5 days 3 days 3 days 1. ZHAW PSS1 Documentation 1. ZHAW PSS1 Documentation 5/19 - 5/23 5/29 - 6/2 5/24 - 5/28 10 days 65% PSS1 PDR PSS1 CDR 0 days 0 days 5 days 5 days 6/3 - 6/4 6/5 - 6/9 6/17 6/10 - 6/16 11 days 15% 2018 2019 2 days 4 days 5 days Week 48 Week 49 Week 5 Week 8 Week 11 Week 14 Week 15 Week 16 Week 17 Week 18 Week 25 Week 27 6/30 - 7/3 6/18 - 6/23 6/24 - 6/29 4 days 1 day TS2 PDR TS2 CDR TS2 FAT TS2 SAT TS2 SIT TS2 FIT TS2 PSS DEMO TS2 SRR 2017 2017 1. ZHAW TS2 Documentation Today 2. ZHAW TS2 Documentation 3. ZHAW TS2 Documentation Documents for TS2 PDR TS2 Hazard and risk Analysis (ES&H) TS2 System description (AD) Safety Plan (PSS) TS2 Concept of Operations (PSS) TS2 PSS SIL determination (PSS) V&V Plan (PSS) Documents for TS2 CDR TS2 PSS Electrical Drawings TS2 PSS Mechanical Drawings TS2 PSS Interface Control Documents TS2 PSS Installation and Commissioning plan TS2 PSS SIL Assessment TS2 Safety Requirements specification TS2 PSS Hardware design PSS Software planning document TS2 PSS Software design document Documents for TS2 SRR TS2 FAT Report TS2 SAT Report TS2 SIT Report TS2 FIT Report Procedures, Training documentation, presentations, etc.

4 2017 2017 Today 11 days 100% 3 days 5 days 3 days 10 days 65% 0 days
Documents for PSS1 CDR PSS1 Electrical Drawings PSS1 Mechanical Drawings PSS1 Interface Control Documents PSS1 Installation and Commissioning plan PSS1 SIL Assessment PSS1 Safety Requirements specification PSS1 Hardware design PSS Software planning document PSS Software design document Documents for PSS1 SRR PSS1 FAT Report PSS1 SAT Report PSS1 SIT Report PSS1 FIT Report Procedures, Training documentation, presentations, etc. 11 days 100% 3 days 5 days 3 days 2. ZHAW PSS1 Documentation 3. ZHAW PSS1 Documentation 5/29 - 6/2 5/24 - 5/28 5/19 - 5/23 10 days 65% PSS1 CDR 0 days 0 days 5 days 5 days PSS1 FAT PSS1 SAT PSS1 SIT PSS1 FIT PSS1 DEMO NCL SRR 6/5 - 6/9 6/10 - 6/16 6/3 - 6/4 6/17 11 days 15% 2019 5 days 2 days 4 days Week 25 Week 27 Week 32 Week 36 Week 40 Week 41 Week 42 Week 44 6/24 - 6/29 6/18 - 6/23 6/30 - 7/3 4 days 1 day Installation and component test Commission 2017 2017 Software design, Install & commission Today Software Simulation

5 Other work: ODH Phase 2 Target PSS Re-build the Lab Existing systems New access door system Materials access system Bunker??? Preparations for first instruments

6 Questions?

7 2017 2017 Today 11 days 100% 3 days 3 days 5 days 10 days 65% 0 days
SECTION 1 May 19 - Jun 2 100% 3 days 3 days 5 days Sub-task Sub-task 2 Sub-task 3 5/19 - 5/23 5/29 - 6/2 5/24 - 5/28 10 days SECTION 2 Jun 3 - Jun 17 65% 0 days 5 days 5 days 0 days Sub-task 1 Sub-task 2 Sub-task 3 Sub-task 4 - zero duration 6/10 - 6/16 6/17 6/3 - 6/4 6/5 - 6/9 11 days SECTION 3 Jun 18 - Jul 3 15% 5 days 4 days 2 days Sub-task 1 Sub-task 2 Sub-sections 1 6/30 - 7/3 6/24 - 6/29 6/18 - 6/23 4 days Sub-sub-task 1 6/27 - 7/2 1 day Sub-sub-task 2 7/3 2018 2017 2017 Week 48 2 3 4 5 6 7 8 Today Tue May 23 Sun Jun 18 Milestone 2 Sat Jun 3 Milestone 4 Mon Jul 3 Milestone 3 Milestone 5 Fri May 19 Milestone 1

8

9

10

11

12

13