1 Activity 2: Technical and Operational Design for the LNG Storage Facility & NG System
Dr. C. Solomonidis Civil and Harbour Engineer Managing Director A. Boutatis Civil and Harbour Engineer (MSc) Technical Director November 2017, Piraeus

2 1 Introduction 2 Activity Description 3 Current Status 4 Work Plan

3 Rogan Associates S.A.

4 Our Services

5

6 1 Introduction 2 Activity Description 3 Current Status 4 Work Plan

7 List of Activities Activity number Activity title Indicative start date Indicative end date 1 Upstream and Midstream Market Roll-out Optimisation 01/04/2017 31/12/2019 2 Technical and Operational Design for LNG Facility & Natural Gas System Development 30/06/2019 3 NG in Road Transportation: Design, Legislation & Implementation Plan 01/06/2017 4 NG for Industrial & Commercial Use: Strategy, Legislation & Implementation Plan 5 NG in the Maritime Sector: Strategy, Legislation & Implementation Plan 6 Financing NG Implementation 01/03/2018 29/02/2020 7 Dissemination & Public Awareness 8 Action Management 31/03/2020

8 Activity 2

9 General Layout Plan

10 Civil Infrastructure: Description of the Jetty
Located west of the main breakwater of Vasiliko Port at a distance of 1.3km Runs offshore in a N.S. direction for 750m and turns (220oN) S.W. for 436m to form FSRU berth Future extension by another 300m for an LNG Carrier is foreseen 4 Breasting Dolphins & 8 Mooring Dolphins Central loading/unloading platform: (30*40*1.5)m at (MSL) Trestle is 14m wide with pile caps on vertical steel pipe piles at 20m interval Pile caps support a 5m roadway & 9m pipe rack, to accommodate cryogenic (LNG) and NG pipes Expansion Loops at about 250m distance Depth at the inner berth: 15-18m(LAT) Depth at the outer berth: 22m (LAT) Rubble mound revetment construction

11 Jetty for the FSRU

12 Structural Model and Typical Cross Section

13 Shelter - Port Expansion Works

14 1 Introduction 2 Activity Description 3 Current Status 4 Work Plan

15 Achieved Goals: Jetty & Onshore Installations
Studies Execution by Start date Submission Completion Basic Design (Jetty) RGN & DTM 1 July 16 August Conceptual design (onshore, cryogenic) DEFA (WSP) Environmental Impact Study RGN Preliminary Safety HL Preliminary QRA Supporting studies Mooring analysis EBS Temperature, air & noise model

16 Achieved Goals: Emergency Shelter
Studies Execution by Start date Submission Completion Basic Design RGN & DTM 1 July 19 August Environmental Impact Study RGN Supporting studies Wave disturbance Coastal impact study Geotechnical CPA Mooring analysis EBS Air, noise, dredged material plume model

17 Overall Progress Activity 2: 25% (time-based) 35% (deliverables-based)
Sub-Activity 2.1: Technical Design and Permits Conceptual Design (Onshore , Cryogenic) Completed Basic Design (Jetty): Completed Preliminary Safety Study & EIA: Completed Preliminary Cost Benefit Analysis: Completed FEED Contract Tender & Award: Completed Final Detailed Design (Jetty) : Follows Tender Documents: Follows FEED Detailed Design (Onshore , Cryogenic) : Follows Sub-Activity 2.2: Ship-to-Facility (STF) Operations Preliminary QRA: Completed HAZID Study: Completed HAZOP Study: Follows NavSim: Follows

18 1 Introduction 2 Activity Description 3 Current Status 4 Work Plan

19

20 Thank You