DOMINICAN REPUBLIC ENERGY SECTOR AT GLANCE

Similar presentations


Presentation on theme: "DOMINICAN REPUBLIC ENERGY SECTOR AT GLANCE"— Presentation transcript:

1 DOMINICAN REPUBLIC ENERGY SECTOR AT GLANCE
Fernando Gonzalez President Consorcio Comercial del Caribe (CCC)

2 Content Power Fuels Opportunities

3 Dom Rep Energy Milestones
1955 Generation and distribution is nationalized 1973 Oil refinery starts operations 1999 Generation and distribution privatized with government participation UK CDC becomes leading investor in generation 2001 Electricity law is approved 2003 Distribution companies return to government property AES LNG terminal starts operation Trinidad RBTT finances with US$110 million EGE HAINA 2007 Renewable Energy Incentive Law approved 2008 Use of LNG introduced in transport and industry 2012 First wind power plant begins operation 2013 Energy and Mines Ministry was established

4 Power Generation in Caribbean
Country Power Capacity (GWh) Puerto Rico 20,710 Dominican Rep. 13.160 Trinidad 7,271 Jamaica 5,280 St. Lucia 3,586 Barbados 1,037 Guyana 817 Grenada 701 St. Kitts 135

5 Installed Capacity by Fuels
BY FUEL (MW) WATER 523 COAL 313 FUEL 2 402 FUEL 6 992 FUEL 2 Y 6 185 LNG 665 WIND 79 TOTAL 3159

6 EXISTING CAPACITY BY FUEL

7 Plants Dispatch Order

8 Power Distribution in Dominican Republic
Total Clients 2,347,524

9 Transmission and Distribution Looses
Power deficit is US$1.2 billion/year

10 NEW PROJECTS 600 MW 2 COAL PLANTS 1000 MW LNG PLANTS 730 MW QUISQUEYA
250 MW ITABO Coal 1000 MW LNG PLANTS 600 MW 2 COAL PLANTS

11 New Projects (Coal – LNG)
430 MW Quisqueya 1 y 2 located in San Pedro de Macoris, promoted by EGE Haina. 250 MW ITABO Plant to be located in Haina, promoted by AES Dominicana. 300 MW Quisqueya 3, plant to be located in San Pedro de Macoris and promoved by EGE Haina. 600 MW, 2 coal plants each of 300 MW to be located in Azua and promoved by an CDEEE via an international tender. 1000 MW LNG plants to be located in Manzanillo promoted by DR government which includes a LNG terminal.

12 SOLAR NEW PROJECTS 57.96 MW solar plant located in Montecristi to be developed by GESTAMP ASETYM SOLAR. 50 MW solar plant located in Guerra to be developed by WCG ENERGY. 50 MW solar plant located in Santo Domingo Norte to be developed by ISOFOTÓN. 30 MW solar plant located in Monte Plata to be developed by ELECTRONIC J.R.C.

13 50 MW photovoltaic plant ELECTRONIC J.R.C.
GESTAMP ASETYM SOLAR 50 MW photovoltaic plant ISOFOTÓN. 50 MW photovoltaic plant WCG ENERGY

14 Other Projects LNG terminal
With a capacity of 160,000 M3 to be located in San Pedro de Macoris. The terminal is expected to supply with LNG a total of 1180 MW, generated by: Compañía de Electricidad de SPM of 300 MW. La sultana 150MW, Quisqueya 1,2 and 3, 730 MW

15 LNG TERMINAL PROMOTERS
GNL of the East Complex. Interenergy a leading investor in power generation in DR. Vicini the oldest and largest conglomerate in DR  Santana and Marti combined the largest private importers and distributors of fuels in DR. Promigas a large LNG distributors in Colombia.  BW a Singapore based LNG and LPG transport company.

16 Quisqueya 1,2 and 3 CESPM and La sultana TERMINAL OF NATURAL GAS

17 Fuels in Dominican Republic
 LPG LPG largest imported fuel There are 3 terminals Two importers, Refidomsa and Coastal Has 71 distributors and 700 propane gas stations. LPG is been considered as a conversion alternative to transition from fuel oil to LNG. 

18 Fuels in Dominican Republic cont.
LNG Fuel with the fastest growing trend Existing LNG terminal of 160,000 M3 New terminal of 160,000 M3 promoted 665 MW are presently fueled by LNG Additional 1180 MW estimated by 2015 6,000 vehicles operate with CNG and 20,000 by 2016 52 industries use LNG 18 LNG stations nationwide

19 FUEL CONSUMPTION HISTORY IN MILLION GALLON

20

21 LNG

22 Energy Sector Opportunities In Dom Rep
LNG CONVERSION: The new terminal will generate needs for financing, equipment, molecules, transportation, pipe lines, etc. RENEWABLE ENERGY: Incentives have been given to investments in renewable energy such as wind, solar, hydro and biomass. OIL AND GAS EXPLORATION: A new ministry of Energy and mines has been created in Dom Rep with the purpose prioritize the sector. Oil and gas exploration will be developed.

23 CONCLUSIONS Given the fact that:
Trinidad is the major hydrocarbon supplier of Dominican Republic. DR has started to give priority to the energy sector New energy projects are been developed. It’s proposed that both Trinidad and Dominican Republica start a process of identifying synergies to complement each other in the energy sector.

24 THANKS