Presentation is loading. Please wait.

Presentation is loading. Please wait.

ELC 347 project management

Similar presentations


Presentation on theme: "ELC 347 project management"— Presentation transcript:

1 ELC 347 project management
Day 20

2 Agenda Integrative Project Part 4 Not corrected (yet) Part 5 Due Nov 24 (page 342) Any of the first five sections can be resubmitted for rescoring prior to finals week. The recorded score will the average of the original score and the score on the resubmitted section. Assignment 6 Graded 3 A’s, 3 B’s, 2 D’s and 1 F Assignment 7 Posted Due Nov. 24 Today will discuss Project Scheduling: Lagging, Crashing and Activity Networks

3 Schedule for rest of semester
Nov 13 Chap 10 Nov 17 Chap 11 Nov 20 Group work Nov 24 Quiz 3 Through Chap 11 IP part 5 Due Assignment 7 due Dec 1 Project s 5 & 6 Dec 4 Group Work Assignment 8 due Dec 8 Chap 12 IP Part 6 due Dec 11 Chap 13 & 14 Dec 10 AM Quiz 4 Through chap 14 IP Project’s due © 2007 Prentice-Hall, Inc

4 Project Scheduling: Lagging, Crashing and Activity Networks
Chapter 10 © 2007 Pearson Education

5

6 Lags in Precedence Relationships
The logical relationship between the start and finish of one activity and the start and finish of another activity. Four logical relationships between tasks Finish to Start Finish to Finish Start to Start Start to Finish

7 This lag is not the same as activity slack
Finish to Start Lag Most common type of sequencing Shown on the line joining the modes Added during forward pass Subtracted during backward pass This lag is not the same as activity slack A Spec Design 6 B Design Check 5 C Blueprinting 7 Lag 4

8 Finish to Finish Lag Two activities share a similar completion point
The mechanical inspection cannot happen until wiring, plumbing, and HVAC installation are complete A Plumbing 6 B HVAC 5 C Inspection 1 D Wiring

9 Start to Start Lag Logic must be maintained by both forward and backward pass A Plumbing 6 B HVAC 5 C Inspection 1 D Wiring Lag 3

10 Start to Finish Lag Least common type of lag relationship
Successor’s finish dependent on predecessor’s start D Wiring 6 Lag 3 B HVAC 5 C Inspection 1 A Plumbing 6 fssf.mpp

11 Gantt Charts Establish a time-phased network
Can be used as a tracking tool Benefits of Gantt charts Easy to create and comprehend Identify the schedule baseline network Allow for updating and control Identify resource needs

12 Create a Gantt chart based on the activities listed in the table.
Task Time Pred Z 8 -- U 3 W Y 5 T 6 V X S 7 U,T 4 Y,X R 9 Task ES EF LS LF Z Y X W V U T S R gantt.mpp

13 Gantt Chart With Resources in MS Project

14 Principal methods for crashing
Crashing Projects Accelerating a project by committing more resources than initially planned Principal methods for crashing Improving existing resources’ productivity Changing work methods Increasing the quantity of resources

15 Example – Calculating the Cost of Crashing
CRASHING ACTIVITIES – AN EXAMPLE Formula Slope = crash cost – normal cost normal time – crash time Example – Calculating the Cost of Crashing SUPPOSE: NORMAL ACTIVITY DURATION = 8 WEEKS NORMAL COST = $14,000 CRASHED ACTIVITY DURATION = 5 WEEKS CRASHED COST = $23,000 THE ACTIVITY COST SLOPE = 23,000 – 14, or, $9, = $3,000 per week 8 –

16

17 Managerial Considerations
Determine activity fixed and variable costs The crash point is the fully expedited activity Optimize time-cost tradeoffs Shorten activities on the critical path Cease crashing when the target completion time is reached the crash cost exceeds the penalty cost

18 Project costs Normal Crashed Crash/day activity Duration Cost A 5 1000
3 1500 250 B 7 700 6 300 C 2500 2 4000 D - E 9 3750 9000 17500 F 4 1600 900 G 2400 3000 H 15000 2000 Total 22450 37500

19

20

21 Other costs Previous examples only includes direct costs What about
Indirect costs (overhead) $ per day overhead Late penalties $ per day late

22

23 What is the lowest cost to complete this project in 53 weeks
What is the lowest cost to complete this project in 53 weeks? Times are in weeks and costs in dollars. Activity Pred Normal Time Min Time Normal Cost Crash Cost A -- 14 9 500 1500 B 5 2 1000 1600 C 10 8 2000 2900 D B, C 2500 E 6 1900 F 3000 G E, F 7 4 600 1800 H 15 11 3600 Initial early and late start and finish times Task ES EF LS LF Slack A B C D E F G H Project 63 Reduce A by 5 days at $200/week = $1000 Project length is now 58 weeks Reduce G by 3 days at $400/week = $1200 Project length is now 55 weeks Reduce C by 2 days at $450/week = $900 Project length is now 53 weeks Total cost to finish project in 53 weeks is $3100 more than normal cost of $9800 crash.mpp, crash.xls

24 Activity on Arrow Networks
Activities represented by arrows Widely used in construction Event nodes easy to flag Forward and backward pass logic similar to AON Two activities may not begin and end at common nodes Dummy activities may be required

25

26 Project delta Activity Pre Duration A 5 B C 6 D B,C 13 E F 4 G 9 H
2

27 Two Succesors Wrong Wrong

28 AOA Network

29 Forward Pass

30 Backwards pass

31 Calculate early and late start and finish times for all activities.
Use AOA to sketch the network that represents the project as described in the table. Calculate early and late start and finish times for all activities. Activity Time Pred A 4 -- F D B 2 G 15 C 10 H 7 E,F,G 3 B,C K 11 E Task ES EF LS LF A B C D E F G H K

32 Controversies in the Use of Networks
Networks can be too complex Poor network construction creates problems Networks may be used inappropriately When employing subcontractors The master network must be available to them All sub-networks must use common methods Positive bias exists in PERT networks


Download ppt "ELC 347 project management"

Similar presentations


Ads by Google