1 PCC Update 07/22/09 Implementation Phase 1
ISD2R\YES NM PCC Update 07/22/09 Implementation Phase 1 12/29/2018

2 Agenda Budget Schedule Current Status Progress 12/29/2018

3 Implementation Phase Budget
Subproject Planned Expenditures & Commitments to Date Yes NM Phase 1 $ 1,6000,000 $1,302,745.87 Business Intelligence $ 618,000 $116,455.42 Imaging\EDMS $2,000,000 995.14 General ISD2R (IV&V, Environment) $116,092.66 TOTAL $ 4,281,190 $1,536,289.09 12/29/2018

4 Current Status YES NM Phase 1 Business Intelligence Imaging Red Green
12/29/2018

5 YES NM Status Summary Outbox is functional and final UAT testing is proceeding. July 27th “go-live” is currently in jeopardy. Content regarding voter registration Time to complete production run-in and security analysis has been delayed by environment challenges. A decision will be made on ‘go-live” by COB Monday July 20. 12/29/2018

6 Business Intelligence
Contract negotiation is underway. 12/29/2018

7 Imaging\EDMS Demo\Orals are scheduled July 21, 22, 23.
Decision will be made by August 7, 2009. 12/29/2018