1 ENTSO-E IT project for Fundamental Electricity Data Transparency
ENTSO-G Transparency Workshop 11 September 2012 Andy Spiceley Project Manager, National Grid

2 The new ENTSO-E Transparency platform
Regulation on transparency in electricity markets ENTSO-E obligations & REMIT Existing transparency platform Project focus and structure Procurement exercise Outline of new platform structure Project schedule & roadmap Key challenges & critical success factors

3 Legal hierarchy of the regulations
DIRECTIVE 2009/72/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 13 July 2009 concerning common rules for the internal market in electricity Regulation 1227/2011 (REMIT) Regulation 714/2009 Implementing acts Network Codes and Transparency Regulation Handbook But this handbook established by ENTSO-E is NOT law but agreed best practices within the industry

4 Elaboration of the Fundamental Electricity
Data Transparency Regulation 2010:ERGEG elaboration of a draft Guideline in close cooperation with ENTSO-E ERGEG advice on comitology guidelines on fundamental electricity data transparency (7/12/2010) EC Public consultation on the ERGEG Proposal (Summer 2011) before proposal of a Commission Regulation : Comitology process 714/2009 Regulation on conditions for access to the network for cross-border exchanges in electricity : Regional Transparency Reports November 19, 2018 4 4

5 The scope of the ENTSO-E Transparency policy
Long-term (years) Mid-term (months) Short-term and ex-post (days) Maintenance of power plants Building of new power plants, Long-term contracts Spot and intraday exchanges Some Market needs Supplying contracts TYNDP Winter and summet outlooks Statistical publications Examples of ENTSOE answer Market data on entsoe.net Market data on entsoe.net Aims of the Fundamental Data Transparency guideline Transparency Policy

6 Transparency platform
Data feed for REMIT ENTSO-E Transparency platform REMIT systems FEDT

7 Next Steps for the Transparency Regulation
DGcomp issues resolved ? Text Finalised EC Inter-service Consultation Aug Electricity XB Committee End Sept Approval End Oct Parliament Review +3 months Adoption and Publish in Official Journal +6 weeks Translation 3 weeks

8 www.entsoe.net Simple and easy to use 34 countries, 41 TSO
Data providers – TSOs, PX, Auction offices, 3rd parties. Users – traders, consultants, European Commission, ACER, Universities, individuals. Each TSO has a single point of contact – Transparency Platform Coordinator (TPC) More than 5 years old not suitable basis for evolution to support all FEDT under regulation Provides valuable operating experience & user feedback

9 Data subject scope & growth
entsoe.net EMFIP Load Generation Transmission Outage Balancing

10 Three challenges, three streams
External coordination : EC, ACER, Brussels stakeholders Transparency Project Steering Group ACER Supervision Close cooperation required Internal coordination : MIT, TPC, EDI, PM BRS IG IT Project Regional projects : TSOs information flows 41 Transparency Projects

11 Stakeholder Engagement
Expert groups: Load, Generation, Transmission, Balancing, IT/Other, Definitions Planning of stakeholder meetings for the Handbook preparation Definitions review Business Requirements Specification (BRS) Implementation Guide – Role, Writers, Deadline, Link between documents

12 Stakeholders Kick-off Workshop
Invitation to Transparency Stakeholder Advisory Group Timing: following DGener/DGcomp agreement & final draft proposal Scope: Terms of Reference Explanation of Regulation Explanation of EMFIP Data Definitions Handbook – xml schemas, mapping data etc. Links to REMIT / UMM

13 Project structure & governance
ENTSO-E board Strategic Data Governance Transparency Project Steering Group (TPSG) Market Committee User groups WG EDI WG MIT EMFIP IT project Domain expert teams TPC

14 Core teams – advocates, champions, experts
BRS Beta testing IGs Core teams subjects Detailed Def’ns subjects subjects Compliance & interoperability Handbook

15 IT supplier procurement
Process defined and co-ordinated for ENTSO-E by EirGrid Activity supported by team of TPC volunteers from TSOs Pre-qualification phase – questionnaire and evaluation – selection of shortlist Development of Request for Proposals Call for Tender materials Scope of Services Requirements Catalogue Assessment criteria Market Consultation sessions Submission and evaluation of bids Final interviews and contract negotiation

16 IT solution scope

17 Web presence

18 Technical overview

19 IT Project - next steps Detailed planning & release schedule
Elaboration of requirements Development and alignment of technical architecture Test definitions Migration strategy

20 Evolution of business requirements
Regulation drafting ………. Comitology process Draft Regulation final Regulation Initial drafts review Propose & agree resolution Generate revised doc revise revise Data model drafting Stakeholder review

21 Existing platform operational
Releases – Roadmap 2013 2014 Q1 Q2 Q3 Q4 Regulation Implentation deadline Existing platform operational archive use only EMFIP live (as “entsoe.net”?) EMFIP Releases: takeover entsoe.net 1 Additional data sets 2 Final release: all data sets 3

22 Key challenges & success factors
Timeline for Regulation & project scope impacts Maintain continuity of service Co-ordination with Data Providers project development Stakeholder engagement Communication with Data Providers Support of Working Group expert teams

23 Thank You