Presentation is loading. Please wait.

Presentation is loading. Please wait.

Dmitri Bugai, Consultant Waste Technology Section NEFW

Similar presentations


Presentation on theme: "Dmitri Bugai, Consultant Waste Technology Section NEFW"— Presentation transcript:

1 Dmitri Bugai, Consultant Waste Technology Section NEFW
Experiences in planning and implementing decommissioning and remediation strategy for the cooling pond of Chernobyl NPP Dmitri Bugai, Consultant Waste Technology Section NEFW Plenary Meeting of the Network on Environmental Management and Remediation (ENVIRONET) 5—7 December 2017, IAEA Headquarters, Vienna The subject of my presentation is ….

2 Contributors of information and data for this presentation
This presentation is based on the IAEA TECDOC on a similar subjected which was finalized by a team of Ukrainian scientists and IAEA experts during June - September 2017 The responsible IAEA officer for this report is Horst Monken-Fernandes The important contributions to the report were provided by V.Kashparov, D.Gudkov, V.Protsak, A.Skalskyy, B.Faybishenko, G.Laptev, V.Kanivets, O.Voitsekhovitch, and others. WATEC 2017

3 Background D&ER activity for the Chernobyl cooling pond is an element of the general D&ER program for the Chernobyl NPP The challenges are related to serious contamination of the pond in the course of the Chernobyl accident in 1986, and it location inside the Exclusion Zone The feasibility study for decommissioning cooling pond was prepared with the assistance from the IAEA in 2013, and approved by Ukrainian Regulatory authorities in 2014 Decommissioning (drainage) of the cooling pond started in 2014, and continues until present time 2013 2017

4 Contents Engineering design and site description
Radioactive contamination Remedial planning (strategy; end-state criteria) Radiological impact assessment analyses (providing bases for remedial design) Remediation experience ( ) and Lessons learned Conclusions

5 1.1 Site description Basic characteristics of the pond Important dates
Parameter Value Length, km 11.5 Mean width, km 2.2 Operational water level”, m a.s.l. 111.0 Surface area, km2 22.9 Volume, million m3 151 Average depth, m 6.6 Max depth, m 18.5 Important dates 1976 – First section of the pond (12.5 km2) was commissioned 1981 – Pond area extended to 22.9 km2 – Chernobyl accident – Last Unit 3 of ChNPP was stopped May 2014 – Start of decommissioning (drainage) of the cooling pond

6 1.2 Engineering design and water balance (operational period)
Design of the dam of the pond Water level in the pond was about ~7 m above the level of Pripyat River The sandy bottom and dam did not have any lining which resulted in large seepage losses Water losses from the pond were compensated by pumping water from Pripyat River Components of water balance of the pond Water balance of the pond Component Value, x106 m3/year Seepage ~ 100 Evaporation (with heat load from 3 units) 30-35 Evaporation (without heat load) ~ 5 ( m3) m3 Maintenance of the pond entailed large exploitation costs (for pumping water)

7 1.3 Bathymetry (depth distribution) of the cooling pond
Bottom topography of the pond based on results of 2001 survey [Buckley et al., 2002] Areas with depths of 7.5 m and less occupied about 70% (~ 15.8 km2) of the pond. These areas can be potentially exposed in case of the drawdown of level in the pond Bottom sediment types at different depths Depth range, m Prevailing type of bottom sediments Bottom area, km2 Fraction of the total cooling pond bottom area, % 0 – 3.5 Sand 2.1 9.6 3.5 – 7.5 Silty sand 13.7 62.6 Silt with admixture of sand (sandy silt) 10-12 Silt 1.7 7.8 > 12 2.3 10.5

8 2.1 Radioactive contamination of the cooling pond
Contamination mechanisms Atmospheric fallout of radioactive aerosols on water surface (nuclear fuel particles, condensation particles) Releases to the pond of the ~5000 m3 of highly contaminated water from the damaged Unit 4 circuits/water used for firefighting 137Cs distribution in bottom sediments (2012) [Voitsekhovitch et al., 2013] Mid-May 1986 : Activity of water in the pond was ~ 104 Bq/L; the total inventory of radionuclides was estimated at ~ 2000 TBq Time dynamics of 137Cs activity in the pond water Media of concern – bottom sediment By the end of 1986: About 95% of 137Cs and 99% of 90Sr in the cooling pond were accumulated in the bottom sediments (sorption on suspended particles, sedimentation…)

9 2.2 Radionuclide inventory and speciation in bottom sediments
Example activity profile in bottom sediments at 12 m depth (2002) [Pirnach et al., 2011] While 137Cs was initially largely in soluble form (condensation aerosols, liquid releases) 90Sr and TRU isotopes were mostly associated with fuel particles (FP) of ~ n 1 … n  10 m size Radioactivity inventory in bottom sediments (2012) [Buckley et al., 2002] Radionuclide Inventory, TBq Max. spec. activity, Bq/g Cesium-137 164±32 ~ Strontium-90 24±9 ~ 100 Plutonuim-239/240 0.5±0.2 ~ 2 Americium-241 1.1±0.4 ~ 4 Autoradiography analyses of FP in bottom sediments [Protsak et al., 2017] Tran-sedimentation; Possibility of RN mobilization in oxidized conditions Due to redistribution (trans-sedintation) highest activities have accumulated in the deep pond areas (>10 m) Geochemical conditions in bottom sediments (anoxic regime, alkaline pH) favoured low dissolution rates of fuel particles In most studies > 90% of activity were in non-exchangeable forms (presumably) associated with undissolved particles

10 3.1 Remedial planning: Strategy – water level drawdown in the pond
Drawdown of water level in the pond has been identified in a sequence of pre-design research projects as an ultimate option for the Chernobyl pond decommissioning Advantages Savings of ~ USD/year (expenses for continued refilling of the pond and dam maintenance) Reduction of radioactivity ex-filtration to Pripyat River Decreasing of groundwater levels in the adjacent areas (including Sarcophagus and radwaste disposal sites) Elimination of the risk of the accident of the dam breach and release of radioactivity

11 3.2 Remedial planning: Risks of water level drawdown in the pond
Atmospheric resuspension of highly contaminated bottom sediments (e.g., accident in Chelyabinsk-65 with dried up Karachay Lake in 1967) Possibilities for exposure to “hot spots” of highly contaminated bottom sediments Increased mobility of radionuclides from bottom sediments (oxidized environment) Ecological damage : “massive dying out of aquatic species”, deterioration of water quality and general ecological situation Predicted configuration of drained bottom areas for different climatic conditions Remedial design foresaw possibility for suspending drainage process (by resuming pumping of water) in case of occurrence of unforeseen negative impacts

12 3.3 Remedial planning: Phases and Radiological End-state criteria
“Brown field” end-state criteria accounting for location of pond inside the Chernobyl Zone End-state coordinated with the decommissioning of the ChNPP (and reflect mean background levels) Zone 1 (NW): 14 µSv/hour Zone 2 (SE): 7 µSv/hour (2012) (criteria set as mean values for 100m x 100 m areas) “Control levels” set for radionuclide airborne concentrations (similar to 10-km zone of ChNPP) Phases of cooling pond decommissioning Preparatory stage ( ) - Creating preconditions (e.g., characterization) and developing design project for the decommissioning Water level drawdown (controlled) – 5-6 years (starting from 2014) Transition period to “stabilization of new aquatic ecosystem” – 7-10 years Period of the long-term institutional control (> 10 years)

13 4.1 Hydrogeological modeling to asses cooling pond drawdown rate and end-state
A set of groundwater flow and radionuclide transport models (MODFLOW, MT3D, NORMALYSA) was developed to assess pond draw-down rate, resulting configuration of residual lakes, and off-site radionuclide fluxes for a set of different climatic scenarios Configurations of residual lakes Normal scenario (B) Dry scenario

14 4.2 Assessment of impacts from drawdown: atmospheric transport of radioactive aerosols
Scenarios: Normal conditions “Dust storm” Wildfire of the contaminated vegetation Reference persons Workers at ChNPP Residents of Chernobyl Town Impacts: For all considered scenarios radiological impact impacts are low (µSv range) Secondary contamination due to deposition is well below existing levels Estimated inhalation 50-yr EED due to atmospheric transport of radioactive aerosols from pond bottom, µSv [KASHPAROV et al., 2011] Scenario Location ChNPP Chernobyl Town “Normal” scenario 0.52 0.009 Dust storm 3.0 0.34

15 4.3 Assessment of impacts from drawdown: Dose rates from bottom sediments
Predicted dose rates from bottom sediments [Kashparov et al., 2011] Several sediment “hot spots” expected in in the Northern and Western parts of the pond Maximum gamma dose rates are comparable to some other locations in Chernobyl zone Managing contaminated bottom sediments: As predicted atmospheric resuspension is low and there is no direct exposure of staff of ChNPP, there is no need to implement large-scale remedial measures for bottom sediments Decisions for local hot spots should be taken on case-by-case basis Conclusion: pond drainage appears to be an acceptable strategy, however the radiation and ecological situation needs to be monitored, and corrective actions shall be carried out in case of need (“controlled drainage”)

16 5.1 Remediation experience: Water level drawdown dynamics
Satellite photo of the pond (August 2016) Reasonable agreement of the actual pond drainage dynamics with a priori modelling predictions By mid-summer 2017 drained bottom area reached ~40% Some discrepancies in elements of bottom relief with the numerical DEM Comparison of the predicted level drawdown rate and monitoring data

17 5.2 Water level drawdown consequences: Re-vegetation of bottom areas
Silty drained pond bottom areas with a densely vegetation (as in 2017) By summer 2017 about 60% of the drained pond bottom was overgrown by newly formed vegetation Highly contaminated silty areas are overgrown by most dense vegetation cover (due to larger organic matter content) Sandy poorly vegetated areas pose low risks of RN resuspension due to low contamination levels Effect of retreating shoreline on “self-seeding” of sandy beaches” (2017) Sandy areas covered by the dead Dreissena shells Photos courtesy of V.Kashparov and V.Protsak, UIAR inst.

18 5.3 Water level drawdown consequences: Radiological impacts
Dose rates from drained bottom areas [data of ChNPP] Radiological impacts (airborne RN concentrations, external dose rates) are generally within the predicted acceptable ranges The fuel particle dissolution in exposed bottom sediments is proceeding slower than expected (part of activity which can be mobilized over next 10 year is estimated at <30%) Atmospheric monitoring data from monitoring stations in the vicinity of the cooling pond Monitoring station Annual averaged 137Cs airborne concentration, Bq/m3 2016 2017 “VRP-750” 2.5E-3 3.6E-3 1.2E-3 “Neftebaza” 6.1E-4 8.7E-4 3.0E-4 “BNS-3” 1.7E-4 2.9E-4 1.5E-4

19 5.3 Water level drawdown consequences: “Ecological” parameters
No feared catastrophic consequences to the pond ecosystem have been observed so far (e.g., massive dying out of aquatic species leading to deterioration of water quality and general ecological situation), which allowed for continuous water level drawdown regime Dissolved oxygen Nitrogen (as ammonia) Data of D.Gudkov, IHB inst.

20 6 Conclusions Behavior of the cooling pond during the initial phase (4 years) of water level drawdown mostly followed a priori modeling predictions Radiological and ecological parameters generally conform to prescribed reference levels A number of natural process/conditions in drained areas favor attenuation of radiological impacts Experience of first 4 years also suggests that better understanding of some radioecological process of the cooling pond would be of broad scientific interest (e.g., fuel particle dissolution behavior, speciation radionuclides in residual reservoirs etc.) Further in-depth radioecological studies of the cooling pond are planned in the frame of the Ukraine-Japan SATREPS project ( ); it is planned that activities of SATREPS will be carried out in close exchange with the IAEA (e.g., joint workshops, information exch. etc.)

21 Thank you! Thank you!


Download ppt "Dmitri Bugai, Consultant Waste Technology Section NEFW"

Similar presentations


Ads by Google