1 Review of UJ56 relocation options
R2E Mitigation Project Review of UJ56 relocation options Main contributions from EN/CV, EN/EL, EN/MEF, GS/ASE, GS/SEM & equipments owners A. L. Perrot, EN/MEF & R2E Study Group 5th November 2010

2 Mitigation options studied
Option A: full relocation in the by-pass (A. L. Perrot) Option B: partial relocation in the by-pass & the UJ561 (UJ561 being the CMS exit path) Option C: partial relocation in the by-pass & the UJ561 finding another CMS exit path (M. Gastal)

3 UJ56 1rst floor Equipment to be moved : power converters + 17 racks

4 UJ56 ground floor - ‘safe room’
Equipment to be moved : 5 racks + internal part of SYAFD01 (fire detection) rack EYP01 (anti-panic lightning), EYC01/02/03 (electric network control), EYU01 (AUG)

5 Option A: full relocation in the by-pass
N.B. request of the equipments owners: 6 racks in the USC55/machine area and 1 rack in the USC55/CMS area - Technically feasible Constraints/consequences: mini safe – room construction in the by-pass (likely) interference with transport volume: Power Converter calibrations racks remaining free space along the USC55 wall before the PAD =20m

6 UJ561 by-pass mini- safe room RYCA01-02 RYMCB01-05
RTQX2.R5 RQX.R5 RYCA01-02 RYMCB01-05 EYU01 & 02 – EYP01 & 02 EYC01 à 04 (h=1.8m) RYLB01 RYLC01 mini- safe room ERD1/56 DYPG01 & 02 CYCIP01 GYPOS01 à 03 CYNET01 – RYSC01 EOD1/56 – EOD3/56 EBS1/56 – UPS machine QYC01 à 04 (h=2.00m) CYTIM01 – CYFRE01 (h=2.00m) RYSA01 – 02 (h=2.00m) Oct Ph. Orlandi, JC Guillaume EN/EL JP Corso, Y. Muttoni, EN/MEF

7 TYCFL02 DYXF01 YYACS01 RYSA CYCIB01 USC55 machine area 6 racks moved from UJ56 1rst floor to USC55 /machine area SYAFD01 eqpt moved from UJ56 ‘safe room’ to USC55/ CMS racks room (S2A19)

8 Option B partial relocation in the by-pass & the UJ561
(UJ561 being the CMS exit path) N.B. request of the equipments owners: 6 racks in the USC55/machine area and 1 rack in the USC55/CMS area - Option B1: install 1 raw of racks in the UJ561= technically feasible => remaining free thickness for the CMS exit path is 1.2 m - Option B2: install the mini safe-room in the UJ561 = technically feasible => remaining free thickness for the CMS exit path is 1.1 m thick Safety requirements concerning exit path (CERN/TIS-GS/ ) depends on the number of persons to evacuate and the number of exits foreseen => 0.9m thick for less than 100 persons

9 Option B: partial relocation in the by-pass &
the UJ561 CMS exit path CYTIM01 – CYFRE01 RYSA01 – 02 QYC01 à 04 DYPG01 & 02 RQX.R5 RTQX2.R5 RYCA01-02 RYMCB01-05 RYLB01 RYLC01 ERD1/56 CYNET01 – RYSC01 GYPOS01 à 03 CYCIP01 Oct Ph. Orlandi, JC Guillaume EN/EL JP Corso, Y. Muttoni, EN/MEF EYU01 & 02 – EYP01 & 02 EYC01 à 04 (h=1.8m)

10 Option B: partial relocation in the by-pass &
the UJ561 CMS exit path Oct Ph. Orlandi, JC Guillaume EN/EL JP Corso, Y. Muttoni, EN/MEF

11 TYCFL02 DYXF01 YYACS01 RYSA CYCIB01 USC55 machine area 6 racks moved from UJ56 1rst floor to USC55 /machine area SYAFD01 eqpt moved from UJ56 ‘safe room’ to USC55/ CMS racks room (S2A19)

12 Civil engineering – Ducts to be drilled

13 Civil engineering – Ducts to be drilled
5 new ducts Ø mm – length 2m ‘mur tympan’ : 5 new ducts Ø 350mm – length 2m

14 Main work to be performed for both Options A & B
Civil engineering activities: - drill 4 ducts between UJ56 and by-pass for PC cables, drill ducts in the wall between by-pass and UJ561 CMS exit path (cables & ventilation) drill 5 ducts in the wall UJ56- machine reinforce the by-pass vault structure (under study) CV activities: UTAs and cooling system installation EL activities: cables trays displacement/installation, cables installation Access : sector door to be moved from by-pass to the UL56 (displt of 11 m) Mini-‘safe room’ construction in the by-pass/UJ561 (under study), BRAN pipes to be rerouted

15 Draft time estimate – main activities
The work load equivalent for options A/B => identical time estimate - EL activities: months (1 shift) months (2 shifts) CE activities: 4 ducts between UJ56/ by-pass - 3 months 5 between UJ56- machine - 1 month 4 ducts in the UJ561/by-pass wall: - 3 weeks CV activities: months (1 shift) - AFD activities: - 5 weeks (detection interruption 5 days) ( 1 shift) - Safe room : - 3 weeks ( 1 shift) Displacement sector door: GS/ASE: days mechanical work :- 1 week negotiation needed with contractor for the options A/B/C compatibility between EL, CE, and CV activities => Planning

16 Draft cost estimate – main activities
- EL activities: opt A: MCHF /opt B: MCHF (1 shift) opt A: MCHF /opt B: MCHF (2 shifts: % manpower) CE activities: 4 ducts between UJ56/ by-pass: 200 KCHF 5 between UJ56- machine: 25 KCHF 4 ducts in the UJ561/by-pass wall: 40 KCHF CV activities: opt. A: 420 KCHF/ opt. B: 445 KCHF (1 shift) - AFD activities: 96 KCHF (1 shift) - Safe room : 57 KCHF Displacement sector door: GS/ASE: 30 KCHF mechanical work : t.b. estimated for the options A/B/C Provisional budget~ 3.4 MCHF EL 1 shift: opt. A: MCHF / opt. B: 3.2 MCHF EL 2 shifts: opt. A: MCHF / opt. B: MCHF

17 Open issues To be done after the decision on the baseline for the mitigation option integration study (details) precise schedule (co-activities) and impact on other LHC activities negotiate the 2 shifts scenario with EL contractor final budget

18 Installation in Jan. 2012decision on the baseline end of Nov. 2011
Time to get ready for installation once baseline mitigation is chosen Integration studies: - 1 month (completion and compatibility CV/EL/LHC drawings, documentation preparation, approval loop) - Planning : month (sequence, co-activities) - EL activities: - DC/CTR: 1 year (Market Survey for special cables?, supply) - power distrib. : 8 months (study, supply) CE activities: months (offers, contractor, work set-up) CV activities: months (Market Survey for special UTAs?, supply) - AFD activities: - 3 months (supply, work set-up) 1 year and 1 month process Installation in Jan. 2012decision on the baseline end of Nov. 2011

19 Summary Option A: full relocation in the by-pass = technically feasible Option B: partial relocation in the by-pass & the UJ561 (UJ561 being the CMS exit path) = technically feasible (CMS exit path 1.2m-1.1 m thick) It looks reasonable to assume that the work could not be performed in less than 15 months for a budget of about 3.4 MCHF Decision on the mitigation option is needed this month to be ready in January 2012.

20 Many thanks to all the involved teams
for their work during this last month Especially to GS/SEM: John Osborne and Antoine Kosmicki EN/EL: Jean-Claude Guillaume, Philippe Orlandi , Nuno dos Santos EN/CV: Piero Valente EN/MEF-INT: Yvon Muttoni, Jean Pierre Corso

21 Back –up slides

22 PCs PC calibration racks Interferences with loading volume: PC: 52 mm PC calibration racks: 338mm UTA: 40 mm

23 Interferences with loading volume : UTA: 40 mm
On UJ561 wall side: dedicated racks with height of 1.8 m in the safe room and 2m elsewhere to stay below the cable trays of ‘forward detectors’(2.4m high). Safe room 1rst door at 21 mm from loading volume -> ok

24 20 m free between the last UTA control box and the PAD door

25 Safe room: 9 fire resisting doors (l. 1 m, h. 2.1 m) Structure in ‘siporex’ 15 cm thick (external dims. L. 16m, h. 2.4 m, d m)

26 Safety requirement for evacuation exit path
(documentation) - 79th SAFETY CO-ORDINATION MEETING FOR LHC EXPERIMENTS (19/10/2001) - Note by TIS/GS in October 2001 concerning the minimum requirements in terms of access / evacuation of an experimental area

27 Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

28 Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

29 Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

30 Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

31 Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

32 Cost /schedule estimate - breakdown
Safe room (options A & B): devis Ingo: 9 fire resisting doors (material + manpower)= 36 KCHF / max 9 days external contractor: the full safe room (structure + doors) - material: 27 KCHF - manpower: 30 KCHF - schedule: 2-3 weeks - delay for material delivery: 10 weeks Civil engineering (options A & B) Drilling 4 ducts between UJ56 and by-pass (diam. 350mm, l. 16.7m): ??? drilling apertures in the UJ561/by-pass wall (3 apertures h25cm, t. 60 cm or 1 aperture h.75cm, t. 60 cm): 30 KCHF /1-2 weeks EL activities: Control and DC cables: 1.5 MCHF (option A); 1.45 MCHF (option B); shift work +10% Puissance: 1.2 MCHF (options A & B), shift work +10% Total: 2.7 MCHF (option A); 2.65 MCHF (option B) ; shift work +10% Planning (see table): one shift: 17.5 months / 2 shifts: 12 months CV activities Budget (material + manpower)= KCHF planning (see table): cooling: demi water: 3 weeks -3 persons/1 shift; iced water: idem ventil: 3 weeks -3 persons/1 shift; elec: 3 weeks -3 persons/1 shift control: 1 week- 2 persons/1 shift

33 EN/EL planning tentative 9th October 2010
J. –C. Guillaume Given for the 1 shift option: total= 15 months Gain 2 months vs previous version (activities in the safe room in // control cable inst. In UL55 compatibility between CE, CV and EL activities ?=> planning