1 SR 25 – Hoosier Heartland Highway Lafayette to Logansport
97th Annual Purdue Road School March 8, 2011 / Stewart Center / Purdue University INDOT Project Management – Jim Earl, P.E.

2 Agenda Corridor Overview Overall Project Status Contract Letting Schedule Construction Change: Roundabout Current Construction Schedule

3 SR 25 – Hoosier Heartland Highway
Four Segments: 1  West Segment 2  Central Segment 3  East Segment 4  Logansport Segment Construction Schedule:  Began in Fall 2008  Complete by End of 2013 Lafayette to Logansport

4 Overall Project Status
Environmental Document complete Design Development on schedule Permitting Process on schedule Utility/Railroad Coordination ongoing Land Acquisition ongoing Over 300 parcels Critical Path – drives schedule Complete by Fall 2011 (depending on condemnations)

5 Overall Project Status
Most contracts funded from Major Moves Some contracts include federal funds One contract stimulus funded (ARRA) Total Estimated Cost approximately $450M All contracts to letting by Summer 2012

6 Contract Letting Schedule
Corridor has 24 total contracts 13 Road Contracts 8 Bridge Contracts 3 Environmental Mitigation Contracts 14 contracts have been let 8 more contracts letting in calendar year 2011 2 contracts letting in calendar year 2012 7 Road Contracts 3 Bridge Contracts Next contract letting 5/11/2011 Last contract letting 7/11/2012

7 IR Segment 2A Letting: 5/11/2011 Delphi

8 IR Segment 3B Letting: 5/11/2011 Burrows

9 IB Segment 4B Logansport Letting: 8/10/2011

10 IB Segment 4A Logansport Letting: 10/13/2011

11 IR Segment 2B Letting: 10/13/2011 Delphi

12 IB Segment 3B Letting: 11/16/2011 Burrows

13 IR Segment 2D Letting: 11/16/2011

14 IR Segment 2C Letting: 12/14/2011 Delphi

15 IR Segment 4A Logansport Letting: 03/07/2012

16 IR Segment 4B Logansport Letting: 07/11/2012

17 Construction Change: Roundabout
Location – just east of I-65 Interchange Original Plan (Traditional T-Intersection) Impacts on unsuitable soils Restrictions on commercial access Concerns for safety and convenience Absence of transition from rural to urban setting Revised Plan (Roundabout) Avoids unsuitable soils Loosens restrictions on commercial access Increases safety and convenience Provides transition from rural to urban setting

18 Original Plan (Traditional T-Intersection)
Construction Change: Roundabout Original Plan (Traditional T-Intersection)

19 Revised Plan (Roundabout)
Construction Change: Roundabout Revised Plan (Roundabout)

20 Construction Change: Roundabout
Minimal additional impact to right-of-way Public Information Meeting held on 11/8/2010 AI Approval received from FHWA on 3/2/2011 Revisions to construction plans Design review completed on 2/21/2011 Utility coordination complete by 3/31/2011 Adjustment to traffic maintenance plan Attempting to complete changes by April 2011 No impact to construction schedule

21 Current Construction Schedule
14 of the 24 contracts have been let 5 contracts are complete (4 are open to traffic) 9 contracts are under construction 10 remaining contracts to letting by Summer 2012 Highway from I-65 to US421  open to traffic by December 2012 Highway from Lafayette to Logansport  open to traffic by December 2013

22 Current Construction Schedule
SR25 HHH 2008 2009 2010 2011 2012 2013 1/1/2011 1st 2nd 3rd 4th IB-30837 Bridge - CR300N over NSRR and SR25 IB-30838 Bridge - CR500E over NSRR and SR25 IB-30839 Bridge - CR625E over NSRR and SR25 IB-30841 Bridge - CR900E over NSRR and SR25 IB-30842 Bridge - CR1000E over SR25 IR-30840 Phase 1A - from I65 to 0.1 m. E of CR750E SIR-30843 Phase 1B - from 0.1m. E of CR750E to 0.1m. W of NSRR IR-30844 Phase 1C - from 0.1m W of NSRR to 0.42m E of CL IR-30845 Phase 2A - from 0.42 m. E of CL to 0.15 m. E of US421 IR-30847 Phase 2B - from m. E of US421 to 0.6 m. S of Main St. IR-30848 Phase 2C - from 0.6 m. S of Main Street to 0.21 m. E of SR218 IR-30846 Phase 2D - from 0.21 m. E of SR218 to 0.48 m. E of CR400W IB-33804 Bridge - CR50W over NSRR and SR25 IR-30849 Phase 3A - from 0.48 m. E of CR400W to 0.11 m. E of CR100W IR-30850 Phase 3B - from 0.11 m. E of CR100W to 0.16 m. E of CR500S IR-30851 Phase 3C - from 0.16 m. E of CR500S to 0.61 m. E of CR325W IR-32543 Grading and Bridges for Phase 3C IB-30855 Bridge - SR25 over Old SR25 and NSRR IB-30854 Bridge - SR25 over Kokomo Pike IR-30853 Phase 4A m E of CR325W to 0.21m E of CR115W IR-30852 Phase 4B m. E of CR115W to US24/US35

23 Thank you! http://www.in.gov/indot/div/projects/sr25study/
97th Annual Purdue Road School March 8, 2011 / Stewart Center / Purdue University


Download ppt "SR 25 – Hoosier Heartland Highway Lafayette to Logansport"

Similar presentations


Ads by Google