1 Work Plan for IEEE 802.16m Standard & IMT-Advanced Submission
IEEE m-09/0019 Work Plan for IEEE m Standard & IMT-Advanced Submission

2 Updated TGm Work Plan IEEE Presentation Submission Template (Rev. 9) Document Number: IEEE m-09/0019 Date Submitted: Source: Jose Puthenkulam Voice: Intel Corporation (TGm Work Plan Adhoc Chair) Venue: Vancouver, BC, Canada Base Contribution: IEEE m Work Plan document (IEEE m-07/001r2) Purpose: Updated Work plan and timeline for TGm development Notice: This document does not represent the agreed views of the IEEE Working Group or any of its subgroups. It represents only the views of the participants listed in the “Source(s)” field above. It is offered as a basis for discussion. It is not binding on the contributor(s), who reserve(s) the right to add, amend or withdraw material contained herein. Release: The contributor grants a free, irrevocable license to the IEEE to incorporate material contained in this contribution, and any modifications thereof, in the creation of an IEEE Standards publication; to copyright in the IEEE’s name any IEEE Standards publication even though it may include portions of this contribution; and at the IEEE’s sole discretion to permit others to reproduce in whole or in part the resulting IEEE Standards publication. The contributor also acknowledges and accepts that this contribution may be made public by IEEE Patent Policy: The contributor is familiar with the IEEE-SA Patent Policy and Procedures: < and < Further information is located at < and < >.

3 Documents to be Developed in TGm
IEEE m-07/001r2 Documents to be Developed in TGm TGm will develop the following documents as part of m standardization process: System Requirements Document (SRD) A set of possible deployment scenarios and applications of the m standard. A set of performance targets and features that m compliantsystems shall meet or exceed. Evaluation Methodology Document (EMD) A complete set of parameters, models, and methodologies for the link-level and system-level simulations that allow fair evaluation/comparison of various technical proposals. Channels Models: A set of spatial channel model parameters are specified to characterize particular features of MIMO radio channels to be used for simulating technical proposals for the future m standard. System Description Document (SDD) Architecture and design of the m air interface amendment Captures the core technical concepts behind the features included in the amendment Will enable analysis and/or simulations for characterizing the coarse level performance benefits of the air interface in association with the Evaluation Methodology Document 802.16m amendment IMT-Advanced Proposal

4 TGm Timelines 3 2009-03-12 System Requirements Evaluation Methodology
2007 2008 2009 2010 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 IEEE Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec IEEE m System Requirements Sep ’07* Jan’08* Evaluation Methodology Amendment Ready for IMT-Adv evaluation System Description Nov ’07 Jan 09* IMT Advanced Proposal ITU based Updates Jan ’09 Sept ’09* Final Proposal Refinements 802.16m AmendmentŦ Nov ’08 May ’09 Nov ’09 May ’10 Working Doc Letter Ballot Sponsor Ballot Jun ’08 ITU-R IMT Advanced IMT.TECH Circular Letter Jun ’08 ITU based Updates Oct ’08 IMT.EVAL Jan’09 Oct ’09 Proposal Submission IMT.RADIO Jun ’10 Proposal Evaluation & Consensus Building Develop Recommendation ITU-R WP5D Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 3 *System Requirements and Evaluation Methodology, System Description, IMT-Advanced Proposal Documents may be further updated based on ITU output (shown by dotted lines). Ŧ m amendment is dependent on the Rev2 Project completion

5 Proposed Process for staging 802.16m Amendment feature development
PHY/MAC features required for IMT-Advanced for a working system P802.16m draft AWD SB WG LB Feature inclusion vote 50% 75% 75% 50% Amendment Feature development: -Feature developed as a RG contribution to TGm -Finally included only as a complete proposal, not a partial one -Develop as a self contained clause/subclause unless it is essential -Do not put place holders in Amendment till the feature is ready. (SDD will still have all features) -RGs should track Amendment development for consistency -WG LB or SB recirculation scope should allow feature inclusion Feature 1 Feature 2 Feature N Feature N+1 RG RG RG Feature WG Letter Ballot Next Project (New PAR) RG AWD = Amendment Working Doc RG = Rapporteur Group LB = Letter Ballot SB= Sponsor Ballot

6 Feature RG process for the Amendment
Feature Rapporteur Groups (RG) will develop contributions for adoption by TGm as per Process (in previous slide) RGs will be authorized/re-authorized at each TGm session TGm will provide final deadlines for completion of RG work. RG must start with a work plan based on TGm final deadlines. RGs must report progress at every TGm session RG final output contribution must be complete by TGm deadlines for adoption into the AWD/Draft RGs may meet during TGm sessions RGs can arrange teleconferences with 7 day advance notice RGs conduct straw polls for decision making RGs are open to all participants