2012 and 2014 Bond Update Citizens’ Bond Oversight Committee

Similar presentations


Presentation on theme: "2012 and 2014 Bond Update Citizens’ Bond Oversight Committee"— Presentation transcript:

1 2012 and 2014 Bond Update Citizens’ Bond Oversight Committee
September 20, 2017 Good evening in accordance with board policy CV (local) it is my pleasure to present the Bond Update

2 2012 Bond $40,300,000 allocated for Technology and Maintenance improvements August 31, Total P.O.’s issued: 33,396,074 or approximately 82.87% completed or in progress

3 2012 Bond Current Projects:
Stephen F. Austin Elementary - Roof Replacement

4 2014 Bond $175,000,000 allocated for new facilities and district wide improvements September 18, Total P.O.’s issued: 71,083,352 or approx 40.62% completed or in progress

5 2014 Bond Completed Projects: New Lanier Gymnasium - Complete
Polk and Griffith Classroom Additions - Complete Polk and Griffith New Gymnasiums - Complete Package A Summer Projects - Complete New Beutel Elementary- Phase 1- Complete

6 2014 Bond Current Projects:
New Beutel Elementary - Phase 2 - Construction Phase Freeport Elementary - Construction Phase Package B and CTE Projects - Construction Phase

7 New Beutel Elementary

8 New Beutel Elementary

9 Freeport Elementary School Opening August 2018

10 Freeport Elementary School Opening August 2018

11 Freeport Elementary School Opening August 2018

12 Package B/CTE Improvements
Summer 2017 Package B/CTE Improvements Polk Elementary School: Building exterior improvements, landscaping, marquee, canopy Create security vestibule Rasco Middle School: Building exterior improvements, landscaping, marquee Clute Intermediate School: New Tennis courts Clute Cottage Program: Demolish existing church. Cottage to remain Freeport Intermediate School: Building exterior improvements, landscaping, marquee, resurface track Brazoswood High School: CTE Program Improvements Brazosport High School: Black Box Theater - Lighting and Sound Rear Drive Turnaround and Parking Lighthouse Learning Center: Exterior improvements, fence, canopy, restripe basketball court Administration Building: Exterior signage Interior improvements, restrooms, boardroom, lobby Water piping replacement

13 Polk Elementary

14 Rasco Middle School

15 Clute Intermediate Tennis Courts

16 Freeport Intermediate

17 Brazoswood High School

18 Brazosport High School

19 Lighthouse Learning Center

20 Questions? THIS PRESENTATION IS A REPORT ONLY AND REQUIRES NO BOARD ACTION.