1 Colorado Plugfest Planning
August 15, 2016

2 Agenda Logistics Update Plugfest Planning Schedule Plugfest Scope
Plugfest Schedule (testing tracks) Next steps 2

3 Logistics Update Registration Page: Will operate under the same Rules of Engagement (ROE) Plugfest wiki page: Host Plugfest Page: Dates: December 5 – 9, 2016 Setup week: November 28 to December 2 (Monday – Friday) Location: UNH-IOL (Durham, NH, USA) 21 Madbury Road, Suite 100, Durham, NH USA 3

4 Plugfest Timeline 2016 2016 2016 Jul Aug Sep Oct Nov Dec Today 4
5 days Dec 5 - Dec 9 Plugfest 5 days Nov 28 - Dec 2 Setup / Install Registration Deadline Nov 19 2016 2016 Jul Aug Sep Oct Nov Dec 2016 Today Jul 18 Aug 15 Sep 26 Oct 24 Nov 21 Planning Call Planning Call Planning Call Planning Call Planning Call Sep 12 Oct 10 Nov 7 Planning Call Planning Call Planning Call 4

5 Plugfest Scope (work in progress)
OPNFV Turn-up: Unordered List Item Target Participants: Hardware Suppliers, Integrators, Installation Development Team(s). Testing Scope: Validation of installation process on different hardware platforms and configurations. Controller Integration: Target Participants: SDN Controllers and Network Infrastructure Providers Testing Scope: Validation of SDN controller integration, coupled with install process testing above, and control of physical hardware. VNF Applications: Target Participants: VNF suppliers Testing Scope: Provide underlying infrastructure and resources to help application provider verify the life cycle management on the OPNFV platform. Testing of the application is outside of the scope of this event. Dovetail Testing Provide Dovertail project with feedback on initial trial runs using their testing tool chain (assuming they have a release ready) 5

6 Plugfest Testing Schedule (proposed)
2016 Day 1 2 3 4 5 6 7 8 9 10 11 12 2016 Today 5 days Plugfest Setup Nov 28 - Dec 2 3 days OPNFV Turn-up Track Dec 5 - Dec 7 3 days SDN Controller Testing Track Dec 7 - Dec 9 5 days VNF Testing Track Dec 5 - Dec 9 2 days Dovetail Track Dec 8 - Dec 9 30 October 2014 OPNFV Confidential

7 Next Setups Participants to register online
Begin setting up Participant Wiki Pages To get access to private wiki pages, contact Lincoln Lavoie, Plan to finalize scope at September 26 planning call Last input / changes reviewed at the September 12 planning call 30 October 2014 OPNFV Confidential