Presentation is loading. Please wait.

Presentation is loading. Please wait.

Construction Project Management

Similar presentations


Presentation on theme: "Construction Project Management"— Presentation transcript:

1 Construction Project Management
Presentation of Construction Project Management Prepared By : Shareef Makhool , Abed Alsalam Kmail Ghadeer Jarooshi

2 What is the “Project”? A project is a temporary endeavor undertaken to create a unique product or service. Temporary : the project has an end date. Unique : the project's result is different from the results of other functions of the organization

3 What is the Project Management?
is the process of combining systems, techniques, and knowledge to complete a project within established goals of time, budget, and scope.

4 Who is the project Manager?
The person responsible for accomplishing the project objectives. is often a client representative and has to determine and implement the exact needs of the client .

5 Management Functions 1 Planning 2 Organizing 3 Leading 4 Controlling

6 Management Skills Conceptual Skills Human Skills Technical Skills

7 Construction Process Phases
Preconstruction phase Procurement phase Construction Close out

8 Our Graduation Project

9 Aneen Secondary Girls School
Project Overview Project Title: Aneen Secondary Girls School Location: Aneen village It is located to the west of Jenin city

10 This Project consists of main building
Project Overview This Project consists of main building and external yards with boundary walls on the land with total area of 500 m2 The main building is consisting of two floors with total area 540 meter square.

11 The project was divided in several units.
Assumptions The project was divided in several units. Working days are all days except Friday . The electrical and mechanical works will be done by sub contractors. Fixing the value (NIS) .

12 The structural method that used is : finishing the structural
Construction Method The structural method that used is : finishing the structural part for the ground floor and then starting on the above floor structural work , and in the same time starting with finishing works for the previous floor.

13 Work Breakdown Structure

14

15 Bill of Quantity Preparation
Calculations were made depending on Drawings to find the quantities and tabulating it.

16 The activity list entered in the (Primavera) program
and it’s dependency also were managed on this program. The dependency of the activities were constructed according to our method of construction.

17 Activities Durations The activity duration depends on the productivity of labors and machines. At this project the productivity taken from site engineers and contractors

18 the pricing for each element of unit was different from each other
the costing process based upon past experience for the contractor and some of labors. the pricing for each element of unit was different from each other some units were priced according to the area, others were priced according to number of units.

19 The profit percentage is 8% The over head percentage is 10%
Results Cost Results Total cost of project calculated using Primavera project is ( NIS) The profit percentage is 8% The over head percentage is 10% The actual cost of project was ( NIS)

20 actual work in the project was 310 calendar days.
Duration Results The total duration of the project as planed in this case study is 242 calendar days(208 working days). actual work in the project was 310 calendar days.

21 Justification of delay
Problem one In excavation work: they found that a rock layer below the clay one and they had to extend the time to excavate the rocks layers Problem two variation order: for the boundary wall and preparing the asphalt work for the external yard

22 Weather Risks 25working days (30 calendar days) added to the end of project depending on rainy days and the beginning and finishing of the activities affected by rainfall.

23 S-Curve cost control of this project made By using (S-Curve). For this project the S-Curve is done by plotting cumulative cost with time as shown.

24 S-curve

25 تم بحمد الله Thank you Happy to hear your questions


Download ppt "Construction Project Management"

Similar presentations


Ads by Google