CMS WEEK Sept. 24 Opening session CMS MUONS: Barrel Drift Tubes
Alignment RPC CSCs Fabrizio Gasparini
2
THE BARREL MU DRIFTCHAMBERS 4 concentric stations
CMS WEEK Sept 24 Opening session CMS Muon fabrizio THE BARREL MU DRIFTCHAMBERS 4 concentric stations 60 chambers each (MB4 70 ch.s) 680 SLs (MB1,2,3: 3 SL each,MB4 2 SL) wires Four assembly sites Aachen MB MB1/4 CIEMAT MB MB2/4 LNL MB MB3/4 Torino MB4 (with two tables)
3
STATUS OF ASSEMBLY SITES:
assembly begun in march 01 in CIEMAT,in May in Aachen and LNL CIEMAT : 12 SL assembled,first MB2 at CERN in June 3 ass. tables are operational Aachen : SL assembled (3 ass. tables operational) LNL : SL assembled (2 ass. tables operational, 2nd PHI in October) 22 chambers (66 SL) should be assembled by end 2001 30 SL MB2 (CIEMAT) / 18 SL MB1 (Aachen)/ 18 SL MB3 (LNL) the three sites shall reach the nominal speed by Jan 02 end production Feb (176 w.d./year) Torino shall begin to assemble MB 4 in September 02 CMS WEEK Sept 24 Opening session CMS Muon fabrizio
4
PLATES TORINO :plates for 22 Ch. end of June DUBNA : will do electrode deposition only all plates cut and Q. Checked in Torino deposition line shipped to D /8 line assembly in D. begins /9 first plates /11 end production fall 2003 BEAMS BOLOGNA : end beam prod. in Bo June 2001 I-beams assembled PROTVINO: 10000 beams assembled at mid July with one table : stable prod up to 220/day ( nominal 160/day) second line at IHEP /10 prod. with 2 lines at IHEP (>= 320 I/g) /02 full lot fall 2003
5
Assembling first MB3 in Legnaro
6
SL construction - 2 working tables
7
Aachen
8
Aachen
9
CIEMAT
10
CIEMAT
11
TORINO
12
DUBNA
13
easy to go to 9 days /three SL
What we learnt: 15 days were taken in CIEMAT to assemble three SL of a MB2 chamber in parallel on the three tables 10 w.d. were spent at LNL to assemble 2 SL in parallel on 2 tables (Sept.) easy to go to 9 days /three SL No,or negligible, problem with gas tightness and HV (18 SL tested, 5400 wires) Still not a large experience on the time needed for the full test of a SL : however the first 3 SL assembled in LNL could be set to the nominal voltages after two days of conditioning. ( 9 days are planned for the SL test: gas tight./HV/rates) CMS WEEK Sept 24 Opening session CMS Muon fabrizio
14
theta1 and phi1 were the training SLs
Baseline theta1 and phi1 were the training SLs CMS WEEK Sept 24 Opening session CMS Muon fabrizio
15
THE CMS ALIGNMENT SYSTEM
Basic elements 4 indipendent Link systems (A,B,C,D) relate couples of local rigid structures in the MU and in the Tracker. The 4 Links are “bolted” together: via the Tracker Internal System via the Endcap Links and Radial Lines Alignment scheme A A B D C The chambers are located with respect to the local rigid structures (muon MABs & tracker Align.”Wheels”) The full system should be able to give a starting position of the chambers within 500/100 micron (MU/Tracker) and monitor relative displacements of 100/20 micron (20 microrad misalignment MU/Tracker) D
16
MAB Prototype (Barrel Alignment)
CERN: Design and specs. INEGI (Portugal): Prototype(s) fabrication Drawings for the pre-production prototype are ready. Material is ordered and partially delivered (all available by end of Sept.) Assembly table to be built (and be completed by mid Nov.) Prototype ready for test by beginning of December. CMS WEEK Sept 24 Opening session CMS Muon fabrizio
17
Layout of the Tracker Alignment System and Link with the Muon Alignment
Design of the 2D Si sensor 6x2 Laser beams (ray 1) provides the linking with the Muon System CMS WEEK Sept 24 Opening session CMS Muon fabrizio
18
Performance/ISR test The major test was performed at ISR:
good results for LINK and Endcap more problematic for Barrel because of the lack of a real MAB, the Barrel need the Endcaps Link Lines to align the MABs of the active planes.
19
For ME2, 3 layers... 1) Mapping the layer with 3 SLMs (6 chambers per layer). 2) Alignment by tracks for overlapping chambers (3-5 strips overlap)
20
In summary: The Barrel and Endcap systems are well in track. No major technical problem is foreseen. Schedule looks feasible. Link with the Tracker has been integrated within the TK internal alignment design. Technical work, including thermal transition and integration issues, is in progress. CMS WEEK Sept 24 Opening session CMS Muon fabrizio
21
RPC CMS WEEK Sept 24 Opening session CMS Muon fabrizio
22
CMS WEEK Sept 24 Opening session CMS Muon fabrizio
23
CMS WEEK Sept 24 Opening session CMS Muon fabrizio Former Trigger
24
CMS WEEK Sept 24 Opening session CMS Muon
fabrizio
25
CMS WEEK Sept 24 Opening session CMS Muon fabrizio
26
CMS WEEK Sept 24 Opening session CMS Muon fabrizio