Signal Improvement Project COMMUNITY DEVELOPMENT DEPARTMENT

Similar presentations


Presentation on theme: "Signal Improvement Project COMMUNITY DEVELOPMENT DEPARTMENT"— Presentation transcript:

1 Signal Improvement Project COMMUNITY DEVELOPMENT DEPARTMENT
Phase 2 COMMUNITY DEVELOPMENT DEPARTMENT

2 Presentation Objective
To provide City Council with implementation costs for Phase 2 of the Signal Optimization Project and receive City Council approval.

3 Strategic Action Plan Objective 1.1: To enhance infrastructure in order to maintain quality neighborhoods and business districts Objective 1.2: To assess the need to expand infrastructure for sustainable growth Strategy 1.2.2: Coordinate facility capacity upgrades to meet the City’s growth needs appropriately Objective 5.2: Enhance safety measures throughout the community Strategy 5.2.2: Continue to enhance safety improvements at intersections and along roadways

4 Project Overview The purpose of the project is to maximize roadway capacity and make them safer. City is taking a phased approach for implementation of the Advanced Traffic Management System (ATMS) Phase 1: Integrated 12 intersections - Completed Phase 2: Integrating 22 additional intersections (FY 2017)

5 Project Overview Phase 1 Work Performed:
Purchase & installation of ATMS Software and Hardware components Fiber connection at 34 intersections Installation of CCTV cameras and communications switches at 12 intersections Creation of a small scale Traffic Management Center Purchasing Testing Equipment for traffic signal components

6 Intersection Corridor Integration
FY 2017 Belle Terre Pkwy – Pine Lake Pkwy to Palm Coast Pkwy (WB) - (5) Belle Terre Pkwy – East Hampton Blvd to Whiteview Pkwy - (4) SR 100 – Belle Terre Pkwy to I-95 - (6) Palm Coast Pkwy – Pine Lakes Pkwy to Corporate Drive & Clubhouse Drive to Palm Harbor Pkwy - (7) A majority of controllers are already upgraded.

7 Recommendations Approve the following expenditures for Phase 2
Installation of CCTV cameras and communications switches at 22 intersections - $119,094.00 Purchase of two (2) new traffic cabinets - $28,100 Fiber connection at 10 intersections - $52,355.60 Total Expenditures: $199,540.60 Remaining FY 2017 Budget: $296,910.98 A majority of controllers are already upgraded.

8 Next Steps FY 2017: Implement Phase 2 as approved by City Council
FY 2018 – FY 2019: Incorporate future phases in 5 year CIP Phase 3: Integrating 13 additional intersections Phase 4: TBD as fiber network is expanded A majority of controllers are already upgraded.

9 Questions? Palm Coast Pkwy includes Old Kings Rd and Cypress Point Pkwy