1 EYETS LHC 2016/2017 Works EN/EL/CF
A. Gonzalez & G. Girardot 11 octobre 2016

2 Agenda 1. Copper cabling 2. Optical fibers 3. Support needed 4. Conclusion 20/10/2015 Coordination meeting

3 1. Cabling campaigns Intervention overview
LHC1G-YEB1 LHC1D-YEB1 LHC1S-YEB1 LHC2G-YEB1 LHC2D-YEB1 LHC3P-YEB1 LHC3S-YEB1 LHC4S-YEB1 LHC5G-YEB1 LHC5D-YEB1 LHC5S-YEB1 LHC6S-YEB1 LHC7G-YEB1 LHC7D-YEB1 LHC7P-YEB1 LHC7S-YEB1 LHC8G-YEB1 LHC8D-YEB1 18 cabling campaigns 275 cables / 21 km 11/10/2016 EYETS – Works EN-EL-FC

4 1. Cabling campaigns – Pt1 (Underground)
Constraints: Liquid Helium in QRL => authorization for the access to the cable trays needed Electrical lockout Installation of scaffolding over the magnets in UJ14 Opening cable passages in UJ14 / UJ16 Pulling fragile cables for AFP activity Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA173001 UL16 ?? EYETS - SEISMIC NETWORK EN-MME M. CABON 4 120 LHC1D-YEB1 C213AHA176001 UJ14 EYETS - CABLAGE BPM AFP.6L1 BE-BI C. BOCCARD 220 LHC1G-YEB1 Length of cables ≈ 350m Estimated duration: Pulling =3d + 3d Connecting + tests =2d + 2d Works Underground 11/10/2016 EYETS – Works EN-EL-FC

5 1. Cabling campaigns – Pt1 (Surface)
Constraints: Electrical lockout Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA163001 SR1 10357 EYETS - CABLAGE NOUVEAU RPADO - SR1 TE-EPC H. THIESEN 11 300 LHC1S-YEB1 C213AHA168001 EYETS - FGC-ETHER FOR LHC - SR1 J. GOMEZ COSTA 1 30 Length of cables ≈ 330m Estimated duration: Pulling =1.5w Connecting + tests =1.5w Works Surface 11/10/2016 EYETS – Works EN-EL-FC

6 1. Cabling campaigns – Pt2 (Underground)
Constraints: Liquid Helium in QRL => authorization for the access to the cable trays needed Electrical lockout Opening cable passages between UA and RA Pulled cable through all the arc 1-2 Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA174001 UA27 10890 EYETS - CABLAGE VACUUM – TE-VSC JP. BOIVIN 1 70 LHC2D-YEB1 C213AHA165001 UA23 11241 EYETS - TDI INTERFEROMETER RESET - EN-STI J. LENDARO 47 LHC2G-YEB1 C213AHA172001 ARC1-2 ?? EYETS - REMPLACEMENT LIAISONS SAREP THERMOSWI TE-MSC P. DENIS 5500 Length of cables ≈ 5617m Estimated duration: Pulling =1d + 1.5w Connecting + tests =2d + 3d Works Underground 11/10/2016 EYETS – Works EN-EL-FC

7 1. Cabling campaigns – Pt3 (Underground)
Constraints: Electrical lockout Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA  UJ33 ?? EYETS - MODIFICATION CABLAGE COLLIMATION UJ33 EN-STI J. LENDARO 54 850 LHC3P-YEB1 Length of cables ≈ 850m Estimated duration: Pulling =1w Connecting + tests = 2w Works Underground 11/10/2016 EYETS – Works EN-EL-FC

8 1. Cabling campaigns – Pt3 (Surface)
Constraints: Electrical lockout Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA163002 SR3 10357 EYETS - CABLAGE NOUVEAU RPADO - SR3 TE-EPC H. THIESEN 11 300 LHC3S-YEB1 C213AHA168002 EYETS - FGC-ETHER FOR LHC - SR3 J. GOMEZ COSTA 1 30 Length of cables ≈ 330m Estimated duration: Pulling =1.5w Connecting + tests =1.5w Works Surface 11/10/2016 EYETS – Works EN-EL-FC

9 1. Cabling campaigns – Pt4 (Surface)
Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA167001 SH4 ?? EYETS - CABLAGE 24VDC REDONDANT P4 - TE-CRG B. IVENS 4 205 LHC4S-YEB1 Length of cables ≈ 205m Estimated duration: Pulling =3d Connecting + tests =4d Works Surface 11/10/2016 EYETS – Works EN-EL-FC

10 1. Cabling campaigns – Pt5 (Underground)
Constraints: Liquid Helium in QRL => authorization for the access to the cable trays needed Electrical lockout Opening cable passages between UL56 et USC55 Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA161003 R571 10906 EYETS - DEPLACEMENT CABLE DC TCTW.A4R5 BE-BI C. BOCCARD LHC5D-YEB1 C213AHA161001 R532 EYETS - BPM POUR TCTW.4L5.B2 6 990 LHC5G-YEB1 C213AHA161002 EYETS - DEPLACEMENT CABLE DC TCTW.A4L5 C213AHA166001 USC55 EYETS - SIGNAUX TENSION TCTW P5 EN-STI J. LENDARO 3 60 C213AHA173002 UP53 ?? EYETS - SEISMIC NETWORK - EN-MME M. CABON 4 120 Length of cables ≈ 1170m Estimated duration: Pulling =1w + 1.5w Connecting + tests = 4d + 1w Works Underground 11/10/2016 EYETS – Works EN-EL-FC

11 1. Cabling campaigns – Pt5 (Surface)
Constraints: Electrical lockout Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA163003 SE5 10357 EYETS - CABLAGE NOUVEAU RPADO - SE5 TE-EPC H. THIESEN 11 300 LHC5S-YEB1 C213AHA168003 EYETS - FGC-ETHER FOR LHC - SE5 J. GOMEZ COSTA 1 30 Length of cables ≈ 330m Estimated duration: Pulling =1.5w Connecting + tests =1.5w Works Surface 11/10/2016 EYETS – Works EN-EL-FC

12 1. Cabling campaigns – Pt6 (Surface)
Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA167002 SH6 ?? EYETS - CABLAGE 24VDC REDONDANT P6 - TE-CRG B. IVENS 4 205 LHC6S-YEB1 Length of cables ≈ 205m Estimated duration: Pulling =3d Connecting + tests =4d Works Surface 11/10/2016 EYETS – Works EN-EL-FC

13 1. Cabling campaigns – Pt7 (Underground)
Length of cables ≈ 8171m Estimated duration: Pulling =1w + 3d + 4d Connecting + tests = 1w + 1w +1w Works Underground Constraints: RP area Electrical lockout Opening cable passages in UJ76 Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA169001 RR77 10538 EYETS - BPM COLLIMATEURS PT7 BE-BI C. BOCCARD 3 900 LHC7D-YEB1 C213AHA164002 R771 10541 EYETS - CABLAGE UA9 EN-STI J. LENDARO 24 1590 C213AHA174004 10890 EYETS - CABLAGE VACUUM TE-VSC JP. BOIVIN 14 1208 C213AHA169002 UJ76 1 250 LHC7G-YEB1 C213AHA174003 R74 9 1150 C213AHA164001 TZ76 15 830 LHC7P-YEB1 C213AHA174002 12 2220 C213AHA187001 ?? EYETS - BIC COLLIMATEUR CRYSTAL TE-MPE C. MARTIN 23 11/10/2016 EYETS – Works EN-EL-FC

14 1. Cabling campaigns – Pt7 (Surface)
Constraints: Electrical lockout Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA163004 SR7 10357 EYETS - CABLAGE NOUVEAU RPADO - SR7 TE-EPC H. THIESEN 11 300 LHC7S-YEB1 C213AHA168004 EYETS - FGC-ETHER FOR LHC - SR7 J. GOMEZ COSTA 1 30 Length of cables ≈ 330m Estimated duration: Pulling =1.5w Connecting + tests =1.5w Works Surface 11/10/2016 EYETS – Works EN-EL-FC

15 1. Cabling campaigns – Pt8 Constraints:
Liquid Helium in QRL => authorization for the access to the cable trays needed Electrical lockout Opening cable passages between UA and RA Affaire Code Building PLAN Title Group User Nb. cables Length (m) Cabling campaign C213AHA165002 UA87 11241 EYETS - TDI INTERFEROMETER RESET EN-STI J. LENDARO 1 158 LHC8D-YEB1 C213AHA174004 10890 EYETS - CABLAGE VACUUM TE-VSC JP. BOIVIN 70 C213AHA186002 UL86 ?? EYETS - CABLAGE P8 QURCA/B TE-CRG B. IVENS 26 1230 C213AHA186001 UL84 34 1155 LHC8G-YEB1 Length of cables ≈ 2613m Estimated duration: Pulling =1w + 3d Connecting + tests = 1w + 1w Works Underground 11/10/2016 EYETS – Works EN-EL-FC

16 2. Optical Fibre – LHC activities
Location Works LHC Survey BIS fibres (5 weeks) US’s, UJ's, UA’s, TZ76, USC55 Blowing O.F. cables over existing duct infrastructure US’s and UJ’s to UA’s Local distribution (Patchcables installation) UA’s + patching and measurements LHC Cryo redundancy LSS and QUI fibres (5 weeks) US’s, UJ's, UA’s, UL’s,TZ76 Local distribution + Blowing O.F. cables US’s and UJ’s to UA’s, UL’s Patching and measurements Fibres for LUA9 P7R (1 week) TZ76, UJ76, R771 Blowing O.F. cables over existing duct infrastructure TZ76-UJ76-R771 + patching and measurements HL-LHC Relocation fibre cables P1-P1.8 (2.5 weeks ) SR1, SM18 Systems disconnection and relocation over the new O.F. cables Replacement of RSF cables (3.5 weeks) (acces by LHC) TI2, TI8 Constraints: Electrical lockout in UA’s Limited working coactivity near blowing activities (2, 3 hours interventions) No more than 2 works at the same time, draft planning will be proposed to EN-ACE 11/10/2016 EYETS – Works EN-EL-FC

17 2. Optical Fibre – LHC activities
Location Registration and inspections Optical Fibre Database UA27, US's ,UJ's Registration /verification labeling of Cable Hardware Duct/microduct registration Verification radiation induced attenuation progression US’s, UJ's Optical fibre measurements O.F. monitoring system UA27, US's ,UJ's, Surface Patching and Optical fibre measurements Constraints: No working constraints (inspections in front of the racks, visual inspection of cable trays) 11/10/2016 EYETS – Works EN-EL-FC

18 3. Support needed Departmental Safety Officer (DSO): EN/ACE EN/EA
Authorization for access to cable tray EN/ACE Detail schedule => the 2 cable campaigns of the same point in parallel (if possible) VIC Electrical lockout EN/EA Scaffolding, … EN/HE 50/60 drums to transport and handle HSE/RP TE/CRG Cryo lockout TE/EPC 20/10/2015 Coordination meeting G. Girardot

19 4. Conclusion Activities on all LHC sites.
The presence of liquid helium in the QRL increase the constraints and risks for cable works. Access constraints during cabling. Many fireproof closure will be open. Many other groups will be involved in our interventions. All new requests will be subject to the approval of the coordination EN/ACE and EN/EL (resources) 20/10/2015 Coordination meeting G. Girardot

20 Thank you for your attention !