Presentation is loading. Please wait.

Presentation is loading. Please wait.

Dave McComas on behalf of the ISʘIS Team

Similar presentations


Presentation on theme: "Dave McComas on behalf of the ISʘIS Team"— Presentation transcript:

1 Dave McComas on behalf of the ISʘIS Team
introduction SPP Science Working Group in D.C. at the Smithsonian

2 Outline ISʘIS Team Hardware Status Calibration Results Summary

3 ISʘIS Team

4 Hardware Status – EPI-Lo

5 EPI-Lo Status – FM Event Board
Flight FPGA burned and installed Completed FM acceptance testing Ready for integration into the top assembly

6 EPI-Lo Status – FM Power Board
Completed FM acceptance testing Removing excess parylene coating

7 EPI-Lo Status – Anode & Energy Bds
Four FM Anode Boards complete, acceptance tested, and ready for next assembly Two FM Spare Anodes built Fifteen FM Energy Board / SSD Assemblies complete, acceptance tested, and ready for next assembly (8 FM and 7 FM Spare) EPI-Lo FM Anode Board, back side EPI-Lo FM Energy Boards, back side

8 EPI-Lo Status – FM Sensor Wedges
2 FM Spare Wedges Assembled and Calibrated at LBNL 3 FM Wedges Assembled and vacuum-tested with sources 11 upper wedge subassemblies complete 9 MCP assemblies complete and tested

9 EPI-Lo Calibration at LBNL
Completed Calibration of 2 FM Spare Sensor Wedges at LBNL in March 2016

10 Hardware Status – EPI-Hi

11 EPI-Hi Status – Electronics Boards
Ebox assembled with all FM boards LVPS, Bias Supply, DPU, LET1, LET2, and HET Boards All FM boards populated with FM parts (except FPGA) FM Flex-Circuits to Telescopes

12 EPI-Hi – FM Telescopes All FM Telescopes fabricated
Minor mechanical updates incorporated into LET1 & LET2 and being completed on HET telescope bodies Progress made on improved screening to find detector wire-bonds issues (breakage on one extreme, sagging on the other) EMI closeout of cabling to telescopes is behind schedule but parts should be complete mid-October

13 EPI-Hi Team – TAMU Calibration
Performed Calibration at Texas A&M Test Dates: June 14-18, 2016 K500 Cyclotron: N14, Ne20, Ar40 and Kr78 beams 56 hours beam time LET1 A, HET A and LET2 tested K150 Cyclotron: Proton beam 13 hours beam time HET A and LET1 A tested 14 ISʘIS team members supported the test at TAMU over a 13 day period. Many other involved with pre-test preparations. 24/7 coverage June 13-18

14 EPI-Hi Team – MSU Calibration
Performed Calibration at Michigan State University Test Dates: July 19-21, 2016 K1200 Cyclotron S2 Vault – SEE line Ni58 beam, 160 MeV/nucleon 44 hours beam time LET1 A, LET1 B, HET A and LET2 tested 14 ISʘIS team members supported the test at MSU over an 8-day period Many others involved with pre-test preparations. 24/7 coverage July 19-21

15 Summary Almost all ISʘIS FM hardware is complete
Integration and Testing has gone well Extensive calibrations performed on FM hardware to ensure performance requirements are met Full FM Integration and Testing expected to complete in October 2016 Pre Environmental Reviews being scheduled for October 2016 Projected delivery to spacecraft in January 2017


Download ppt "Dave McComas on behalf of the ISʘIS Team"

Similar presentations


Ads by Google