1 Swamp Creek: Culvert Replacements
Sokaogon Chippewa Community Roman Ferdinand Tribal Water Workshop – Mille Lacs October 9, 2014

2 Swamp Creek: Culvert Replacements October, 2014
Project Locations Problem Statement and Confirmation Design Permits Construction Side Note

3 Project Location:

4 Project Location: Swamp Creek – Class II Trout Stream, ERW and ORW; ONRW Wolf River – Class II Trout Stream, ORW, NWSR

5 Rice Lake:

6 Stream Crossings:

7 How it fits: ASSESSMENT RESTORATION PROTECTION

8 Problem Statement: Perched culverts
Backwater issues (temperature, inhibited groundwater discharge, siltation, erosion, etc.) Fish habitat modifications (spawning, passage, etc.)

9 Problem Confirmation:
Topographic survey (stream, floodplain, stream crossings) HEC-RAS modeling ( Contracted to Inter-Fluve, Inc. ( ) Length – 6 miles, simulate 3 crossings Cost: $25,000 Funding: WTCAC (Small Projects grant)

10 HEC-RAS: USACE Channel geometry Flow and stage data
Calibrate the model to real observations Predictive scenarios

11

12

13 Design: Site specific topographic survey
Soil testing (bearing capacity) Three design alternatives with cost estimates Preferred alternative – detailed design and material/construction cost estimate Construction bid package, proposal review and contractor recommendation Cost: $32,000 (up to $62,000) Funding: EPA CWA 319

14 Preliminary Estimated Cost ($) Delivery Lead Time (weeks)
Opening Width Material Type Preliminary Estimated Cost ($) Delivery Lead Time (weeks) Materials* Installation Total 20' Clearspan Aluminum Box $ ,600.00 $ ,020.00 $ ,620.00 4 - 5 Concrete Box $ ,700.00 $ ,390.00 $ ,090.00 6 - 8 30' Clearspan Truss Bridge $ ,000.00 $ ,000.00 $ ,000.00 $ ,700.00 $ ,190.00 $ ,890.00 $ ,300.00 $ ,210.00 $ ,510.00

15 Permits: State of Wisconsin U.S. Army Corps of Engineers
Combined Waterway Protection General Permit Work within the existing stream crossing footprint – no wetland delineation needed. Review process: 30 – 60 days

16 Construction: Preferred construction inspection by design engineer
Billed on time/expenses not to exceed Cost: Materials/Installation $110, $250,000 per site Inspection $ 27,000 (up to $ 41,000) estimate of 1 week per site Funding: GLRI (through BIA) EPA CWA 319 FWS National Fish Passage Program Private

17 Precipitation Frequency
Finally – Side Note! Precipitation Frequency 2 year 24 hrs 100 years 24 hrs…….

18 Precipitation Frequency
Used in engineering design: Flood events (steam crossings) Stormwater runoff storage (detention or seepage ponds) SCC – 24 hour 100 years storm event – 6.5 inches

19

20 NOAA Atlas 14 (2013)