Presentation is loading. Please wait.

Presentation is loading. Please wait.

City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010.

Similar presentations


Presentation on theme: "City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010."— Presentation transcript:

1 City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010

2 Agenda Recent Flood Fight Strategy (2009/2010) Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk Management Projects 2010/11 Proposed City Flood Risk Management Projects Assessment of Flood Risk Assessment of Flood Risk Overview of Project Overview of Project Project Schedule / Financing Project Schedule / Financing Meadow Creek Flood Risk Management

3 Agenda Recent Flood Fight Strategy (2009/2010) Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk Management Projects 2010/11 Proposed City Flood Risk Management Projects Assessment of Flood Risk Assessment of Flood Risk Overview of Project Overview of Project Project Schedule / Financing Project Schedule / Financing Meadow Creek Flood Risk Management

4 2009 Spring Flood – Meadow Creek Drive

5 2009 Spring Flood – Meadow Creek Area

6 2009 Flood Information Probabilistic Stage Predictions as of 3/11/2009 Probabilistic Stage Predictions as of 3/11/2009 Actual Crest 3/28/2009 Actual Crest 3/28/2009 Approx. 50% Chance of 36.0-ft and 10% Chance of 38.5-ft 6 Approx. 50% Chance of 38-ft 10% Chance of 40-ft Actual Crest 40.8- ft

7 2010 Flood Information Probabilistic Stage Predictions as of 3/9/2010 Probabilistic Stage Predictions as of 3/9/2010 Actual Crest – 3/21/2010 Actual Crest – 3/21/2010 Approx. 50% Chance of 36.0-ft and 10% Chance of 38.5-ft 7 Approx. 50% Chance of 38.0-ft and 10% Chance of 42.7-ft Actual Crest 36.99-ft

8 Current Flood Fight Strategy

9 2009 Flood Fight - Meadow Creek Drive

10 Sandbagging Effort

11 Agenda Recent Flood Fight Strategy (2009/2010) Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk Management Projects 2010/11 Proposed City Flood Risk Management Projects Assessment of Flood Risk Assessment of Flood Risk Overview of Project Overview of Project Project Schedule / Financing Project Schedule / Financing Meadow Creek Flood Risk Management

12 Potential Flood Risk Reduction Projects. Total Est. Cost $35 Million

13 Agenda Recent Flood Fight Strategy (2009/2010) Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk Management Projects 2010/11 Proposed City Flood Risk Management Projects Assessment of Flood Risk Assessment of Flood Risk Overview of Project Overview of Project Project Schedule / Financing Project Schedule / Financing Meadow Creek Flood Risk Management

14 Assessment of Flood Risk River Stage 37.0ft Insert Map Sandbag Estimate – 7,600

15 Assessment of Flood Risk River Stage 38.0ft Insert Map Sandbag Estimate – 32,800

16 Assessment of Flood Risk River Stage 39.0ft Insert Map Sandbag Estimate – 79,300

17 Assessment of Flood Risk River Stage 40.0ft Insert Map Sandbag Estimate – 138,300

18 Assessment of Flood Risk River Stage 41.0ft Insert Map Sandbag Estimate – 221,100

19 Assessment of Flood Risk River Stage 42.0ft Insert Map Sandbag Estimate – 314,900

20 Assessment of Flood Risk River Stage 42.5ft Insert Map FEMA 100-yr Flood Stage 39.5 USACE Recent Evaluation – 1% Flood in Fargo is 42.4? Sandbag Estimate – 375,000

21 Agenda Recent Flood Fight Strategy (2009/2010) Recent Flood Fight Strategy (2009/2010) Assessment of Flood Risk Assessment of Flood Risk Overview of Project Overview of Project Project Schedule / Financing Project Schedule / Financing Meadow Creek Flood Risk Management

22 Bike Path (East and West) Permanent Storm Water Pond Channel Relocation Low Flow Storm Sewer Extension Low Flow Storm Sewer Extension and Channel Re-grade Completion of Timberline Levee Earthen Flood Control Levees to RS 43+1ft

23

24

25 VISUALIZATION

26 Agenda Recent Flood Fight Strategy (2009/2010) Recent Flood Fight Strategy (2009/2010) Assessment of Flood Risk Assessment of Flood Risk Overview of Project Overview of Project Project Schedule / Financing Project Schedule / Financing Meadow Creek Flood Risk Management

27 Preliminary Construction Cost Estimate: Preliminary Construction Cost Estimate: –Approximately $2.0M Preliminary Funding Plan Preliminary Funding Plan –City of Fargo Flood Control Sales Tax –ND State Water Commission (50%) –Potential Special Assessments Project Schedule / Financing

28 Conceptual Planning Conceptual Planning Preliminary Geotechnical Review Preliminary Geotechnical Review Preliminary Design Preliminary Design City/Park District Meetings City/Park District Meetings Public Informational Meeting (tonight) Public Informational Meeting (tonight) Detailed Geotechnical Analysis Detailed Geotechnical Analysis Hydraulic Analysis / Impacts Hydraulic Analysis / Impacts Final Plans / Specifications / Cost Estimates Final Plans / Specifications / Cost Estimates Permitting Permitting Construction Bidding Construction Bidding Anticipated Construction Begins (Fall 2010) Anticipated Construction Begins (Fall 2010) Project Schedule / Financing

29 Comment Form

30 Questions / Discussion www.cityoffargo.com\Engineering Meadow Creek Area Flood Risk Management – Project 5944


Download ppt "City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010."

Similar presentations


Ads by Google