API 17J, B, K, L1, L2 Flexible Pipe Standardization
API C2 / SC17: Winter Status Report. Houston, TX Reporting Chair Krassy Doynov, Ph.D., ExxonMobil Production Company
2
Scope of Work and Status
STANDARD NAME PUBLISHED STATUS Recommended practice for flexible pipe API RP 17B 2-May-2014 to be updated 2018 ISO 19-Sep-2006 HOLD Specification for Unbonded Flexible Pipe API Spec 17J 4th edition Specification for Bonded Flexible Pipe API Spec 17K 1-Nov-2005 2Q 2017 3rd edition ISO 1-Oct-2005 Specification for flexible pipe ancillary equipment API Spec 17L1 23-Nov-2015 to be updated 2019 ISO Recommended practice for flexible pipe ancillary equipment API RP 17L2 5-March-2013 ISO The Ageing of PA-11 in Flexible Pipes API 17TR2 1-Jun-2003 to be updated 2018/2019
3
Status of JIP for the update of API 17TR2 “The Ageing of PA-11 in Flexible Pipes”
SOW is to provide Guidelines for Qualification of Polyamides (PA11, PA12, …) in Flexible Pipes based on collecting field experience and integrity issues, and standardizing test procedures and acceptance criteria after performing round robin tests to ensure reproducibility. Steering Committee meeting held on November 8th and 9th, 2016. Round robin tests on PA11 and PA12 at different test labs completed. Test scatter is being compared, and results - analyzed for reproducibility. 9 JIP Participants: ExxonMobil, GE Oil&Gas, Evonik, NOV Flexibles, Woodside, PetroBras, Total, Arkema, 4Subsea. JIP Manager – 4Subsea Norway. K. Doynov will submit SRRR form for revision to 17TR2, upon JIP completion in 2017/2018.
4
Status of API 17K (ISO 13628-10 - on hold)
API 17K (upcoming 3rd edition) ballot opened on Dec-7, 2016 and will close on Feb-1, 2017. Ballot was delayed with 4-to-5 months due to conducting material- and mid-scale testing to verify FAT test acceptance criterion for seawater intake bonded pipes – a new application added to API 17K. API ballot comments to be addressed in 2Q17; and the new 3rd edition published in 3Q17. Project Summary: Duration – 2.5 years (January May 2017); 5 F2F meetings of FPTG = 3 * Houston + 1 * Oslo/Norway + 1 * Pau/France; F2F meeting attendance – between 13 and 22 SMEs; Participating companies – up to 28; Participating SMEs – up to 45; Project Champion: Gergely Szekely of ContiTech: leading manufacturing task group, testing, and providing organizational and technical support. API 17K updates based on synergies with the latest revisions of API 17J, 17B, 17L1, 17L2 and pulling Industry lessons learned since 2005: Pressure and temperature definitions, System design philosophy, load classes, load conditions, design load effects, design methodology verification, pipe and end fitting design acceptance criteria, storage and operating bend radii; Material qualification and matching testing standards – with new details on non-metallic reinforcement materials and elastomers; Manufacturing control updates; Repair procedures validated with test data; Documentation requirements specified; FAT: new tests and test procedure updates for SWI application and bonded pipe constructions with non-metallic reinforcement components; Purchasing guidelines and pipe data sheet update.
5
Status of API 17L1, L2 (ISO/FDIS 13628-16,17 – on hold)
The revision of API 17L1 and L2 is planned to be kicked off in 2H17 – after publishing the 3rd edition of API 17K. The SOW will to address: 135 Monogram comments (un-auditable areas), Technip’s 31 technical comments received in 2014, and recent Industry Lessons Learned between 2012 and 2016. Anticipated Project duration – 2 years.
6
Status of API 17J & 17B Revision (ISO 13628-2 &11 – on hold)
Update API 17B with edits identified during the 17K Project to align with new API 17K. Estimated duration is 3-6 months. NOTE: 17B is the RP supporting both the 17J Spec and 17K Spec
7
MEMBERSHIP: 17K Flexible Pipe Task Group
Wayne Morris 3M 2 Roger Hagen 3 Svein Are Løtveit 4Subsea 4 Nils Gunnar Viko 5 Christoffer Nilsen-Aas 6 Roberto Biollo BASSI OFFSHORE 7 Emilien Rulence Bureau Veritas Marine & Offshore 8 Francois Migeon 9 Aymeric David 10 Gergely Szekely ContiTech Rubber 11 Tibor Nagy 12 István Grepaly 13 Jorge Suarez DNV-GL 14 Kam Zandiyeh Dunlop Oil & Marine 15 Jo Wiggers 16 Don Johnson ETA 17 Krassy Doynov ExxonMobil 18 Richard Shepherd 19 David Barnard Clearwater FPC 20 Erik Bendiksen NOV Flexibles 21 Trond Sundby Petroleum Safety Authority 22 Langøy Morten Andre 23 Francois-Regis Pionetti 13 SAIPEM 24 Giaccobi Stephane 25 Cyrille Mengeot 26 Sunil Dutt 14 Technip 27 Jesus Arrieche 28 Ludovic Assier 15 TOTAL 29 Vincent Lagarrigue 16 Trelleborg Industrie SAS 30 Jean-Noel Vincent David Ponchon 31 Remi Morvan 17 Wood Group Kenny 32 Shankar Bhat 18 INTECSEA 33 Naiquan Ye 19 MARINTEK 34 Benjamin Biausser 20 SBM Offshore 35 Charles B Paton 21 Shell 36 Jan Berger 22 Evonik 37 Sarah Abercrombie Weatherford 38 Terje Peder Stavang Statoil 39 Rune Haakonsen Kongsberg Oil&Gas 40 Torgrim Andersen 41 Andy Thompson Techflow Flexibles Ltd 42 Yu Xian Hong Techflow Flexibles Yantai 43 Yang Peng 45 Kent Caveny Kent Caveny Services LLC
8
UPDATED TARGET DATES FOR NWI AND DELIVERABLES
API 17K - New 3rd edition to be published no later than 3Q2017. API 17B K based update to be kicked off in 2H2017 after publishing API 17K API 17L1&L2 - Revision process to be kicked off in 2H2017 after publishing API 17K API 17TR2 - K. Doynov to submit SRRR form, after 17TR2 JIP completion ~ 2018
9
FUTURE MEETINGS & RESOURCE NEEDS
plans for future FPTG meetings 1-2Q 2016: Addressing API SPEC 17K Ballot Comments via FPTG teleconferences in resource needs 2Q 2017: API editorial help for 3rd edition of API 17K