1 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Outline: Financial Situation Schedule SESAME Support Installation overview Critical issues Next steps Pulsed Power Supplies SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

2 Financial Statements in U.S. Dollars (Capital)
2011 to 30/9/2016 CONTRIBUTIONS Iran 0.00 Israel 5,000,000.00 Jordan Turkey Total Contributions 15,000,000.00 Total Fund Expenses & Debts Expenses 2016 4,710,798.73 Expenses 2015 3,982,423.00 Expenses 2014 1,034,827.49 Expenses 2013 543,955.16 Expenses 2012 311,498.67 Expenses 2011 324,399.53 Account Payable 1,670,848.00 Total Expenses & Debts 12,578,750.58 Other Income Net Book Balance 2,421,249.42 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

3 Installation Plan as Wished
C.L.: Reduce first Beamlines from four to two Speed up Installation of storage ring Work with two teams using external support from Pakistan, Iran Plans, plans, talks, Interferences, plans But: Deliveries delayed: FMB (Final August) Danfysik, CECOM (Final Nov) Increased pressure on companies needed Final Delvery end Nov Vacuum (+) Installation with one team from Pakistan ok SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

4 Installation-Plan as Done
No principle change compared to Nov 2015, but one month delay Installation of Girder and Magnets finalized: May 2016 Installation of Main Vacuum System finalized: Aug 2016 Installation of 2+1/2 RF Amplifier (1+1/2 damaged): Sep 2016 Installation of 2 (3)RF cavities: Aug 2016 Installation of main cooling pipes finalized: Jul 2016 Installation of AC distribution finalized: Sep 2016 Installation of transfer line started: Sep 2016 Main cabling finalized: Oct 2016 Alignment, Check of installation: Nov 2016 Start Commissioning: Dec 2016 Last amplifier, last cavity: Jan 2017 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

5 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Difficulties we faced Delayed delivery: CECOM up to 1 Y man power Danfysik (NTG) up to 1 y (ceramic, leak) ELETTRA, CINEL 1 y (¼ Y) administrative (leak) FMB ½ y manpower Tesla 0 Y ELYTT ½ Y CERN-PS 1 Y (development) Nortemecanica ¼ Y Damaged components: Solid State Amplifier (FAT/SAT), shipping Administrative obstacles: Prepayment, Export, Import, Custom clearance lenses Local Restrictions: Parts partially not available in Jordan Partially Minor Quality No mechanical work shop at SESAME Loss of people: Control (A.I.), Power Supplies (I.A.) Mechanics (A.H.) SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

6 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Support for SESAME Pakistan: send two people for vacuum installation for nearly one year Iran: offered two people, prepared coming, abstained due to further delay by FMB Sweden: offered one person, then delayed, then canceled (personal reasons) Mohammad Rashid and Ali Ayaz from Pakistan SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

7 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
IAEA Support INT0092 Workshop/Meetings /Conferences Mahmoud Adellatief Apr ELETTRA Nashat Sawai Apr SOLEIL RF Maher Attal May Pohang Koryun Manukyan May Pohang Maher Shehab May FMB Abdullah Ahmad Aug ANKA Abdallah Ismail May Diamond Mohammad Al-Najdawi Sep ALBA Thaer Abu-Hani Oct ESRF Anas Abadi Oct Campinas Mustafa Al-Zoubi Oct ELETTRA Expert-Mission Guido Blokesch Oct Pulsed PS Paul Dumas Jun IR BL Monique Tortrat Sep Alignment Carlos Lopez Sep Installation Alexandre Thonet Sep Installation Attilio Milanese Nov Installation Miguel Bastos Nov installation Monique Tortrat Nov Alignment Pascal Catherine Nov Installation Francis Perez ? Commissioning Amor Nadji ? Commissioning Fellowship Hossein Khosroabadi Aug Diamond Saima Rasheed Oct DESY Anas Abdadi ? Alba Gihan Kamel ? Soleil Muhammad Farhan ? Diamond Murat Kurudirek ? Elettra Expert Mission paid by SESAME Monique Tortrat Feb Alignment Carlos Lopez Feb Installation Alexandre Thonet Feb Installation Lothar Schulz Feb Installation SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

8 Installation completed Nov 2016
16 girder 16 dipoles 64 Quadrupoles 64 Sextupoles 32 Vacuum Chamber 110 Ion-Pumps 1 km water-pipes 12 km cables Contribution Maher Shehab, Mohammad Najdawi SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

9 All 133 Power-Supplies Installed
No I [A] U [V] DP 1 550 1000 QF 32 300 16 QD 8 SF 2 125 40 SD 80 Corr 64 +/-10 +/-24 Per Quadrant: Quadrupole PS (4x4), Corrector PS (16) Diagnostics (24 BPM) Control (Vacuum, Machine Protection) Gateways at Test Dipole PS Contribution Safian Javar SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

10 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Diagnostics Transfer-line: 4 Fluorescent screens, 1 FCT Storage-ring: 3 fluorescent screens , 48 BPM, 1 DCCT, 1 FCT, 1 Synchrotron Light Monitor Fluorescent-Screen DCCT/FCT BPM-Block Brilliance+ Contribution Hussein Al-Mohammad SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

11 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
SR-Cooling-Pipes Thanks to CERN (Ralf Heuer, Roberto Saban, Mauro Nonis) for revising the specs Contracted to ALPHA, Jordan SR: 750 m of pipes SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

12 Water-Pipe-Installation
Specification done by SESAME, Reviewed by CERN Roberto Saban, Mauro Nonis 4 offers, Alpha selected 3d design done by SESAME (virtual conflicts do not hurt) Contractor uses 2d ‘drafting’ works ‘on sight’ Components had to be installed then work started Reduced Means Adapters, transitions, tools: Partly not available in Jordan Reduced Quality: Parallel M-thread to tapered F-thread Threaded adapters used for welding Not centered gaskets Material not as specified (‘316 LN’ gets rust) Limitations required compromises , at least it no leaks SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

13 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Cooling Plant Commissioned with Booster and SAT four years ago Connecting of Storagering and RF circuit: Missing sensors (Temperature, Flow) Broken sensors Flow, Pressure not within specs (15 (21) l/s, 6 (10) Bar Debris in circuit High return Pressure (2 bar) SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

14 Cable-Tray-Installation/Cabling/AC Distribution
Specification done by SESAME Reviewed by CERN, Roberto Saban, James D Devis Cables ordered by SESAME Cable-trays, AC-distribution 4 offers, TECO selected Cabling done by SESAME plus external Contribution Sofian Javar SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

15 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Radiation Safety Request for licensing operation done Documents requested by EMRC provided (Apr.2016) Up to now no licensing for storage-ring operation Personal safety System for storage-ring: Installation done Personal safety System for BL hutches: Installation started Further 5 online γ+n Monitors ordered Offline Dose meters (TLD’s) Contract with Landauer (measuring uncertainty 50 nSv, ϒ and n) not extended TLD’s from JAEC (measuring uncertainty 500 nSv, ϒ only) in use Contribution Adli Hamad, Anas Abbadi SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

16 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
HOM-Temperature Set Cav. Temperature to about48°C HOM shifter shift Resonances to higher Temp. Cavities is detuned due to beam loading Accumulation (0-200mA): 60 kHz / 30 min Ramping: ( GeV): kHz / 1 min higher tuning speed needed SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

17 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Work Shop Was a mess: Item and Hilti components on floor, tools disappeared, broken drill bits not replaced Some cleanup had been done, some shelves installed Got equipment from DESY (i.e. NC milling machine) No use for big CNC lath (no operator) small (NC) lath ok Need trained mechanical craftsman Need responsible person to supervise workshop Objection from Administration: man power utilized for 25% of his time Use external work shops More administrative (needs specs, bids, shipping) Quality partly minor More time (delays) SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

18 Microtron Refurbishment
Magnetic Septum?: Septum sheet 0.1 mm to 2 mm Injection efficiently reduced by factor two calculated Gain in stability factor two? Modulator control: partly refurbished by Iftikhar (resigned) tested, not installed Wave guide SF6 leaking Gas cylinder valve Leaking Transformer Oil leaking E-gun / Auxiliary gun control: Complicated analogue feed back system no spare parts, reverse engineering needed? Auxiliary gun, Cathode replacement not reproducible SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

19 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Resigned Staff Both Ismail and Iftikhar Left after installation and test Both Agreed to remote support Nevertheless: Knowhow got lost SESAME-CERN-PS Team reduced from 3 to 1 Pulsed PS expertise reduced from 1 to 0 Firmware (FPGA) expertise reduced from 1 to Increased work load for S.J. who left (further debugging, maintenance) Need to built up replacement units for Pulsed PS Replacement necessary SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

20 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Next Steps Commissioning: Beam into SR: Operate TL2 First turn: Use Fluorescent screens, BPM More turns: Measure and correct Tune RF on: Accumulate current, do more diagnostics Start ramping Install all cavities: Accumulate current and ramp Clean up: Correct, replace the provisional solution Do documentation Built up spare parts and test exchange Raised floor Organize maintenance Refurbish Microtron (Electronics) Built up mechanical workshop SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

21 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Employment New hired: Electrical Engineer: Obadah Manasrah (Power distribution) Resigned: Abdallah Ismail: Control Iftikhar Adid: Pulsed Power Supplies Akrum Homoud: Design , workshop operation (got trained at DESY) Critical Temporary hired: Water pipe system (Abdelquader Younges) Computing (Mohammad Qatatshed) Cable installation (6 p) Diagnostics (2 p) Open position: Control Engineer (Position open all time, response minor qualification) (Power-Supply Engineer) SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

22 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Pulsed Power Supplies Device Pulse form Switch type Pulse width U charge [kV] U/I L [µH] Magnetron E-gun Flat top Thyratron 3 9.0 45 kV 63 kV Injection Septum Sine Transistor 1000 0.4 100 kV 6 Injection Kicker Half sine 5 0.3 125 A 2 Extraction Kicker 0.1 30 300 A 1 Extraction Septum 500 A 10 600 6000 A 5.0 E2v cx1659 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

23 Storage Ring Injection Septum
Deflection angle 9deg Magnetic field 0.6T Magnetic inductance H Current 7.1kA waveform Full sine Full sine pulse width < 500μs The System has been installed and tested with the actual magnet SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

24 Storage Ring Injection Septum
The system consists of: DC Power Supply of 400V/2A installed in service area An enclosure that contains capacitor bank and control electronics installed in the ring under the magnet A desired voltage is set via EPICS channel, and Trigger is enabled via PLC. A 7.1kA current pulse produces 0.6T nominal field in the magnet. As can be noted in the picture SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

25 Storage Ring Injection Septum
The magnetic field has been measured such that 7.1kA current pulse produces 0.6T nominal field in the magnet. As can be noted in the above picture Blue Curve = Current Pulse 2kA/division Black Curve = Integrated Magnetic field 200mT/division Red Curve = Magnetic probe voltage 2volt/division SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

26 Storage Ring Injection Kicker
The system consists: Kicker magnet of 1uH, Half sinewave High voltage power supply Capacitor bank+Thyratron +Thyratron driver Control Electronics EPICS+PLC communication The H.V power supply is installed in the service area. The enclosure contains H.V capacitor bank, thyratron switch and its driver and installed inside storage ring under the kicker magnet. A desired voltage is set via EPICS channel, and Trigger is enabled via PLC. 550Apeak current produces 0.018T field resulting in Tm kick. The system has been installed in the ring and tested with the actual magnet SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

27 Storage Ring Injection Kicker
SESAME-TAC-2016-Erhard-Huttel-Reporting-Back

28 SESAME-TAC-2016-Erhard-Huttel-Reporting-Back
Tuner-Movement SESAME-TAC-2016-Erhard-Huttel-Reporting-Back