TE-EPC internal review of the ELENA project

Similar presentations


Presentation on theme: "TE-EPC internal review of the ELENA project"— Presentation transcript:

1 TE-EPC internal review of the ELENA project
ELENA sub-work package 2.4.3 APOLO Power Converters 5th November 2015

2 Deliverables of ELENA WP 2.4.3
1 APOLO_2p + 1 spare (450V/900Apeak/400Arms), Function: Bending magnets, Functional specification: all information already included in WP description EDMS # MPC Linkmen: G. Le Godec / C. Mutin 5th November 2015

3 Purchasing strategy of ELENA WP 2.4.3
Converters already produced, tested and validated (performance tests performed by HPM section): 1 unit stored in BA80 waiting for installation in b.193, 1 unit modified for new SIRIUS family:  Energy Balance strategy validation,  Test bed for Electrolytic capacitors, will be kept in 866 until Q (schedule to be confirmed). 5th November 2015

4 Installation strategy of ELENA WP 2.4.3
Installation procedure: Who is in charge? C.Coupat with the support of C.Mutin, What is done: DC cables: choice validated with EN/EL, To be done: AC cabling (EN/EL), Water cooling (EN/CV) ? Magnet interlocks (TE/MPE), Ethernet, 5th November 2015

5 Overall status of ELENA WP 2.4.3
Budget code 99250:  70 kCHF to spend. BC were used to manufacture the APOLO package are now used to manufacture the APOLO_4p and for the commissioning of all these converters. BC could be closed at the end of 2016, better in Status to be done end 2016. 5th November 2015