Presentation is loading. Please wait.

Presentation is loading. Please wait.

Harold G. Kirk Brookhaven National Laboratory The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005.

Similar presentations


Presentation on theme: "Harold G. Kirk Brookhaven National Laboratory The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005."— Presentation transcript:

1 Harold G. Kirk Brookhaven National Laboratory The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005

2 Harold G. Kirk The Funding Profile

3 Harold G. Kirk High Field Pulsed Solenoid l 80 o K Operation l 15 T with 5.5 MW Pulsed Power l 15 cm warm bore l 1 m long beam pipe Peter Titus, MIT

4 Harold G. Kirk Pulsed Solenoid Milestones Delivery to MIT December 05 Reception Testing January 06 Integration Testing September 06 Ship to CERN November 06 Installation at CERN December 06

5 Harold G. Kirk The Hg Jet System Double Containment System, with snout inserted into magnet. Mercury inventory ~ 20 liters. Hydraulic system can deliver up to 1000 psi, to propel mercury at > 20 m/s

6 Harold G. Kirk Hg Jet System Milestones Delivery of Hydraulics February 06 Containment Vessels May 06 Optics Delivery June 06 System integration at ORNL June-July 06 Integration Testing at MIT September 06 Ship to CERN November 06 Installation at CERN December 06

7 Harold G. Kirk Target Test Site at CERN

8 Harold G. Kirk The Tunnel Complex TT10 TT2 TT2A ISR (Control Room Location) MERIT Hyd Pump & Controls in TT2

9 Harold G. Kirk Surface above the ISR 6000 l Dewar Access Route Two 18kV sub-stations One 18kV Sub-station

10 Harold G. Kirk Power Converter (From SPPS Transfer Line) 8000 Adc, 1000 Vdc Global view Rectifier bridges Passive filter Passive filter capacitors self capacitors DC output Strategy: Refurbishment of the West Area Power Converter, making it compatible with the project requirements

11 Harold G. Kirk Power Supply Milestones Site Preparations January 06 Relocate and Install February 06 DC Cabling February 06 AC Cabling March 06 Refurbish PS March-April 06 Interlocks September 06 Commissioning October 06

12 Harold G. Kirk Cryosytem Layout LN 2 and N 2 gas stored on the surface. Cold valve box in the TT2 tunnel. Exhaust gas vented into TT10 tunnel through filtration system. ~ 150 liters of LN 2 per Magnet pulse. Magnet flushed with N 2 prior to each pulse, to minimize activation of N 2.

13 Harold G. Kirk Cryogenics Process and Instrumentation

14 Harold G. Kirk Cryogenic System Milestones TT10 Vent Installation January 06 Cold Valve Box Fabrication April-July 06 Control System Development January-June 06 Surface Preparations May 06 Transfer Line Installation July 06 Cold Valve Box Testing October 06 Heater System Installation September 06 Cold Valve Box Installation November 06 Commissioning December 06

15 Harold G. Kirk Project Major Sub-systems FY05 Q4 FY06 Q1 FY06 Q2 FY06 Q3 FY06 Q4 FY07 Q1 Magnet Magnet Delivery Receiving Testing Integration Testing Shipping Installation Hg Jet System Fabrication Nozzle Development Optical Diagnostics System Testing ORNL System Testing MIT Shipping Installation

16 Harold G. Kirk CERN Infrastructure FY05 Q4 FY06 Q1 FY06 Q2 FY06 Q3 FY06 Q4 FY07 Q1 Power Supply Site Preparations Installation DC Cabling AC Cabling Interlocks Commissioning Cryogenics TT10 Vent Cold Valve Box Fab. System Testing CERN Surface Preparations Tunnel Installations Commissioning


Download ppt "Harold G. Kirk Brookhaven National Laboratory The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005."

Similar presentations


Ads by Google