1 FORSYTH COUNTY SCHOOLS CAPITAL PROGRAM LOCATION CONSTRUCTION PROJECT
LOCATION CONSTRUCTION PROJECT ARCHITECT A/E START GC/CM OPEN SUMMARY STATUS HIGH SCHOOL ADDITIONS AND MODIFICATIONS North Forsyth H.S. Stadium visitors concession and restroom BRPH Done Charles Black Certificate of Occupancy issued 8/14/14 Additions & Cafeteria FSF Barton Malow FM Certificate of Completion issued 5/31/16 , Furniture installed Gymnasium FM Certificate of Occupancy issued 6/24/16 Renovations (Band,Choral,Classrooms) Dec-16 Band CO scheduled for 11/1, Choral 12/1, Classrooms 12/30 Forsyth Central H.S. Additions CPL Parrish FM Certificate of Occupancy issued 5/17/16 , Furniture installed Renovations (STEM labs) In progress South Forsyth H.S. Gymnasium , Adds, Cafeteria MSSA Balfour Beatty FM Certificate of Occupancy issued Renovations East Hall Classrooms FM Certificate of Occupancy issued 9/20/16 Renovations (W Hall Classrooms, Culinary) Lambert H.S. Additions- 19 classrooms , band FM Certificate of Completion issued 5/27/16, Furniture installed Renovations (Engineering & Health Labs) FM Certificate of Completion issued 7/27/16, Furniture installed Artificial Turf Field (IGA $ , not bond) Breedlove Shaw West Forsyth H.S. Additions - Performing Arts (Band,Choral) Cooper & Co Apr-17 steel , masonry in progress Renov's (Art,Computer,Engineering Labs) Jul-17 Denmark H.S. Denmark HS New Construction Jun-18 sitework , foundations, steel, masonry in progress Alliance Academy Alliance Academy New Construction GC Final Dwgs approved by DOE, GC RFP released 9/6 RFP responded 10/6, GC interviews 10/18

2

3

4

5 West Forsyth High School – Band Addition

6 West Forsyth High School

7 MIDDLE SCHOOL ADDITIONS AND MODIFICATIONS Liberty M.S.
Modify front entrance for security James Buckley Done Complete Modifications cafeteria Kevin Price Aug-16 Cafeteria renovations completed Expand Band Classroom Jan-17 Band Addition to be complete 1/1/17 Little Mill M.S. Modify front drive entrance McFarland Dyer Sep-16 Mar-17 Aug-17 North Forsyth M.S. Media center , band , team room Band , Media Renovations completed, Adds 1/1/17 HVAC replacement / modification CGE Capital City Aug-15 HVAC completed Otwell M.S. Expand engineering lab , band Piney Grove M.S. Front Drive sidewalk in progress Modify technology lab Tech Lab Renovation completed 10/1/16 South Forsyth M.S. 23 Classroom Addition RaLin FM Certificate of Completion issued 5/24/16, Furniture installed Expand Media Ctr ,Cafeteria, Modify PA Expansions completed 8/2/16 Riverwatch M.S. 24 Classroom Addition FM Certificate of Completion issued 5/19/16, Furniture installed Expand band room Band Renovation to be completed 8/1/16 Vickery Creek M.S. Expand Media Ctr , Engineering Lab Additions to be completed 1/1/17 DeSana MS MS #10 New Construction Evergreen FM Certificate of Occupancy issued 6/15/16 , furniture installed Middle School #11 MS #11 land purchase search, due dilligence options in progress

8 ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS Brandywine ES
Brandywine ES New Construction LPBC Done Charles Black Certificate of Occupancy issued 6/9/16 , furniture installed Midway ES Sanitary sewer service CEC Started MidSouth Completed 7/12/16 Daves Creek HVAC replacement / modification CGE Waters Aug-15 HVAC completed Settles Bridge Capital City General security,media ctr, partitions, parking TBD