1 Breakdown Work Structure Applying Management Tools to a Project

2 Work Breakdown Structure (WBS) WBS: Defines the total system to be developed or produced. Relate the elements of work to be accomplished to each other and to the end product. Is displayed as a product oriented family tree composed of hardware, software, services, data and facilities which defines the total program. Standard: Mil Hdbk-881

3 ORGANIZATIONAL Provides Structure for Assigning Multi-Disciplinary Product Teams TECHNICAL Shows the System and its Subsystems as a Product Tree Product Tree aids: Interface Identification & Control Specification Development Provides a Structure: Work Assignment Material/Part Ordering Configuration Items must be traceable to WBS BUSINESS Provides Structure for Budgets and Cost Estimates Collect and Analyze Costs to track Budget Basic Purposes of Work Breakdown Structure

4 The Anatomy of a WBS A WBS has a Product Part and a Process Part. Product part of the system – Products delivered to the operational customer. – Design (Physical) architecture. Process part of the system – Efforts required to develop, produce and support products. – Execution of the IPT primary function process elements.

5 WBS Development Ensure all applicable work is represented. Enough levels provided to identify work packages for control purposes. (usually levels 0,1,2) Duplication of work eliminated. If too few levels identified - management visibility and integration of work packages may be difficult. If too many levels - too much time may be wasted in performing program review and control actions.

6 Level Zero- Overall System (derived from Functional level 0) The entire Program Example: EE321X course (Robots and C&C Essay) Level One- Subsystems (derived from Functional level 1) Major System(s) Examples: Recycling Robot (competition) – C&C Reflective Essay Level Two- Components (derived from Functional level 2) Subsystem(s): Recover, Move, Store, Sort ……, Research, Select, Reflect, Review, Draft, Write For Program Managers, levels 1-3 are of prime importance WBS Levels

7 Work Breakdown Structure Program (eg Aircraft System) Program (eg Aircraft System) Air Frame Engine Navigation L E V E L Z E R O L E V E L O N E L E V E L T W O Program Management/ Systems Engineering Program Management/ Systems Engineering Other services, data, facilities Other services, data, facilities Prime Mission Product (Air Vehicle) Prime Mission Product (Air Vehicle)

8 Air Vehicle Integration, assembly, test, and checkout efforts Systems engineering and Program management Systems engineering and Program management Training Data System test and evaluation System test and evaluation Peculiar support equipment Peculiar support equipment Common support equipment Common support equipment Operational and site activation Operational and site activation Industrial facilities Industrial facilities Initial spares and repair parts Initial spares and repair parts This combination of prime mission product and other supporting process elements constitutes a complete Work Breakdown Structure. Air Frame Engine Navigation Program Common WBS Elements

9 WBS - Defense Materiel Item Categories Aircraft / Helicopter systems Electronic / Automated Software systems Missile systems Ordnance systems Ship systems Space systems Surface Vehicle systems www.dsp.dla.mil

10 Work Breakdown Structure Dictionary WORK BREAKDOWN DICTIONARY CONTRACT NUMBER Index Item No. 2 WBS Level 2 F33657-72-C-0923 WBS ELEMENT A10100 WBS TITLE Air Vehicle Specification No. 689E078780028 DATERevision No.Revision AuthApproved Chg SPECIFICATION TITLE: Prime Item Development Specification For AGM 86A Air Vehicle/Airframe Contract Line Item: 0001, 0001AA, 0001AB, 0001AC, 0001AD 0001AE, 0001AF, 0001AG, 0001AH ELEMENT TASK DESCRIPTION Technical Content: The Air Vehicle element task description refers to the effort required to develop, fabricate, integrate and test the airframe segment, portions of the Navigation/ Guidance element, and Airborne Development Test Equipment and Airborne Operational Test Equip- ment and to the integration assembly and check- out of these complete elements, together with the Engine Segment, to produce the complete Air Vehicle. The lower level elements included and summarized in the Air Vehicle element are: Airframe Segment (A11100), Navigation/Guidance Segment (A32100), Airborne Development Test Equipment (A61100, and Airborne Operational Test Equipment (A61200) COST DESCRIPTION MPC/PMC Work Order/Work Auth A10100 See lower level WBS Elements Applicable SOW Paragraph: 3.6.2 Cost Content - System Contractor The cost to be accumulated against this element include a summarization of all costs required to plan, develop, fabricate, assemble, integrate and perform development testing, analysis and reporting for the air vehicle. It also includes all costs associated with the required efforts in integrating, assembling and checking our GFP required to create this element.

11 Relationship of Spec Tree and WBS System Specification System or Item Perform. Specification Item Perform Specification Item Perform. Specification Item Detail Specification Detail Drawings Specification Flowdown System System/ Subsystem Component (Assembly) Subassembly (Detail Part) WBS Decomposition Defense System Air Vehicle Airframe Electrical Subsystem Power Supply Amplifier Circuit Board Subsystem

12 Work Package Defines: The work required. Functional responsibility for performance. It is a specific task or set of tasks to be accomplished to produce a: -Drawing, -Design, -Piece of hardware or service.

13 WBS Summary WBS development is a systems engineering responsibility. – Total system described through a logical breakout of elements into work packages. – Tool for planning and assignment of tasks and work packages. – Assists in tracking resource expenditure, schedule, and technical performance. – Must be developed to appropriate level and represent all applicable work.

14 WBS Assignment Complete a WBS for your project using the WBS Microsoft Template located at in the Teamwork file at the Angel site.

15 AUGV SYSTEM Vehicle T & E Training Data Logistic Supportability Sys Eng & Integration AUGV WBS Program Mgt

16 AUGV WBS Exercise Review contract WBS and make any proposed changes to second level As a minimum, take the “vehicle” element and extend it to level 3 Show complete WBS in either tabular or graphic form, including numbering convention


Download ppt "Breakdown Work Structure Applying Management Tools to a Project."