Presentation is loading. Please wait.

Presentation is loading. Please wait.

NML - RF Unit Test Facility Jerry Leibfritz Fermilab.

Similar presentations


Presentation on theme: "NML - RF Unit Test Facility Jerry Leibfritz Fermilab."— Presentation transcript:

1 NML - RF Unit Test Facility Jerry Leibfritz Fermilab

2 May 18-19, 2009DOE SRF Review 1 Outline NML Project Overview and Goals Layout of Facility Technical Progress Since Last Review Major Milestone Schedule NML-Related ARRA Spending Plan Conclusions

3 May 18-19, 2009DOE SRF Review 2 NML Project Overview Overall Goal –Build an RF Unit Test Facility at the New Muon Lab building (NML) RF unit = 3 cryomodules 10-MW RF system Beam with ILC parameters (3.2 nC/bunch @3 MHz, up to 3000 bunches @ 5Hz, 300-μm rms bunch length) Various Project-X parameters will also be tested with beam Phase-1 (FY07 - FY09) –Prepare facility for testing first cryomodule (CM1) without beam Infrastructure, RF power, cryogenics (Refrigerator #1) Install first cryomodule (CM1) and Capture Cavity-2 (CC2), cooldown, and RF test

4 May 18-19, 2009DOE SRF Review 3 NML Project Overview Phase-2 (FY10 - FY11) –Prepare for first beam Civil construction to expand facility (capability for 2 RF units) Install gun, injector, test beamlines, beam dump, second cryomodule (CM2) Phase-3 (FY11 - FY13) –Complete RF Unit Upgrade RF system to 10 MW, install third cryomodule (CM3) Commission new Cryogenic Plant Operate full RF Unit with beam Begin installation of 2nd RF Unit

5 May 18-19, 2009DOE SRF Review 44 Phase-1 Layout of NML Cryomodule-1 (CM1) (Type III+) Capture Cavity 2 (CC2) CC2 RF System 5 MW RF System for CM1

6 May 18-19, 2009DOE SRF Review 55 Overall Layout of NML Building CryomodulesCapture Cavity 1 (CC1) 5MW RF System for Gun CC1 & CC2 RF Systems RF Gun 5MW RF System for Cryomodules Future 10MW RF System CC2 3.9/Crab Cavity Test Beamlines

7 May 18-19, 2009DOE SRF Review 6 Future Expansion of NML Facility Existing NML Building New NML Underground Tunnel Extension (Space for 6 Cryomodules (2 RF Units), AARD Test Beam Lines) New Cryoplant & CM Test Building (300 W Cryogenic Plant, 2 Cryomodule Test Stands, Space for 2 Horizontal Test Stands, 10 MW RF Test Area)

8 May 18-19, 2009DOE SRF Review 7 NML Building Expansion Test Beam Lines/AARD Area Raw Water Skid Beam Dump Rack Room/Laser Hut Alcove for Cryoplant Tie-in CM6 Construction Scheduled to Begin - 8/09 CM5 Existing NML Building Internal Review of Design - 4/09

9 May 18-19, 2009DOE SRF Review 8 Cryoplant & CTS Building (2) Cryomodule Test Stands (CTS) 300 Watt Cryogenic Plant CTS Building Horizontal Test Stand #2 (HTS2) Horizontal Test Stand #1 (HTS1) 10 MW RF Test Area

10 May 18-19, 2009DOE SRF Review 9 NML Technical Progress

11 May 18-19, 2009DOE SRF Review 10 NML Infrastructure (FY07-08) Completed Removal of Chicago Cyclotron Magnet Prepared Building Infrastructure –AC power, network cabling, piping, cable tray, air ducts –Cleaned out building, epoxy coated floor, alignment network –Cave for Phase-1 (~3/4 of full cave), electrical racks –Reused existing equipment (tray, racks, piping, shield blocks, gas storage tanks, cryo heat exchangers & refrigerator components) NML During Removal of Chicago Cyclotron Magnet(CCM) (September, 2006) NML Facility after CCM Removal and Floor Painting (February, 2007)

12 May 18-19, 2009DOE SRF Review 11 Current Picture of NML Facility

13 May 18-19, 2009DOE SRF Review 12 View From North

14 May 18-19, 2009DOE SRF Review 13 NML Cryogenic System Cryogenic System –Installed Refrigerator Room & helium storage tanks –Tevatron Satellite Refrigerator #1 operational - 8/07 –Tevatron Satellite Refrigerator #2 installation - Fall 2009 –Distribution system Feedbox, Feed Cap & End Cap installed –Orbital welder Interconnect mockup and test fixture built Initial orbital welding tests successful –Vacuum pump and Frick compressor Commissioned - 1/09

15 May 18-19, 2009DOE SRF Review 14 NML Cryogenic System Refrigerator Room Feedbox/Feedcap Cryo Vacuum Pump Orbital Welder

16 May 18-19, 2009DOE SRF Review 15 NML RF System RF System –5 MW for CM1 Preparing for commissioning –300 KW for CC2 Commissioning in progress –Distribution CM1 distribution from SLAC (in-house) 5 MW RF Waveguide (SLAC) CC2 RF300 KW RF

17 May 18-19, 2009DOE SRF Review 16 NML Accelerator Injector –Detailed Lattice designed –New gun being built (will be tested at A0 Photoinjector) Collaboration with DESY, KEK & INFN –CC2 (single 9-cell cavity) installed - 3/09 Accelerator –CM support girders installed & aligned –First cryomodule test install. - 8/08 Test Beamline –Beamline layout complete –Beam Absorber analysis complete

18 May 18-19, 2009DOE SRF Review 17 NML Auxiliary Systems Vacuum System –Low-particulate vacuum carts built and tested Leak detectors, RGA’s, pumps, gauges, controls –Equipment for insulating, beamline, and coupler vacuum systems in-house –(3) portable cleanrooms built (capable of achieving Class-10) Tested during CC2 vacuum installation Water Cooling System –System design complete –New pumps and heat exchanger installed –Temporary skid (for Phase-1) operational Safety Systems –Radiation, ODH, Interlock, and Safety Assessment documentation being prepared

19 May 18-19, 2009DOE SRF Review 18 NML Auxiliary Systems Water System CC2 InstalledCleanroom Work on CC2 New Vacuum Cart

20 May 18-19, 2009DOE SRF Review 19 NML Controls/Instrumentation Controls –Control Room finished and operational –Wireless network installed throughout building Instrumentation –Wire Position Monitors for CM1 tested and installed in Endcaps –Faraday Cup assembled –RF protection/interlock system complete Before After

21 May 18-19, 2009DOE SRF Review 20 NML Facility Milestones Phase-1 Cryogenic System Operational(Aug. 2007) Delivery of First Cryomodule to NML(Aug. 2008) Begin Civil Construction of NML Expansion(Summer 2009) First Cryomodule Ready for Cooldown*(Summer 2009) Cold RF Testing of First Cryomodule*(Fall 2009) Delivery of 2nd Cryomodule to NML (S1)(2010) Install Gun and Injector(2011) First Beam(2012) Cryoplant Operational(2012) Full RF Unit Testing (3 Cryomodules) (S2)(2012) Cryomodule Test Stand (CTS) Operational(2012) *Significant project delays occurred due to funding cuts in 2008

22 May 18-19, 2009DOE SRF Review 21 NML-Related ARRA Funds NML Equipment$10,765* –Accelerator beam line components Magnets, Vacuum, Instrumentation –Facility infrastructure upgrades Electrical, Chiller –Beam absorbers/dump, utilities, shield blocks –RF, cryogenic, controls & cleanroom equipment –Contract labor (electricians, pipefitters, etc.) NML Building Expansion$4,900 Cryogenic Refrigerator$7,815 Cryogenic Distribution$1,550 Cryoplant & CTS Building$7,000 10 MW RF Klystron$1,020 *All given values are direct M&S in $k

23 May 18-19, 2009DOE SRF Review 22 Conclusions Despite budget cuts in FY08, significant progress was made in the construction of the NML Facility The planned ARRA funding will help put the project back on track to complete the infrastructure required to become operational and contribute significantly to the Global S1 and S2 goals of the ILC & Project-X In addition to testing SRF cryomodules, NML will provide a state-of-the-art facility for conducting Advanced Accelerator R&D (AARD) for future accelerator components

24 May 18-19, 2009DOE SRF Review 23 Backup Information

25 May 18-19, 2009DOE SRF Review 24 Bunch Compressor ILC RF unit Diagnostics Gun CC I,II Laser 3 rd har Test Area ~ 22 M 72 M Existing Building New Enclosure New ILC like tunnel 2 nd ILC RF unit Test Areas RF Equipment RF Unit Test Facility at NML Overall Plan: Test RF units: Px, ILC S1 & S2 goals ILC: 3 CM, Klystron, Modulator, LLRF Move A0 Injector to provide ILC like beam New Tunnel Extension: design to allow 2nd RF unit, diagnostic beam lines, AARD facility New Building: Cryoplant, Cryomodule Test Stands

26 Integrated ILC- Px SRF Plan

27 May 18-19, 2009DOE SRF Review 26 Beam Line Layout Injector Beam Line Layout Test Beam Line Layout


Download ppt "NML - RF Unit Test Facility Jerry Leibfritz Fermilab."

Similar presentations


Ads by Google