Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix 2010 - 26Jan’10)

Slides:



Advertisements
Similar presentations
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Advertisements

Summary of session 3: Optimise Interventions and Recovery from Collateral Damages on Cold Sectors Prepared by Caroline Fabre & Pierre Strubin Based on.
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
1 Integration of collimators in the dispersion suppressors Status of 11 T cryo- assembly integration Dec 17, 2013
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
SC - 04Feb'13Cryo Heaters Review Cryogenic Heaters Review Operation use and wishes S. Claudet - A. Suraci LHC Cryogenic Operation.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Session 3 - What repair activity can be done today on a locally warmed-up sub-sector Paul Cruikshank TE/VSC What repair activity can be done today on a.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
Workshop on cryogenic and vacuum sectorisations of the SPL CERN, 9 th -10 th November 2009 Workshop Organisation and Goals Vittorio Parma TE-MSC.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
MICE CC Test Status Ruben Carcagno 11/06/13 1. Cooldown Coil Temperature (calculated average in each of 8 coil segments) SC Transition (voltages across.
05 Novembre 2003Chamonix XIV Workshop, January How to deal with leaks in the QRL and magnet insulation vacuum Paul Cruikshank for AT/VAC Germana.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Road map of the workshop Machine availability: – “work-horse” in the injection chain – 100% availability not viable,.What is achievable? And at which cost?
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
HC review, A. Perin, 12-MAY DFB Project LHC hardware commissioning review May 2005 Hardware commissioning of the DFBs and DSLs and connection.
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
[R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] HWC Workshop ( ) Consolidation and major changes that have impact on the powering circuits.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
Vacuum, Surfaces & Coatings Group Technology Department 22 nd January 2015 C. Garion2 Beam Line Interconnection: snapshot of present design principles.
CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in.
The integration of 420 m detectors into the LHC
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
TE-CRG Activities D. Delikaris, TE-CRG.
Cryogenic Cooling Schemes for the SPL U. Wagner TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Page 1 CRYOMODULE 650 (TESLA Style) Stand Alone Tom Peterson and Yuriy Orlov Collaboration Meeting 25 Jan 2011.
LHC Cryogenics, equipment & interventions around P3/P7 S. Claudet, “volunteer” for TE_CRG 16 Oct’14.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
Roadmap for triplet cryostats
SMACC Tenth report [15 min] 13/09/2013
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
The LHC - Status Is COLD Is almost fully commissioned
Cryogenics for sc links, a short update
Coordination of Hardware Commissioning
Consequences of warming-up a sector above 80 K
Keeping LHC cold during LS periods Preliminary proposal
Hollow e- lens, Cryogenic aspects
Consolidation of the dipole diode insulation Technical aspects
The 11T cryo-assembly: summary of design and integration aspects
Summary post TCC#54_02Aug’18
HL-LHC New MS optimisation WP9, Preliminary cost estimates
J. Fleiter, S. C. Hopkins, A. Ballarino
HL-LHC Post MSO optimisation, Complementary considerations for Q4
Presentation transcript:

Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors What would you expect ? The LHC sub-sectorisation baseline tells you: NO ! Partial warm-up could damage PIM’s, we remember we were told to periodically re-cool the magnets last year !! Air in the circuits could be trapped on cold surfaces, and perturbate operation of VAC and Cryo systems !!! The operation of the cryogenic system starts only to be under control, with great expectations for the coming years, and this could reduce their availability ! Why me ?!? Things may change and be reconsidered …

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Content Present LHC baseline Developments made for PIM’s issues (2008) Main actions & Warm-up cases Sequence: –Cutting –Re-installing Conclusion

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Present LHC baseline (1/3)

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Present LHC baseline (2/3) LHC Design Report, Figure 11.5 Cryogenic flow-scheme and instrumentation of a LHC lattice cell Only interventions inside the cold mass volume (sectorised) could be envisaged with a partial warm-up: splices, diodes, He leak, …

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Present LHC baseline (3/3) [ text extracted from LHC Design Report] Together, these two sub-sectoring schemes for cold mass and insulation vacuum allow to warm-up a limited length of cryo-magnets (up to 600 m) to perform short interventions on the cold-mass components (splices, diodes, 60 A current leads…). In that case, the warm-up and re-cool-down time is reduced by a factor three with respect to the normal full sector warm-up and cool-down times. However, for removing cryo-magnets, which require the opening of cold bores or bayonet heat exchangers or main headers, the complete sector has to be warmed up and re-cooled down.

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Developments for PIM’s (1/3) PIM WG Reported by P. Cruikshank to MaRiC

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Developments for PIM’s (2/3) To be looked at

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Developments for PIM’s (3/3) OK for 100K at cold/warm interface Principle to be kept

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Content Present LHC baseline Developments made for PIM’s issues (2008) Main actions & Warm-up cases Sequence: –Cutting –Re-installing Conclusion

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Main actions to be performed Cold Mass, Line N: OK as according to baseline (sectorised) Line X/Y (bayonet HX), Line C’ (cooling intercept): Even with a warm QRL, air would reach cold surfaces in the cold sub-sectors and get trapped ! Line E (thermal shield): Air would reach cold surfaces in the cold sub-sectors and get trapped Beam tubes: just like changing a PIM! NB: future beam effect (scrubbing) as if entire arc vented Prevent air flow when cutting / welding Prevent condensation in insulation vacuum

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Required warm-up Floating 20K to 130K Warm-up of concerned sub-sector to 300K, and adjacent right to 100K (then GN2 bag against condensation) Most likely a 2nd sub-sector to be warmed- up, as ELQA of Line N requires so far to access 4 boxes (3 x 54m) Only PIM with potential (very) small risk by now

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Cutting/Welding without air in pipes Cutting to be made with little over-pressure (experience!) Temporary cap to be placed Beam tubes: just like changing a PIM! Delicate definition of required over-pressure and pipe preparation, but seems possible without too much pollution of cryo pipes with air QUI Via QRL return module DN 50 DN 15 DN 80

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Caps or welding with He flow Temporary caps on opened pipes, with GHe flow when fixing in place ( kind of clamp + screw plug) Probably common development for Vacuum and Cryo pipes Pseudo leak-tight sleeve with exhaust for GHe before welding libs, and welding of plug at the end

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Specific case of Line N Very specific installation procedure, no splice designed yet except in junction box every 54m (an add. One would create a non standard magnet type), and specific ELQA tests requiring access to 4 such boxes

SC -26Jan'10Cham'10 - Optimised interventions on cold sectors Conclusion Minimising the risks associated with a complete thermal cycle (plus cost and time advantages) is definitely worth being looked at This very preliminary evaluation tends to validate the principle of a partial warm-up (Maxi: 2 sub-sectors at 300K + 1/2 at 100K) for replacement of a magnet, provided: –We can develop tools and procedures for welding sleeves without entering massively air in the pipes –We do not have systematic problems at cold-warm interface (such as PIM’s or other items) To be considered as a global optimisation process, as some systems could be penalised after restart of operation