CLIC DETECTOR PAC RING SHIELDING CONCEPT Jerome Axensalva BE/OP16/12/2011 MDI meeting1.

Slides:



Advertisements
Similar presentations
Panda Solenoid Timelines. General Layout constraints and HOLD POINTS.
Advertisements

SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Chapter 3 Hydraulic Cylinders
STAR Detector Main Support System1 Lateral Tracking of the STAR Detector during Translation. November 23, 2005 Ralph L. Brown STAR Operations Group.
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
Magnetic circuits of transformers. Magnetic circuits of transformers - assembly Obtuse layout (no-overlapping) easy assembly for small-sized transf. disadvantages:
SPACE FRAME Interface between the LGT and the IST 21/06/2011 Marco Ciapetti.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
1 M. Modena for the CLIC MDI magnet study Team (A. Aloev, P. Thonet, E. Solodko, A. Vorozhtsov) CLIC MDI Meeting,16 January 2015.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
1 Discussion for basic options — engineering video conference July 12, 2006 Outline Water pool — advantages — issues, problems, engineering options Aquarium.
M. Modena, A. Aloev CERN, Geneva, CH “An alternative Super-ferric design for ILC QD0” “LCWS14, 6-10 October 2014 Belgrade.
STATUS of the final PACMAN bench integration PACMAN meeting 11/06/2015 Hélène Mainaud Durand.
Flex Cam – Training This shows one version of a complete FlexCam system including Power Unit HCP and Compact Cam CC for piercing operation.
CMS Pixels upgrade CO 2 cooling transfer lines Introduction to the two projects P.Tropea 5 Dec 2012.
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
DBQ support – motorization and performance upgrade Mateusz Sosin EN/MEF-SU.
SVD Mechanics Markus Friedl (HEPHY Vienna) BPAC, 26 October 2015.
Original ATE brake calipers and remanufactured calipers Thermal stability and maximum decelerating power.
Date Event Global Design Effort 1 Platform Moved on Hillman Rollers, Deformations John W. Amann ILC – Mechanical Engineering 9/12/07 IREng07.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
CLIC Workshop th -17 th October 2008 Thomas Zickler AT/MCS/MNC 1 CLIC Main Linac Quadrupoles Preliminary design of a quadrupole for the stabilization.
1 Jim Thomas - LBL A proposal to close the Grid Leak “it will never die” Yuri Fysiak, Jim Thomas & Gene VanBuren Eric Anderssen, Howard Wieman & Jon Wirth.
Grapple Housing Top Sub Grapple Collet Seal Housing Bottom Sub Seal Housing Metal Seal Ring.
CLIC Stabilisation Day’08 18 th March 2008 Thomas Zickler AT/MCS/MNC/tz 1 CLIC Quadrupoles Th. Zickler CERN.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
September 20, 2007H. J. Krebs/B. Wands/B. Cooper1 SiD Collaboration Preliminary End Door Design Concept Support of Forward Systems H. James Krebs Bob Wands.
1 Proposal of the mechanical support on the Buffer for the 10“ PMTs by Enrique Calvo Alamillo.
Enrique Calvo Alamillo Ds DHCAL m 3 modular structure. 2. Basic modular distribution. 3. Guiding and repositioning system. 4. Detector.
The integration of 420 m detectors into the LHC
8/12/2010Dominik Dannheim, Lucie Linssen1 Conceptual layout drawings of the CLIC vertex detector and First engineering studies of a pixel access/insertion.
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
PSB Reference Magnet (for the 2.0 GeV upgrade) A.Newborough 16 th October 2014.
1 st LTEX meeting Protecting the experimental caverns and personnel from a "sector 34 like" incident: work planned in the LHC tunnel Prepared by M GASTAL.
CONCEPTUAL DESIGN OF D2 MECHANICAL STRUCTURE (DOUBLE COLLARING OPTION) S. Farinon, P. Fabbricatore (INFN-Sezione di Genova) Sept. 24 th 2015.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC Michigan State.
12 July 2007IRENG07 WG-A M. Breidenbach1 SiD Concept SiD is relatively modest in scale compared to the LHC detectors, and comparable to SLD: Tracker Radius.
Page 1 GSI, Hydraulic Actuators for PANDA Target Spectrometer Jost Lühning, GSI Darmstadt Functional Specifications for moving the TS: Two synchronous.
Tagger and Vacuum Chamber Design Jim Kellie Glasgow University.
Proposal for Microstation Prototype Jaak Lippmaa CERN 2005.
Shielding the turbomolecular pump and the vacuum gauge 11 June 2013 Kiril Marinov ASTeC, MaRS, DL 1.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Roller/rail - System for PANDA
SiD Collaboration Meeting SLAC, December 2011
Status of the PANDA Magnet mechanics (yoke & cryostat)
STRAW TRACKER SYSTEM CAD STATUS :
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Status and Progress of NSW HUB and Extension
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
PANDA Yoke of the Magnet
Forces on MICE magnets in Step IV, commissioning steps J Boehm
Update of experimental hall in Japanese mountain site
Arc magnet designs Attilio Milanese 13 Oct. 2016
Detector hall in mountain regions
WG4 – Progress report R. Santoro and A. Tauro.
Control Valve with Floating Seal
Integration and IR Hall
o-ring groove depth = 0.080” width = 0.145” clearance
Detector hall in mountain regions
CNGS horn / reflector in 2005: The story of the glass ring insulator
Senad Kudumovic Design engineer
The Mechanical Engineering & Technology (MET)
Bunker Wall Design Wall ESS
Introduction to Presses
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
IR Beam Transport Status
Progress of CEPC detector magnet
Presentation transcript:

CLIC DETECTOR PAC RING SHIELDING CONCEPT Jerome Axensalva BE/OP16/12/2011 MDI meeting1

Introduction 1: At its both ends, the CLIC detectors must be shielded to avoid radiation leaks in the experimental cavern, this can be achieved by filling the gap between the detector and the cavern walls with dedicated material. Jerome Axensalva BE/OP General Layout. Drawing by Nicolas Siegrist 16/12/2011 MDI meeting2

Introduction 2: To allow the detectors to be moved in and out the cavern and to insure the maximum tightness against radiations (no gap between the cavern wall and the detectors), it is foreseen that this radiation shielding can be extended and retracted. Jerome Axensalva BE/OP Shielding layout. Drawings by Nicolas Siegrist 16/12/2011 MDI meeting3

Constraints we have around the demanded shielding: - The first 100 mm of depth of the yoke material. - 4 fixed concentric coil rings. - Cavern wall (not shown). - If any other, please specify…! Jerome Axensalva BE/OP16/12/2011 MDI meeting4

What is required : A Moveable Shielding System Between the Coil Rings to Fill the 50 mm Gap. Jerome Axensalva BE/OP16/12/2011 MDI meeting5 Shielding in extended position Shielding in retracted position

What is proposed 1: We need a supporting system for the moveable shielding rings -> screwed sliding pins in the yoke… Jerome Axensalva BE/OP16/12/2011 MDI meeting6 Shielding supporting pins

What is proposed 2: …to guide and support the shielding rings… Jerome Axensalva BE/OP16/12/2011 MDI meeting7 Shielding support

What is Proposed 3: … and finally a translation equipment to perform the 50 mm In and Out stroke -> double effect hydraulic cylinders. ! Note, that, at this point, grooving's in the yoke are needed to run the hydraulic piping to the inner shielding rings. Jerome Axensalva BE/OP16/12/2011 MDI meeting8 Yoke grooving and hydraulic equipment

What is Proposed 4: Note that the shielding rings are also grooved to house the hydraulic cylinders. Low friction material is in place at the interface between the sliding pins and the shield to minimize the risk of jamming. Jerome Axensalva BE/OP16/12/2011 MDI meeting9 Shielding viewed from backward with yoke material hidden

Manufacturing consideration: The rings are difficult to manufacture and transport in one single piece (Ø max ~ 11 m)… A reasonable solution is to split them into 3 equal sectors and re-assemble them once on the detectors. Jerome Axensalva BE/OP16/12/2011 MDI meeting10

Test Bench: Preliminary tests are proposed on a prototype system to validate the hydraulic and sliding systems… Jerome Axensalva BE/OP16/12/2011 MDI meeting11 Test bench assembly

Test Bench: …and we also need to perform endurance tests on components: hydraulics, low friction pads, motion sensors, etc… Jerome Axensalva BE/OP16/12/2011 MDI meeting12 Test bench assembly

Test Bench: View from the bottom, grooves for hydraulic piping Jerome Axensalva BE/OP16/12/2011 MDI meeting13 Test bench: grooves in the dummy shield part and hydraulic piping

Test Bench: Hydraulic cylinders. Jerome Axensalva BE/OP16/12/2011 MDI meeting14 Test budget: ~ kCHF

Questions: Is this concept compatible with the yoke’s magnetic field (Threads, Grooves, Piping fixes, … ) ? Do we really have 100 mm of the yoke’s material available ? Can we anticipate a clearance between the fixed coils rings and the moveable shield rings of 5 mm ? Need to evaluate the stress and deformations of the yoke around the sliding pins threads -> need to know the exact yoke material. Radiation levels compatible with the hydraulic components ? (piston rings of the hydraulic cylinders are made of synthetic material). Failure mode(s) ? Redundancy ? Seismic constraints ? Cavern wall movements transmitted to the detectors ? (hydraulic circuits opened/relieved or not during operation) ? … Jerome Axensalva BE/OP16/12/2011 MDI meeting15