LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.

Slides:



Advertisements
Similar presentations
1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Advertisements

February 2009 Summary of Chamonix 09 Steve Myers.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHCC 3rd June 2015 Mike Lamont for the LHC team
Injection test? Mike Lamont For initial discussion.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
1 Copper Stabilizer Continuity Measurement Project Copper Stabilizer Continuity Measurement Status & Plans – May 2011 MPE-TM – 12 May 2011 M. Koratzinos,
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
PostMortem Workshop January LHC “Post Mortem” Workshop: Introduction Initiative by Robin Lauckner, Adriaan Rijllart and myself, helped by many other.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
Status of the LHC Mike Lamont for the LHC team. LS1 - descent into the underworld again.
RBAC Content: LHC Operational Mode Piquet Roles RBAC Strict LHC Operational mode and CMW Acknowledgements: Pierre C., Wojtek S., Stephen P., Lars J., Verena.
CSCM Project Status and Prospects Andrzej Siemko on behalf of the CSCM project core team: Mike Koratzinos, Jens Steckert, Hugues Thiessen and Arjan Verweij.
M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS… S UPERCONDUCTING CIRCUITS RE - COMMISSIONING AFTER THE 2011 C HRISTMAS BREAK.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Dry runs and cold checkout Markus Albert, Reyes Alemany, Rossano Giachino, Delphine Jacquet, Verena Kain, Belen Salvachua Ferrando, Matteo Solfaroli Camillocci.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
Running scenario 2009/10 Run through components – and then synthesis.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
Quench Detection System R. Denz TE-MPE-EP on behalf of the QPS team.
Latest on the Schedule K. Foraz LMC October 7th, 2009 Wednesday, Oct. 7th 2009K. Foraz - LMC.
1 J. Mourao (TE/MPE/CP) Enhanced DQHDS functionality  Status for 2011  Increase Magnet diagnostic capabilities  Our proposals.
MPE activities within MP3 Arjan Verweij A. Verweij, MPE review, 2 June 2015 The questions: 1. Define the scope of work for your activity 2. Structure of.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
New projects, priorities and main objectives for /12/15 TE-MPE Annual Meeting1.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
CERN Report R-D Heuer ECFA, November Scientific Strategy Implementation of all four European Strategy high priority items Implementation of a diverse.
MPE Workshop for LS1 Summary of Global Activities Thanks to Speakers Arjan Verweij Hugues Thiesen Zinur Charifoulline Kajetan Fuchsberger.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
The prototype test String 2 May 13, 20082Roberto Saban – Academic Training Lecture 1 – Why LHC Hardware Commissioning?
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
CERN TE-MPE-EP, RD, 09-April Quench Protection Systems (QPS) for the LHC R. Denz, TE-MPE-EP Acknowledgements: K. Dahlerup-Petersen, A. Siemko, J.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
MPE Workshop 14/12/2010 Post Mortem Project Status and Plans Arkadiusz Gorzawski (on behalf of the PMA team)
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Powering LHC magnets version 30/3/2007.
Minimum Hardware Commissioning – Disclaimer
12 October 2009 RRB Plenary R.-D. Heuer
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
Powering the LHC Magnets
MPE main activities planned for LS2
Powering from short circuit tests up to nominal
Summary of week 7 Hardware Commissioning:
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
TEST PLANS for HL LHC IT STRING
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Machine Protection Xu Hongliang.
Commissioning of the LHC superconducting magnets systems: Why an LHC Hardware Commissioning? Specificity and complexity of this machine Roberto Saban.
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
Review of hardware commissioning
Presentation transcript:

LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al

July August September October November December January February March April P P2P P4P P6P P May June July August September October November December January February March April May June Machine Check-out V4.1e From 7th November, 2014 MPE & LS1 resources loaded schedules Pressure test Cool-down Flushing, nQPS, ELQA NC Cool-down ELQA PT  1 PT  2 Cool-down ELQA NC Flushing, nQPS, ELQA Cool-down PT  1 NC ELQA Flushing, nQPS, ELQA Cool-down PT  1 NC ELQA Pressure test Flushing, nQPS, ELQA Cool-down ELQA PT  2 NC ELQA CSCM PT  1 PT  2 ELQA CV maintenanc e Cool-down ELQA PT  1 NC Flushing, nQPS, ELQA ELQA CV maintenanc e Cool-down CSCM ELQA Pressure test Beam Commissioning CSCM PT  2 ELQA CSCM PT  2 CSCM PT  2 ELQA PT  1 PT  2 PT  PT  2 Physics PT  1 Courtesy Katy Foraz

CSCM (Copper Stabilizer Continuity Measurement) Connect the two 6 kA/200 V power converters in series Stabilize the sector 20 K so the magnets and bus are not superconducting. Apply a current of a few 100 A to open the bypass diodes Apply a current pulse of 6.5 TeV equivalent and watch carefully Fully qualify magnet bypass = copper stabilizer of the bus-bar + diode + diode leads Bypass contains about 3500 connections/joints per sector!

Signals from 11.1 kA run

CSCM results so far RRR of the busbars as expected The main busbars, including the consolidated joints, behave as expected and are qualified for 6.5 TeV operation. The diodes behave as expected and are qualified for 6.5 TeV operation. The diode leads behave in a not-fully-understood, but rather predictive way, similar to the previous sectors, and are also qualified for 6.5 TeV operation. 7 sectors completed Arjan Verweij, Hugues Thiesen and team

Cool-down - status Sector KCSCM OK Sector 235 KCSCM OK Sector 3426 K Sector 4520 KCSCM OK Sector KCSCM OK Sector KCSCM OK Sector 785 K5 KCSCM OK Sector KCSCM OK Represents a major and successful effort by the cryogenics group

Before powering Electrical quality assurance Cable connection, 2.1 kV, 1.5 kV Quench protection system tests Configuration, triggering, thresholds, heater discharge Energy extraction checks Interlock tests EE, PIC, permit, quench signal… And address the inevitable on-conformities Have to ensure that all circuits are safe to power, all protection functionality is sound. Small team – a lot of ground to cover

QPS Major consolidation and upgrades to the Quench Protection system during LS1 – First major system upgrade since introduction of the nQPS layer in 2009 Essential debugging and testing of all: – Hardware – Firmware – Middle and high-level software “Teething problems during initial exploitation phase to be expected (otherwise something is really wrong …)” Reiner Denz

Operation “Yellow rack” Reiner Denz

17248 items to be tested, 5880 circuit boards programmed! 6160 items to be tested, 5008 circuit boards programmed! Reiner Denz

Powering tests Phase 1 – low current only – preliminary tests and measurements (QPS, energy extraction…) – 60 A, 120 A: low current correctors – 600 A: lattice correction circuits (sextupoles etc.) Phase 2 – Full scale tests – IPQs: individually powered quadrupoles – IPDs: individually powered dipoles – ITs: inner triplets – MB, MQ (mains): dipoles, quadrupoles All circuits taken to nominal current level one by one – Rigorous checks of quench protection, energy extraction, interlocks, power converters…

Main dipoles 800 lb gorilla is the main dipoles – 100 or so quenches expected to get to 6.5 TeV – One so far in sector 67 at around 5.8 TeV S67 1 st training quench

The first (re)training quench S67 After the successful execution of the previous steps, the first ramp to nominal current was executed, leading to the first training quench at a current of 9779 A (corresponding to a bit less than 5.8 TeV) Secondary quenches were detected – A26L74248 A – C26L74235 A – A27L7381 A SM18 data for the first quenching magnet: 3285Quench 1Quench 2 I (A) B (T) E (TeV)5.07.5

Present status: sectors 12 to 45 S12 ElQA completed, powering tests in progress 60/120 A circuits tested 600 A start today Preparation of the mains started and progressing well S23 On the way to 1.9 K S34 Stable at 20 K CSCM between 21 st November and 4 th December S45 CSCM will finish today Magnet alignment in progress Then ElQA and cool-down to 1.9 K

Present status: sectors 56 to 81 S56 ElQA will be completed mid next week S67 Powering tests up to first dipole quench Cooling tower maintenance on-going Powering will resume on Nov.24. Training will resume at the beginning of December S78 Cool-down in progress ElQA in shadow of cooling tower maintenance Powering in the New Year. S81 Powering. Tests will be stopped at the end of this week - to be resumed in January - due to cooling tower maintenance Powering tests well advanced for A Preparation of the mains well advanced

HWC - summary CSCM will be completed on all sectors within a couple of weeks Major QPS upgrade - the debugging of the first sector was important and the result was evident in the following sectors… ELQA, QPS prep. etc. mostly cleared by Christmas. Experience on extensive training on one sector by Christmas – S12 – benchmark… Opening the way to an intensive powering test campaign in the New Year. Big thanks due to a relatively small team: Machine Protection and Electrical Integrity (ELQA, machine protection, QPS, magnets), Power converters, MEF, Operations, Survey… Based on 4.1e - KF

July August September October November December January February March April P P2P P4P P6P P May June July August September October November December January February March April May June Machine Check-out V4.1e From 7th November, 2014 MPE & LS1 resources loaded schedules Pressure test Cool-down Flushing, nQPS, ELQA NC Cool-down ELQA PT  1 PT  2 Cool-down ELQA NC Flushing, nQPS, ELQA Cool-down PT  1 NC ELQA Flushing, nQPS, ELQA Cool-down PT  1 NC ELQA Pressure test Flushing, nQPS, ELQA Cool-down ELQA PT  2 NC ELQA CSCM PT  1 PT  2 ELQA CV maintenanc e Cool-down ELQA PT  1 NC Flushing, nQPS, ELQA ELQA CV maintenanc e Cool-down CSCM ELQA Pressure test Beam Commissioning CSCM PT  2 ELQA CSCM PT  2 CSCM PT  2 ELQA PT  1 PT  2 PT  PT  2 Physics PT  1 Courtesy Katy Foraz RF BEAM DUMPS INJECTION COLLIMATION

Aside from the magnets Beam dumps – Reliability run ongoing Injection kickers – Conditioning, to be OP tested next weekend RF – Conditioning high-voltage, high-power, cavities, LLRF, hardware/controls… Dry runs – Full scale tests of: beam instrumentation, controls, timing, software, interlocks, RF synchronization etc. from CCC Plus: survey, vacuum, transverse feedback, collimators…

TT60 Access system tests: 8/9 Nov. DSO tests: 15/16 Nov. Transfer line tests: 22/23 Nov. Transfer line tests this weekend

2015 Q1/Q2 FIRST BEAM 9 th MARCH SCRUBBING FOR 50 ns SCRUBBING FOR 25 ns

2015 Q3/Q4

2015 version 0.5 PhaseDays Initial Commissioning56 Scrubbing23 Early special physics run (LHCf/VdM)5 Proton physics 50 ns Proton physics 25 ns – phase 144 Change in beta* 5 Proton physics phase 2 (including ramp-up) 44 Special physics runs (TOTEM/VdM) Intermediate energy run - to be scheduled 7 Machine development19 Technical stops15 Technical stop recovery6 Ion setup/Ion run Total280 (40 weeks)

Conclusions Steady progress but little contingency left: – Cool-down has gone well – CSCM: additional overhead, but invaluable, 7/8 complete – excellent results – Important commissioning/debugging of other systems – Powering tests thus far have gone well Most of the preparation work will completed in 2014, opening the way to intensive powering test campaign in 2015 – Experience with training in S12 will be the benchmark