Presentation is loading. Please wait.

Presentation is loading. Please wait.

Latest on the Schedule K. Foraz LMC October 7th, 2009 Wednesday, Oct. 7th 2009K. Foraz - LMC.

Similar presentations


Presentation on theme: "Latest on the Schedule K. Foraz LMC October 7th, 2009 Wednesday, Oct. 7th 2009K. Foraz - LMC."— Presentation transcript:

1 Latest on the Schedule K. Foraz LMC October 7th, 2009 Wednesday, Oct. 7th 2009K. Foraz - LMC

2 Progress since September 9th Sector 12: QPS IST finishing. The first sector took longer than expected, and its experiment shows that 3 steps are needed for the full commissioning of the nQPS system. But the results are there. Powering tests phase 2 in progress Sector 23 ELQA at cold finished nPST racks installed, the tests for 2kA will follow the 6kA tests in sector 78  Powering phase 2 of the mains will start in wk. 43 (2 wks. of delay w.r.t September 9 th ) Sector 34 DSLC filling this week-end, boil-off will be done next week, 2 wks. of delay w.r.t September 9 th (Logistic) Sector 45 ELQA at cold finishing, some delays due to DFBA consolidation (valves and filter) Powering test, pahse 1 just starting 1.5 wks. of delay w.r.t September 9 th Wednesday, Oct. 7th 2009K. Foraz - LMC

3 Progress since September 9th Sector 56: ELQA at cold finished Powering tests phase 2 will start this week. 2 wks. of delay w.r.t September 9 th Is this coming from the DFBA consolidation ??? Sector 67 Boil-off in progress- 2 wks. of delay w.r.t September 9 th (Logistic) Sector 78 ELQA at cold finished nQPS tests at 2kA in progress Powering tests phase 2 in progress 2 wks. of delay w.r.t September 9 th Is this coming from the DFBA consolidation ??? Sector 81 ELQA at cold in progress, some delays due to DFBA consolidation 1 wk. of delay w.r.t September 9 th Wednesday, Oct. 7th 2009K. Foraz - LMC

4 Schedule outcomes Powering phase 2 – durations (number of shifts): the experiment of sector 12 shows that the number of shifts was overestimated, – but the experiment of sector 12 shows that about two weeks are needed to commission the system at 2kA & 6kA (part of the powering tests). Wednesday, Oct. 7th 2009K. Foraz - LMC

5 Powering  2 Updated Schedule Wednesday, Oct. 7th 2009K. Foraz - LMC Cool-down ELQA nQPS installation & IST nQPS tests @2kA &6kA Powering  1 Beam Commissioning 1.5 wks of delay w.r.t September 9 th

6 Remaining activities Doors: PM18 and SPS Floor painting Smoothing and beam vacuum chamber alignment in sector 34 Test of UPS batteries All the machine areas have been cleaned again, all the “alone” materials have been removed. So please keep the areas clean. Wednesday, Oct. 7th 2009K. Foraz - LMC

7 Conclusion Machine cold in wk.41 Powering tests phase 2 – Experiment of the first sector was very good – Durations (in term of shifts) were overestimated – New tests to be included for the nQPS – End of powering tests phase 2 = wk.47 (+1.5wks) Wednesday, Oct. 7th 2009K. Foraz - LMC


Download ppt "Latest on the Schedule K. Foraz LMC October 7th, 2009 Wednesday, Oct. 7th 2009K. Foraz - LMC."

Similar presentations


Ads by Google