Contents Jason Tarrant STFC Aim of Presentation to show: l Problem of compressors located at south shield wall l Description of compressor layout and services.

Slides:



Advertisements
Similar presentations
West Wall Compressor Requirements West Wall Mezzanine Move compressors to the West Wall to distance from magnetic field Find compressor position on West.
Advertisements

TPC Proposal for the 35 Ton Liquid Argon Test Abstract We propose to equip the 35 ton cryostat with one APA and two CPA’s, and all the necessary equipment.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006.
Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
1 G4MICE studies of PID transverse acceptance MICE video conference Rikard Sandström.
MICE VC 17 Aug MICE MAGNETIC FIELDS & SHIELDS J. H. Cobb & H. Witte Oxford University Magnet fields for MICE (VI) calculated including magnetic shield.
1 RAL Integration Issues MICE Collaboration Meeting, Osaka, August 1-3, 2004 Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Operational and Technical Requirements Rob Connatser Chief Instrument Project Engineer November 2014.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
Shielding the Weiner PSU 7 May 2013 Kiril Marinov ASTeC, MaRS, DL 1.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE Integration Engineering Jason Tarrant - STFC l Contents »South Mezzanine change summary »Integration Envelope Model »A/C Move »Maus Geometry »AFC.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
MICE CM32 8 th February 2012 Magnet Group Report Vicky Bayliss Victoria Blackmore John Cobb Mike Courthold Roy Preece Mike Zisman 1.
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
Undulator Orientation & Electron Beam Spacing Should the undulator frames be toward the central aisle or the tunnel walls? What is the optimum spacing.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
MICE Integration Engineering Jason Tarrant - STFC l Contents »Device Interfaces – General »AFC »Spectrometer Solenoids »RFCC »EMR / KL »South Mezzanine.
Some Thoughts on Magnetic Measurements for MICE Michael A. Green Lawrence Berkeley Laboratory Berkeley CA 94720, USA.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
PRY Implementation - Contents l Fit with Experimental Devices (& services connections) l Fit with Tracker Cryo l Fit with Floor & Trench l Fit with Mezzanine.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 Mice Collaboration Meeting CM28 Bankya Palace Spa Hotel, Sofia, Bulgaria 3 rd -8 th Oct 2010 Daresbury Laboratory Spectrometer Report Authors : Ian Mullacrane.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
MICE CM35 Status and Goals Alain Blondel 1 WELCOME TO MICE CM35! – Status and Goals - Many thanks to Chris Rogers, Debbie Loader and Rose Hayes for taking.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
PID PC 7th Sept MICE MAGNETIC FIELDS & SHIELDS J. H. Cobb & H. Witte Oxford University Magnet fields for MICE (VI) calculated including magnetic.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 Collaboration Meeting 33 - Glasgow 26 th June 2012 Design Layout Andrew Moss for Alan Grant, STFC.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE CM32 25 th February 2012 Magnet Group Report Vicky Bayliss Victoria Blackmore John Cobb Mike Courthold Roy Preece Mike Zisman 1.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
CMTF GROUNDING FOR PIP-II K. Carlson PXIE Electrical Coordination Meeting December 19 th, 2013.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Joint Institute for Nuclear Research Deformations and stresses in the flux return yoke A.Efremov, Yu.Lobanov, A.Makarov Darmstadt,
Magnetic Field Engineering Update CM36 IIT Craig Macwaters 17/6/13 1.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
1 Target Station Design Dan Wilcox February 2012.
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
S A Griffiths CM42 June 2015 Electrical & Control.
Update on PANDA solenoid design
Miscellaneous Topics MEC Session, CM March 2017 at GSI J. Lühning, GSI
RF Layout 3pi/2 for Discussion
MICE Partial Return Yoke Mechanical Design
Step IV PRY Preparation - Contents
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Extract from today’s talk given to DCB
Rack Placement Chopper Workshop
Presentation transcript:

Contents Jason Tarrant STFC Aim of Presentation to show: l Problem of compressors located at south shield wall l Description of compressor layout and services routing at west wall l Work involved

Current Compressor Location Current Proposed Compressor Position Under South Mezzanine Water and power services already installed for compressors South shield wall

Magnetic Field Analysis Magnetic Field Plots for Step IV & VI Around South Shield Wall Area (V Bayliss CM33) Step IV Step VI Level requires 5 mm Fe / 1 mm mumetal shielding

Magnetic Shielding of Compressor Magnetic Shielding Cabinet for Compressor as South Shield Wall Location Labyrinth cable entry/exit 5 mm Iron + 1 mm mumetal Compressor Only suitable for Step IV at west end of the South Mezzanine, Step VI magnetic field too strong £11,500 – £13,000 each! 19 Compressors (IV) = £218k (~$350k) min.

Current West Wall Layout Current West Wall Configuration West End Stairs Services Distribution Panel West Wall North Mezzanine

Current West Wall Layout Area at West Wall for Device Assembly & Preparation Potterax Door Assembly & Preparation Area Installation Path Spectrometer Solenoid with Tandem Lifting Beam (at crane extent) Beam dump

Proposed Compressor Layout Provisional West Wall Compressor Layout (J Webb) Compressor spacing allows ‘transplant’ of existing services to west wall with minimum of reconfiguration or manufacture of new services runs

Compressor Line Routing Different Routing Layouts l Cryomech 40 m (purple) / Sumitomo 30 m (yellow). Adv = Only 4 x Sumitomos crossing main assembly area. Disadv = 4 x Sumitomos crossing assembly area. Cryomechs at 40 m (30 m max w/o losses). Hoses connected on north side in way of moving platforms (hence alternative red hoses shown). l Cryomech 35 m (green) / Sumitomo 30 m (yellow). Adv = Cryomech hoses closer to 30 m. Disadv = Most hoses cross assembly area, require false floor. l Cryomech 30 m(black) / Sumitomo 30 m (white). Adv = Cryomech & Sumitomo at preferred length. They are not routed across the assembly area. Disadv = Cryomech hoses will have to form bridge over ‘landing’ just inside Potterax door. Full West Mezzanine required to move 6 Step IV compressors to south side.

Proposed Step IV Scheme Proposal for Step IV Compressor Layout at West Wall West wall mezzanine Sumitomo hose for Tracker cryo (max 28.5m) Services bridge Alternative position for stairs Cryomech hose for device cryo (max 28.5m)

Proposed Step IV Scheme SPECTROMETER SOLENOID AND TANDEM LIFTING FRAME STAIRS NEED TO BE REMOVED TEMPORARILY WHEN DEVICES ARE TO BE MOVED INTO COOLING CHANNEL DEVICES WILL NEED TO BE ROLLED INTO HALL PAST SERVICES BRIDGE UPON DELIVERY BEAM DUMP

To Do To Investigate l Ensure magnetic field is low enough not to affect compressors in west wall position l Can all cold heads / compressors accept an extra few metres of line temporarily, i.e. when devices pulled off-line on moving platforms (non operational – keep cold e.g. <50 ºK) l Ensure assembly area is big enough and that stairs & services bridge are compatible with device assembly and installation To Design l Optimise routing & length of hoses and power cables from compressors to cryo-heads etc to minimise excess. l Structure to manage 38 to 62 relatively large and stiff hoses + power services l West mezzanine and stairs

To Do l Installation l Remove current stairs & PPS cage l Install west mezzanine platform, stairs & new PPS l ‘Transplant’ services from south mezzanine l Reroute water feeds l Install services management & compressor supports l Fit compressors l Run hoses & power to devices as required

Finally Conclusion l 30 m hoses (no performance losses) can be run from west wall to devices with minimal compromise (reduced assembly area) l Compressor layout (with mezzanine) allows easy & safe access to 2x high compressors l Structural work (mezzanine, stairs, PPS) significant but not expensive in comparison to 19x compressor magnetic shielding cabinets l Capacity in solution for Step V & VI compressors l If magnetic fields turn out to be too high at any step on west wall and there are no other solutions then magnetic shielding may be implemented in this configuration