Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, 2001. 1 The Expanded Very Large Array Phase II Baseline Plan and Constraints.

Slides:



Advertisements
Similar presentations
1 National Radio Astronomy Observatory The EVLA -- Status, Future Rick Perley National Radio Astronomy Observatory.
Advertisements

National Radio Astronomy Observatory June 13/14, 2005 EVLA Phase II Proposal Review EVLA Phase II Computing Development Bryan Butler (EVLA System Engineer.
CSV Plan status Robert Laing ESO Science IPT. 2 Recent changes Complete rewrite to take account of rebaselining and revised delivery schedule Proposal.
Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array EVLA Observations of.
1 National Radio Astronomy Observatory EVLA Status -- Jim Ulvestad, for Mark McKinnon, Rick Perley, and the EVLA Team.
2000/9/ jdr1 VLBA Upgrade: Scientific, Observational, and Technical Requirements Jonathan D. Romney NRAO, Socorro NRAO Long-Range Planning Retreat.
Jim UlvestadEVLA Mid-Project Review May 11-12, EVLA Operations Jim Ulvestad Array Science Center Concept (Requirements) Staffing and Cost Plans.
J.M. Wrobel - 25 June 2002 PROPOSALS 1 PROPOSAL WRITING TUTORIAL Outline 30 minutes: Lecture on Generic Issues 60 minutes: Small Groups Write Proposals.
C. ChandlerEVLA Advisory Committee Meeting September 6-7, Scientific Commissioning Plan Claire Chandler.
Multiwavelength Continuum Survey of Protostellar Disks in Ophiuchus Left: Submillimeter Array (SMA) aperture synthesis images of 870 μm (350 GHz) continuum.
System Planning- Preliminary investigation
National Radio Astronomy Observatory May 17, 2006 – Legacy Projects Workshop VLA/VLBA Large Projects Jim Ulvestad Assistant Director, NRAO.
EVLA Early Science: Shared Risk Observing EVLA Advisory Committee Meeting, March 19-20, 2009 Claire Chandler Deputy AD for Science, NM Ops.
Wideband Imaging and Measurements ASTRONOMY AND SPACE SCIENCE Jamie Stevens | ATCA Senior Systems Scientist / ATCA Lead Scientist 2 October 2014.
November 2009, Lunch talk The most compact E configuration for the EVLA. L. Kogan, G. Stanzione, J. Ott, F. Owen National Radio Astronomy Observatory Socorro,
EVLA Overall System Specifications Rick Perley EVLA Project Scientist.
Cycle-3 Capabilities and the OT Andy Biggs ALMA Regional Centre, ESO.
Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array New VLBA capabilities.
The Expanded Very Large Array: Phase I Science and Technical Requirements Rick Perley NRAO - Socorro.
Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array Meeting Summary Richard.
Designing Experiments T. Venturi Istituto di Radioastronomia, Bologna, INAF ERIS, Manchester, 9 September 2005.
Correlator Growth Path EVLA Advisory Committee Meeting, March 19-20, 2009 Michael P. Rupen Project Scientist for WIDAR.
JVLA capabilities to be offered for semester 2013A Claire Chandler.
2 nd convergence workshop: introduction R. T. Schilizzi Penticton 22 July 2004.
Moscow presentation, Sept, 2007 L. Kogan National Radio Astronomy Observatory, Socorro, NM, USA EVLA, ALMA –the most important NRAO projects.
EVLA Transition to Science Operations: An Overview EVLA Advisory Committee Meeting, March 19-20, 2009 Bob Dickman AD, NM Operations.
Rick PerleyEVLA Advisory Panel Meeting May , Scientific Impact of Descopes Rick Perley.
Imaging Molecular Gas in a Nearby Starburst Galaxy NGC 3256, a nearby luminous infrared galaxy, as imaged by the SMA. (Left) Integrated CO(2-1) intensity.
Answers from the Working Group on AGN and jets G. Moellenbrock, J. Romney, H. Schmitt, V. Altunin, J. Anderson, K. Kellermann, D. Jones, J. Machalski,
SAGE meeting Socorro, May 22-23, 2007 EVLA Science Operations: the Array Science Center Claire Chandler NRAO/Socorro.
Summary of the Paris SKA Meeting 4-8 September 2006 R. T. Schilizzi.
Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array Observing with NRAO.
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
Rick PerleyNSF Mid-Project Review May 11-12, Scientific Impact of Descopes Rick Perley.
The North America Array Technology Development and the Realization of the SKA-High Steven T. Myers & Jim Ulvestad NRAO 15 Oct 2009 USSKA Consortium Meeting.
03/6/121 Using the VLBA for Spacecraft Navigation Jonathan Romney National Radio Astronomy Observatory VLBA 10 th Anniversary 2003 June 9 – 12.
2005/7/131 Plans and Options for e-VLBI on the VLBA Jon Romney NRAO, Socorro 4 th e-VLBI Workshop 2005 July 13.
UlvestadEVLA Advisory Committee Meeting September 6-7, Future EVLA Operations Jim Ulvestad.
Rosie Bolton 2 nd SKADS Workshop October 2007 SKADS System Design and Costing: Update and next steps Rosie Bolton University of Cambridge.
R. HaywardEVLA Feeds CDR – Project Budget & Schedule 17 Feb EVLA Feeds CDR Project Schedule & Budget.
Rick PerleyEVLA Front-End CDR – On the Sky Tests April 24, EVLA Front-End CDR On the Sky Tests.
Frazer OwenNSF EVLA Mid-Project Review May 11-12, Transition to EVLA
Rick PerleyEVLA Advisory Committee Meeting December 14 – 15, EVLA `Descoping’ Options Rick Perley.
10 January 2006AAS EVLA Town Hall Meeting1 The EVLA: A North American Partnership The EVLA Project on the Web
P.NapierEVLA Advisory Committee, 10 June, EVLA ADVISORY COMMITTEE PROJECT OVERVIEW Scope Organization Schedule Budget, personnel.
Jim UlvestadEVLA Advisory Committee Meeting May 8-9, EVLA Operations Jim Ulvestad Array Science Center Concept Requirements Staffing and Cost Plans.
Michael RupenEVLA Phase II Definition Meeting Aug 23 – 25, EVLA Phase II Scientific Overview Michael P. Rupen.
International Telecommunication Union Document WRC-15-IRWSP-15/8-E 3 September 2015 English only 3 rd ITU INTER-REGIONAL WORKSHOP ON WRC-15 PREPARATION.
WIDAR Correlator Options and Potential Craig Walker NRAO Socorro U.S. VLBI Technical Coordination Meeting May 14-15, 2007.
The North America Array Technology Development and the Realization of the SKA-High Steven T. Myers NRAO 14 May 2009 USSKA Consortium Meeting Washington,
Atacama Large Millimeter/submillimeter Array Karl G. Jansky Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array ngVLA: Reconfigurability.
NRAO VLA Archive Survey
EVLA Spectral-Line Science Below 1200 MHz
EVLA Basic Operations Jim Ulvestad
EVLA Availability - or - When Can I Use It?
EVLA Project Peter Napier
VLA/VLBA INTEGRATION With appropriate outfitting, the VLA+NMA+VLBA could be one integrated instrument covering all resolutions from arcminutes to well.
Rick Perley National Radio Astronomy Observatory
Observational Astronomy
Observational Astronomy
Shared Risk Observing Claire Chandler EVLA SSS Review, June 5, 2009
VLA to EVLA Transition Plan
Some Illustrative Use Cases
Gustaaf van Moorsel September 9, 2003
Shared Risk Science with the EVLA
EVLA Operations Jim Ulvestad
Correlator Growth Path
NMA and E-array Progress
EVLA Construction Status
Rick Perley NRAO - Socorro
Presentation transcript:

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, The Expanded Very Large Array Phase II Baseline Plan and Constraints

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Why Phase 2? Why is the VLA Expansion Project split into two phases? Historically: –Preparation for the 1990 Decadal Panel indicated a budget for the whole ‘Upgrade’ would be > $70M. –Administration declared this too large, and broke the project into two ~equal pieces.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Why Phase 2? Regrettably, neither half was funded in the 1990s. When we began to prepare for the 2000 Decadal Panel process, it was decided to retain the distinction. This two-phase approach makes sense.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Why Phase 2? Phase I: An upgrade of an existing facility, using modern technologies. –Includes items for which there is broad community support. Phase II: An expansion to new configurations, with new stations/antennas. –Includes items which need more study, more discussion, more thought.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Why Phase 2? However, the realities of budgets and timescales have blurred this distinction. Migration of items from Phase I to Phase II has occurred, and may continue. Reverse migration is conceivable …

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Phase II Baseline Plan There are currently four components in the baseline plan: 1.Improving resolution by a factor ~10 2.Providing continuous frequency coverage between ~300 MHz and 1000 MHz 3.Improving large-scale imaging capability 4.Incorporating the VLBA

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Improving Resolution Goals: –Improve resolution by a factor ~10. –Attain image fidelity as good as that from the existing VLA. Achieve this by: –Addition of new stations with distances up to ~250 Km. –Incorporation of two nearest VLBA stations.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Improving Resolution Sensitivity-Resolution Synergy –Phase I will improve VLA sensitivity by large factors – 2 to 20 (continuum modes), depending on band. –The full science potential of this increase in sensitivity cannot be attained without a similar increase in resolution. –High fidelity imaging of thermal objects on mas scales will be enabled.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Low-Frequency Coverage The goal is to implement a system to permit full frequency coverage from ~300 MHz to 1 GHz. This item is a transfer from Phase I. Why? –Budget Overrun! –Implementation of an efficient, wide-band low- frequency facility on the VLA antennas is difficult. –Details will be given in my later talk.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, The ‘E’-Configuration The goal is to improve the VLA’s imaging performance for large-scale, low-brightness emission. Achieve this by construction of a new configuration with maximum baselines of ~250 meters. Various arrangements to ‘dense pack’ the antennas have been proposed.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, The ‘E’-Configuration This item is a ‘transfer’ from Phase I. Why? –Cost (~$5M) –Concerns that ‘E’ configuration will not add sufficient new capabilities over ‘D’. –Concerns that other facilities can provide the imaging performance on these scales. Frazer will be advancing the case of this component in a later talk.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Inclusion of the VLBA A long-range goal of the NRAO is to ‘real-time’ the VLBA. Rapid advances in wide-band fiber optic transmission suggest that real-time operation of the VLBA is within the near future. The VLBA needs short spacings to achieve better imaging performance. –The ‘New Mexico Array’ antennas can provide these spacings.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Inclusion of the VLBA These arguments suggest inclusion of a real-time VLBA within the EVLA Project. –Note that inclusion of PT and LA has always been in the plan for the New Mexico Array. –Full inclusion would be an extension to the plan presented to the Decadal Panel. –It is critical at this stage to ensure that our planning does not exclude eventual incorporation of ALL VLBA antennas into a real-time system.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Practical Matters We must decide the relative importance of these components. We must balance the competing demands of performance, cost, and timescale. –This is particularly true of the ‘New Mexico Array’ (which in the opinion of the Project Scientist is the defining component of Phase II)

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Phase II Cost Is there a cost ceiling to Phase II? Probably not … –The suggested budget by the Decadal Panel was $140M – for ALL the EVLA. –The current budget for Phase I is ~$70M. A well-justified increase for Phase II should be presentable!

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Phase II Cost What are the rough cost estimates for these four components: –New Mexico Array: $5.9M/antenna + fiber. Fiber burial costs of ~$20M! Cost of renting unknown. –E-Configuration: $3 – 5M. –Sub-L-band: $7M (?) –VLBA inclusion: ???

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Phase II Timescale How soon should Phase II begin? Right away (The ASAP Plan), or After some development and thought? –Advantages of ‘ASAP’: Existing (‘safe’) technology sufficient Science goals are great Could finish by 2010, along with Phase I. Better synchronism with LOFAR and SKA projects.

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Phase II Timescale –Advantages of a more cautious approach: NSF funding probabilities … Development of new technologies may offer better solutions at lower cost. How fast is ‘ASAP’? –6 months to write a decent proposal. –6 months for submission, review, etc. –Development funding could start in 2003? –Construction money FY2005. 

Rick PerleyEVLA Phase II Definition Meeting Aug 23 – 25, Meeting Goals The primary purpose of this meeting is to clarify these competing issues, and give us a sense of: –What should Phase II include –How fast should we should implement it.