Document number Anticipated Impacts for FRRS Pilot Program ERCOT TAC Meeting September 7, 2012.

Slides:



Advertisements
Similar presentations
In the Post 06 Environment November 9, 2006 Jim Eber Demand Response.
Advertisements

Achieving Price-Responsive Demand in New England Henry Yoshimura Director, Demand Resource Strategy ISO New England National Town Meeting on Demand Response.
DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Early Lessons Learned from DOE-EPRI Framework Experience Melissa Chan MA DPU.
ENERGY VALUE. Summary  Operational Value is a primary component in the Net Market Value (NMV) calculation used to rank competing resources in the RPS.
11 Presentation for ERCOT ETWG FERC Notice of Proposed Rulemaking: Frequency Regulation Compensation in the Organized Wholesale Power Markets (RM )
Western Regulation Usage and Pilot Program Results 1.
Preliminary Impacts of Wind Power Integration in the Hydro-Qubec System.
Demand Response in Connecticut Presented by: Bob Laurita ISO New England December 2, 2004.
DISTRIBUTION EFFICIENCY UPDATE 1. Distribution Efficiency – Quick Review Tier 1 study (19 circuits) completed in 2011 – Four circuits identified for pilot.
Toward a Sustainable Future Name of Conference, Event, or Audience Date Presenter’s Name | ©2011 Synapse Energy Economics Inc. All.
Susan Covino Senior Consultant, Emerging Markets March 31, 2015
ENERGY ONLY RESOURCES & THE RPS CALCULATOR. Deliverability Overview Most resources procured to date have been procured to be fully deliverable – CAISO.
INTEGRATION COST. Integration Cost in RPS Calculator While “Integration Cost” is included in NMV formulation, the Commission stated that the Integration.
National Renewable Energy Laboratory Innovation for Our Energy Future * NREL July 5, 2011 Tradeoffs and Synergies between CSP and PV at High Grid Penetration.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
Long Term Study Task Force Update to ETWG ERCOT Long-Term Study: Scenarios, New Software, and Emerging Technology Assumptions January 27, 2012.
Floyd Trefny Director of Product Development Future of Demand Response In ERCOT A Presentation to the Workshop – September 15, 2006 Project Number
Pricing Enabled by AMI What Types? What are the Benefits? Dr. Steven D. Braithwait Christensen Associates Energy Consulting EUCI Webinar September 12,
Loads in SCED Comments submitted by Luminant Energy Company, LLC.
Market Based Solutions for Demand Response Providers Today and the Future Alice Jackson Occidental Energy Ventures Corp.
Julia Matevosyan, Resource Adequacy January, 2014 Application of KERMIT in the DOE LTS process.
Document number DNV KEMA KERMIT Overview ERCOT Joint Regional Planning Group / Long Term Study Task Force Austin, TX October12,
Crossing Methodological Borders to Develop and Implement an Approach for Determining the Value of Energy Efficiency R&D Programs Presented at the American.
PJM©2013www.pjm.com Deployment of smart-grid technologies – Technology and market challenges Stu Bresler VP, Market Operations PJM Interconnection University.
COMMUNITY CHOICE AGGREGATION: TECHNICAL STUDY RESULTS Peninsula Clean Energy September 24,2015.
Demand Response: Keeping the Power Flowing in Southwest Connecticut Presented by: Henry Yoshimura Manager, Demand Response ISO New England September 30,
1 The Costs of Participating in Restructured Wholesale Markets American Public Power Association February 5, 2007 William M. Bateman Robert C. Smith.
“Demand Response: Completing the Link Between Wholesale and Retail Pricing” Paul Crumrine Director, Regulatory Strategies & Services Institute for Regulatory.
Demand Response Workshop September 15, Definitions are important Demand response –“Changes in electricity usage by end-use customers from their.
Linking the Wholesale and Retail Markets through Dynamic Retail Pricing Presented by: Henry Yoshimura Manager, Demand Response ISO New England September.
NPRR XXX: PRR 307 Inclusion in Nodal…Part II. Questions Raised 06/26/06 Section 3 –COP (resource parameters) –CLR participation limits –Telemetry Requirements.
PJM©2013www.pjm.com Economic DR participation in energy market ERCOT April 14, 2014 Pete Langbein.
1 October 2003 Electricity Markets Regional Evolution Randy Berry
1 1 Beacon Power Corporation Energy Storage – Regulation Issues Prepared for: Emerging Technologies Working Group January 5, 2011.
Kevin Hanson Doug Murray Jenell Katheiser Long Term Study Scenarios and Generation Expansion Update April, 2012.
Chicago Advanced Energy Demand Response & CSP Evolution Kellen Bollettino Comverge Inc. 10/23/14.
Demand Response: What It Is and Why It’s Important 2007 APPA National Conference San Antonio, Texas June 26, :00 a.m. to Noon Glenn M. Wilson Director.
Final Report on Fast Responding Regulation Service (FRRS) Pilot Project TAC March 27th, 2014.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
Power Association of Northern California Maintaining Grid Reliability In An Uncertain Era May 16, 2011 PG&E Conference Center Jim Mcintosh Director, Executive.
Outstanding Issues & Action Items 1.Obligations to Honor Ancillary Services Commitments 2.Variable ERCOT Bias 3.Sign reversals of the Regulation Signal.
PDCWG Report to ROS David Kee Chair CPS Energy Sydney Niemeyer Vice Chair NRG Energy.
ERCOT Pilot Project for Fast Responding Regulation Service (FRRS) August 8, 2012 PDCWG August 9, 2012 ETWG/QMWG.
OPSI Annual Meeting October 13, Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be.
Electric Capacity Market Performance with Generation Investment and Renewables Cynthia Bothwell Benjamin Hobbs Johns Hopkins University Work Supported.
BAL-001-TRE-01 ERCOT CPS2 R2 Waiver Regional Variance April 16, 2009 Sydney Niemeyer.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
Economic Analysis Proposed Scope ERCOT RPG Meeting September 17, 2010.
Long Term Study Transmission Results May 21 st, 2013.
1 WMS Report TO TAC April In Brief Two Working Group reports Two Working Group reports Two Task Force Reports Two Task Force Reports BENA presentation.
Future Ancillary Services Team (FAST) Update April 24, 2014 TAC Meeting 1.
INTEGRATING WIND ENERGY WITH ELECTRIC SYSTEMS ERIC HIRST Consultant in Electric-Industry Restructuring Bellingham, WA December.
Analysis for the Determination of X, Y, and Z for Compliance Monitoring NATF.
Real Time Balancing (RTB) & Resource Plan Statuses Change to the QSE practice of showing offline units as online and available ERCOT Presentation to ROS.
Preliminary Report on ERCOT Pilot Project for Fast Responding Regulation Service (FRRS) June 12th, 2013.
ERCOT Pilot Project for Fast Responding Regulation Service (FRRS) June 13, 2012 WMS and June 14, 2012 ROS.
ERCOT Pilot Project for Fast Responding Regulation Service (FRRS) PDCWG April 26, 2013.
April 13, 2007 Regional Planning Group Meeting Wind Impact/Integration Analysis Warren Lasher Regional Planning.
Future Ancillary Services Cost Benefit Analysis Overview Julia Matevosyan February 1, 2016 FAS Workshop.
Weather-Sensitive ERS Pilot Project Proposal March 7, 2013 TAC Meeting.
Draft NPRR Weather Sensitive ERS Loads December 2012.
Current FRRS Language & Explanation of Posted Data
ERCOT Pilot Project for Fast Responding Regulation Service (FRRS)
Pilot Project Concept 30-Minute Emergency Response Service (ERS)
ERCOT – Southern Cross Transmission ROS/WMS Working Group Assignments
Allegheny Power Residential Demand Response Program
Draft 2013 Energy-Efficiency Forecast
Marginal Cost Pricing: Why Is It Important? Have We Achieved It?
Market Pricing Issues: Update
Energy Storage Roadmap & Flexibility Roadmap Information Session
Presentation transcript:

Document number Anticipated Impacts for FRRS Pilot Program ERCOT TAC Meeting September 7, 2012

Agenda  DNV KEMA Introduction  Review Order 755 and Related ISO Experience  Summary of DNV KEMA PJM Fast Response Study  Criteria for FRRS Assessment  Questions 2

Review FERC Order 755  FERC finalized Order 755 last summer and introduces a performance payment to current regulation markets  Performance payment contains two key aspects  Add a regulation market product that rewards regulation resources based on the amount of regulation energy they provide - Basis is that faster resources travel more “MWs” than slower resources thereby doing more work - As a result, this portion of Order 755 is referred to as the “MW-mileage” payment  Base MW-mileage payments for any type of regulation provider on performance - Difficult to separate random generator movements from responses to regulation signals - Other ISOs have developed 2 and 3 statistical metrics to determine how well a generator followed AGC signals  Every system operator is responding to this order in different ways 3

PJM Fast Acting Resources – Project Goals  Establish a platform for these and other long term dynamics / system regulation and frequency response studies of the PJM system and its resources by developing a KERMIT model implementation of the PJM system and calibrating it to observed real time data  Examine the relative performance and impact on system performance of fast versus traditional regulation resources  Simulate and analyze the metric of MW-mileage and response accuracy for resources with different responses to the PJM regulation control signals. 4

PJM Fast Acting Resource – Key Findings / Conclusions  Based on the simulations, the addition of faster regulation resources in 5% increments (from 5% to 50% of the regulation requirement), improved the average CPS1 scores for all studied dates, when compared to the base case simulation results and while keeping the same regulation requirements as in present practice.  Over 12 sample days of simulation, fast resources provided 30% more value than conventional 5

List of Economic / Operational Impacts  Change in net regulation deployment - This is the primary metric for ERCOT and where we expect the majority of benefits / costs to be observed  Leads to Potential Reductions in Procured Regulation Capacity - Use regulation deployments per regulation capacity as metric indicating regulation capacity savings - Weighted ratio of regulation MW-mileage of conventional resources to fast resources is first order (linear) indication of how much less regulation capacity can be procured and still maintain the same system performance  Avoided reserve deployments - Difficult to estimate, would need to make assumptions about what would have happened if FRRS Pilot Program was not in place  Change in administrative costs - Providing two regulation products may increase ERCOT O&M 6

List of Long Term Benefits  These are post pilot long term benefits that could be observed  More efficient dispatch - Measure changes in total MW bid into other ERCOT markets - Generators that no longer participate in regulation market may increase their participation in the real time market - FFRS pilot study first step towards estimating market efficiency benefits; simulations using the pilot data next step to quantify system wide effects  Increased system reliability - Difficult to measure, can track change in average reserve deployments or MW of load lost - Would need to make assumptions about what would have happened if FRRS Pilot Program was not in place 7

Additional Considerations  Need to control results for varying system conditions - Wind and other sources of variability will change from the base case to when the FRRS pilot program is implemented - Generation portfolio can change (e.g. increased wind capacity over course of pilot study, generator builds and retirements) - Market structure and competitiveness of FRRS and Regulation markets - Weather - Industrial and commercial production  And need to examine results based on FRRS pilot program implementation details - FRRS parameters can be examined and modified during the course of the pilot program - ERCOT can examine how sensitive the results are to FRRS implementation  Results can be controlled and examined either through a statistical analysis or via simulations 8