SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.

Slides:



Advertisements
Similar presentations
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
Advertisements

Cryogenics at CERN (LHC)&Helium Inventory Brief review with emphasis given on cryogen management Americas Workshop on Linear Colliders 2014 Fermilab,
L. Tavian, TE/CRG, Page 2 12 th September 2013 Accelerator Consolidation Workshop L. Tavian, TE-CRG.
ZONE 18 CRYOGENICS M. Sanmarti On behalf of AT-ACR-OP section.
ITER Cryoplant System Status
ESS Cryogenic System Process Design Philipp Arnold Section Leader Cryogenics CEC – ICMC 2015 June 29, 2015.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
SOFT 2004 OVERVIEW OF CRYOGENIC TECHNOLOGY FOR THE THERMONUCLEAR FUSION P. DAUGUET, M. BONNETON, P. BRIEND, F. DELCAYRE, B. HILBERT, A. RAVEX Air Liquide.
Test Stands Roger Ruber Uppsala University ESS TAC4 16 Feb
Progress report on the test facility project design and construction P. Schnizer and L. Serio on behalf of bldg. 180 test facility project team members.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Internal review of superconductors and magnet laboratories 2nd part: Infrastructure/Laboratories Cryogenics Klaus Barth (CERN), Vladislav Benda (CERN)
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Project X RD&D Plan Cryogenics Arkadiy Klebaner AAC Meeting February 3, 2009.
Experience from large helium inventory management at CERN ILC Cryogenics and Helium inventory meeting CERN, Wed. 18 th of June 2014 D. Delikaris Technology.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Central He distribution service upgrade status and dedicated He distribution for AD K. Barth on behalf of TE/CRG ADUC and ELENA Meeting Wednesday, September.
AT-ACR B. VULLIERMECSOC Meeting 29 September Cryogenics for LHC Test Benches Safety Aspects Overview of the Test Station Overview of the Operation.
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
TE-CRG Activities D. Delikaris, TE-CRG.
RESEARCH AND DEVELOPMENT FOR FUTURE LHC SUPERCONDUCTING MAGNETS POINT SUR LA STATION D’ESSAIS préparé par Jean-Marc Gheller Steering committee –September.
Crab cavities – cryogenics for SPS and LHC LHC-CC13, 6 th LHC Crab Cavity Workshop – CERN, Geneva, Switzerland 9-11 December 2013 K. Brodzinski on behalf.
TAC2 Alpi consolidation in Cryogenics and Cryomodules.
LCLS-II Cryoplant Overview
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
CRYOGENIC SYSTEM of RAON Chul Jin Choi, Ki Woong Lee Cryogenics and Control Team Accelerator Division 5/23/2013 Chul Jin Choi, Ki Woong Lee Cryogenics.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
Internal review of superconductors and magnet laboratories 2nd part: SM 18 & b.163: current status, weak points, possible improvement Cryogenics Vladislav.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
TE-CRG Activities A. Perin, on behalf on the Cryogenics Group.
ILC Cryogenics: Study of Emergency Action and Recovery - in progress -
Cryogenics storage and distribution
Status, Schedule and EVM for the test facility project
Crab cavities Cryogenics progress for the SPS
HL-LHC IT STRING and Series test of SC link
The HL-LHC Circuits: Global View and Open Questions
Innovative He cycle Francois Millet.
Cryoplant Installation Scope
N. Hasan1, P. Knudsen2 and V. Ganni2
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
SPS cryogenic proximity equipment and SM18 validation
CRYOGENICS – strategy, unavailability root causes and limitations
Preparation of the activities for the LHC Long Shutdown 2
Hollow e- lens, Cryogenic aspects
on behalf of FCC cryogenic team
Overview & baseline of LS2 and roadmap for CRG
ESS RF Development at Uppsala University
Status of the cryogenic system for B180
ILC Cryogenic Systems Draft EDR Plan
TEST PLANS for HL LHC IT STRING
Mathew C. Wright January 26, 2009
ILC Experimental Hall Cryogenics An Overview
ESR2 Process Cycle Design
Conceptual design of the Cryogenic System of Comprehensive Research Facility for Key Fusion Reactor Core Systems Liangbing Hu Sep.4.
Cryogenic upgrade of B165 CRG Status Meeting 16th may 2019
ESR2 Process Cycle Design
Review Bloc 4 and SM18 facilities and upgrade
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

SM18 cryogenics infrastructure upgrade L. Serio TE-CRG

Outline Project definition – Scope of work, limit of supply and interfaces – Requirements and assumptions – Estimation of the cryogenic loads based on Users planning and theoretical loads Benchmarking with measured data Baseline conceptual proposal – Phased implementation – Budget and resources Alternative scenarios parametric study Risks and opportunities L. Serio – TE/CRG

Scope of Work Consolidation and upgrade of the SM18 cryogenic infrastructure for the HL-LHC Project and other large cryogenic capacity needs to cover the period (and beyond ?) The new infrastructure shall: · increase testing rate and parallel testing capabilities -> increase LHe production and 1.8 K pumping capacity · increase availability -> implement redundancy · fulfil cooling needs for IT String (3) (triplet Q, SC link and feed box) -> additional and dedicated equipment L. Serio – TE/CRG

Limits of supply Magnet test stations Vertical Horizontal SC links / IT String (3) Cavity test stations Vertical Horizontal Cryogenic test station GReC Cryogenics production Helium liquefiers / refrigerators compressor stations purification system and balloons L/G He and LN2 common storage Warm and cold pumping units Common valve boxes and TL CWUs Utilities Cooling water Electrical power distribution Industrial controls Limit of supply and interfaces Interfaces Magnet test stations proximity cryogenics Vertical Horizontal SC links / IT String (3) Cavity test stations proximity cryogenics Vertical Horizontal Cryogenic test station GReC Utilities Civil engineering Cooling and ventilation Electrical power distribution Transport and handling Integration Platform and structures Industrial controls L. Serio – TE/CRG

Requirements and assumptions Baseline testing capability/requirement based on foreseen test plan (incl. other limitations) and theoretical loads (Q1-2014)  Magnets: 2 Vertical and 2 Horizontal magnet cold / month (2 powering)  Cavities: 1 cavity test/2 weeks; 1 module test every 6 months  SC link or IT String (3) o Integrated systems testing, commissioning and operation o ‘demanding’ individual systems tests on dedicated facilities  Apply 50 % contingency for o Known unknowns (e.g. unplanned tests, repeated tests and low performing components) o Unknown unknowns L. Serio – TE/CRG

Estimated loads and capacity Mini: lower consumption tests Maxi: no HW limitation – all tests AVG: assumptions and 1 month avg Recommended installed: AVG + 50 % margin Mini: lower consumption tests Maxi: no HW limitation – all tests AVG: assumptions and 1 month avg Recommended installed: AVG + 50 % margin LHe 4.2 K VLP 1.8 K new existing new existing L. Serio – TE/CRG

6 kW Linde 6 kW Linde + new 35 g/s liquefier L. Serio – TE/CRG Cryogenics loads based on users planning [estimated theoretical loads and benchmarking] Delayed start Longer and delayed SD New benchmark point WPU1 & WPU2 WPU1 + WPU2 WPU1 + WPU2 + WPU3 WPU1 + WPU2 WPU1 + WPU2 + WPU3 6 kW Linde + new 10 g/s liquefier

Baseline conceptual proposal 7L. Serio – TE/CRG

Proposed implementation plan 8 Phased approach with available resources (minimisation of risk and investment) : 1.Review tests requirements, milestones and implementation plan 2.Review availability (redundancy) requirements 3.Implement instrumentation (HW and virtual) to control/optimise distribution 4.Upgrade controls (advanced) to improve performance and optimize 5.Upgrade VLP (interconnections) to increase capacity and availability 6.New WPU and CWU 7.New refrigerator done implementing under study on-hold < K < K < 200 kW CWU < K < K < 27 g/s LHe < 300 kW CWU < K < K < 60 g/s LHe < 300 kW CWU production capacity: < K < K < 27 g/s LHe < 200 kW CWU L. Serio – TE/CRG

Budget and resources 9 Estimates for cryogenic production infrastructure – Utilities and civil engineering tbd after reviewing global SM18 UPG project – Doesn’t take into account String 3 resources needs and overlap Budget and resources available for TE/CRG – Conditional to smooth operation and maintenance of the LHC – Conditional to successful implementation in 2016 of new CRG O&M contract L. Serio – TE/CRG

Alternative scenarios parametric study 10L. Serio – TE/CRG Scenarios: 1.Controls/instr. 2.Coupling WPUs 3.WPU3 4.New liq 10 g/s 5.New liq 25 g/s 6.New liq 35 g/s 7.New ref 6 kW BASELINE possible recommended

Risks and opportunities 11 RISKS – Not finalised or changing requirements -> cost against performances (?) Existing test stands: configuration, test rate, planning and required parallelism Contingency for known unknown and unknown unknown What beyond 2024 ? – Resources availability constraints Smooth operation and maintenance of the LHC / New M&O contract ? Other projects (e.g. HL-LHC, SM18 proximity cryogenics, String 3, HIE-ISOLDE) LS2 overlap and conflict – Budget Review of global SM18 UPG requirements and impact on utilities and CEOPPORTUNITIES – String 3 delayed to 2021 / 2022 Proceed with scenario 2 only Delay to 2016 the decision based on a comprehensive review of all costs of SM18 project – Synergies with other projects HL LHC, FAIR (?) L. Serio – TE/CRG

References SM18 upgrade Project Plan – Presentation TE-TM – L. Serio – TE/CRG

boundaries L. Serio – TE/CRG

WPU 1 WPU 2 By-pass valves l LHe dewar Heater New Compressors New cold box HPLP LHe heater 1 heater 2 WPU 3 heater 3 Compressors 6 kW Linde cold box HPLP LHe Dryer Pre/ads SM18 Infrastructure Purification GHe Storage LHe GHe LN2 Storage Precooler By-pass valves L. Serio – TE/CRG

Horizontal magnets Vertical magnets RF 4x h & 2 x v SC link String 3 SC helium Shield GReC CWU 1 CWU 2 CWU 3 Proximity Cryogenics Feed Box L. Serio – TE/CRG

WBS 8 1 PROJECT MANAGEMENT 2 CRYOGENIC PRODUCTION AND DISTRIBUTION kW LINDE LIQUEFIER kW LINDE COMPRESSOR STATION 2.3 new REF or LIQU. 6 kW 2.4 new COMPRESSOR STATION 2.5 CWU CWU new CWU 3100 kW 2.8 main distribution valve box 2.9 main distribution transfer lines 3 PURIFICATION SYSTEM 3.1 Purification system Purification system Recovery compressor Recovery compressor Balloon system 3.6 impure storage 4 STORAGE 4.1 LHe dewar - 25'000 l 4.2 LHe mobile dewar - 10'000 l 4.3 GHe tanks 4.4 LN2 dewars 4.5 new GHe tanks K pumping system 5.1 Warm pumping unit 1 & heater 5.2 Warm pumping Unit 2 & heater 5.3 Refurbished (new) Cold Pumping Unit New Cold Pumping Unit New WPU cold distribution box 5.6 New Warm Pumping Unit 3 6 g/s 5.7 New Cold Pumping Unit 3 6 CONTROLS AND ELECTRICAL 6.1 Controls upgrade 6.2 New refrigerator 6.3 New pumping Unit 6.4 Infrastructure 7 UTILITIES 7.1 Civil engineering 250 m2 7.2 Controls and network upgrade 7.3 Cooling and ventilation 2 MW; 100 kW 7.4 Electrical power and distribution 2 MW 7.5 Transport and Handling 20 t crane L. Serio – TE/CRG

Review of client baseline testing program and consumptions Estimates of the 4.5 and 1.8 K loads based on 2014 last quarter test plan Comparison with measured loads Extrapolation to 2015 – 2026 baseline test program L. Serio – TE/CRG

Benchmark on 2014 tests: 4.5 K L. Serio – TE/CRG

Benchmark on 2014 tests: 1.8 K L. Serio – TE/CRG

Conceptual study ongoing for positioning of cryogenics infrastructure to supply IT String. Very likely that a new building will be required. SM18 SH18 cryogenics SW18 Cooling water & Cryogenics New refrigerator or liquefier New WPU3 New compressor station ? L. Serio – TE/CRG

Phase 3a Cold by-pass for full redundancy between the heaters and WPU’s (check for use of existing interface box valves L. Serio – TE/CRG

Phase 3b (ready for String 3) L. Serio – TE/CRG

Upgrades and loads L. Serio – TE/CRG