FHI 32: FCC tunnel layout and transferline update Tuesday, 9 February 2016 CE Updates: Comparison of 100km Intersecting and Non-Intersecting options New.

Slides:



Advertisements
Similar presentations
Haivan Pass Tunnel Construction Project
Advertisements

版权所有: CMC 1 Sonda-Jherrukh Coal Mine& Power Plant Project.
 Location – Maneri to Uttarkashi, India  Length – 8.56km long, diameter 4.75m  Use – a power tunnel, part of the hydro-electric project on the River.
Tunnelling Methods.
Yellow River Diversion Project Use of Tunnel Boring Machines to Divert the Yellow River, China John Train & Philippa Reed.
Design Parameters.
DUBLIN PORT TUNNEL CONSTRUCTION CHRIS PAGE & THOMAS SMITH 19/03/2009 H24GGY GEOLOGY FOR CIVIL ENGINEERS Dublin Port Tunnel Project.
GROUNDWATER CONTROL.
ENGINEERING GEOLOGY OF THE CHANNEL TUNNEL Richard Rae & Robert Hazelhurst March 2006.
Geological Problems Encountered and Solutions Implemented
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
CFS challenges for a linear collider J.Osborne CERN ILC-GDE Dubna - 4 June 2008 OUTLINE : Introduction Civil Engineering -Geology (water, stability issues.
SOIL, GEOTECHNICAL ENGINEERING AND FOUNDATION ENGINEERING
Foundation Engineering CE 483
3/2011 CFS BTR Global Design Effort 1 Americas Region Civil Design Tom Lackowski.
NATM NEW AUSTRIAN TUNNELING METHOD.
John Osborne GS/SE March 2013
LAGUNA at Fréjus LAGUNA/LAGUNA-LBNO General Meeting March 3 th -5 th, 2011, CERN Eng. Francesco Amberg.
Infrastructure & Operation 27 th May 2015 Infrastructure & Operation 27 th May 2015 Update on optimisation of tunnel footprint and location Charlie Cook.
Other Construction Projects
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
Details of Construction Lecture-2 “Shallow Foundation”
Investigation of FCC position Impacts on Hadron Injectors John Osborne, Charlie Cook, Yung Loo (ARUP) 16/09/2014.
General meeting LAGUNA LAGUNA – Fréjus site
Laughton 7/04 Long Baseline Neutrino Program Tunneling Chris Laughton, Fermilab.
TOT-FCC: Tunnel Optimisation Tool for the Future Circular Collider Introduction and lessons learnt C. Cook, J. Osborne, P. Lebrun, Y. Robert, M. Jones,
Geotechnical & Civil Engineering Studies Future Circular Colliders (FCC)
Department of Civil Engineering,
FCC Tunnel Civil Engineering and Geology John Osborne (CERN GS-SE) 4 April 2014.
Introduction: Excavations and other engineering constructions in the ground are central to many civil and mining projects. Ground reinforcement includes.
November 17, st XFEL / ILC Meeting 1 ILC GLOBAL Design Effort The Current ILC Twin Tunnel Design Wilhelm Bialowons and Nicholas Walker · MPY.
Contents Scope of Work and Work Stages
4.4 SOIL NAILING SOIL NAILING IS A REINFORCEMENT METHOD TO REINFORCE THE GROUND WITH STEEL BARS OR STEEL BARS IN GROUT FILLED HOLES. IT IS MAINLY USED.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
Report from ARUP meeting Andrea Gaddi, CERN Physics Department.
Europe / CERN studies for SB2009 ILC Re-Baseling J.Osborne CERN (CFS & CES) 2009 Linear Collider Workshop of the Americas 28 September - 4 October 2009.
MDI 9 th Meeting - 22 nd January 2016 FCC Experimental Caverns - Feasibility and Excavation C. Cook (GS), J. Osborne (GS),
FCC-hh MDI 5 th Meeting Friday 13 th March 2015 Civil Engineering Layouts for Experimental Caverns – First Draft Charlie Cook (GS), John Osborne (GS)
Infrastructure and Operation meeting 20 th January 2016 Amberg’s Report Summary : Comparison of 100km Intersecting and Non-Intersecting options C. Cook.
Review of FCC tunnel footprint & implementation Introduction & scope Philippe Lebrun Review of FCC tunnel footprint & implementation CERN, 11 June 2015.
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES - 3D VISUALS FOR SURFACE STRUCTURES.
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES John Osborne GS/SE 16 May 2013.
5 December 2011 Task 2 Cavern Study Ground model and 3D cavern layout Matt Sykes Eden Almog Alison Barmas Yung Loo Agnieszka Mazurkiewicz Franky Waldron.
Matt Sykes Andy Kervell Yung Loo Heidi Clough Craig Sturzaker ARUP: Update on GIS Model and tunnel options under lake.
PRESENTED BY- Namrata M. Lolge (09CM16F) M. Tech. 1 st sem NITK.
WP 17.1 Civil Engineering Platform height / vs option Status on M. Manfredi on behalf of WP17.1 team.
Construction Beam Tunnel
Development and Application of High Strength FRP Pipes as Grouted- Reinforcing Members in Slope and Tunnel KSCE Annual Conference and Civil Expo 2004 Daewon.
DIAPHRAGM WALLS.
RISK ASSESSMENT FCC draft, 2. September 2015.
FCC Underground Infrastructure
Civil Engineering for FCC-eh and LHeC
Civil Engineering update - alignment configuration
FCC Civil Engineering Optimisation and Design Development
CLIC Civil Engineering Update
CLIC Civil Engineering Update
FCC Civil Engineering John Osborne, Jo Stanyard, Matt Stuart(SMB - Site Engineering - FAS Section) Cost & schedule Phase 3 - specification 10th May 2017.
FCC Civil Engineering John Osborne & Jo Stanyard (SMB - Site Engineering - FAS Section) FCC week outline 10th May 2017.
Acknowledgements to all FCC study teams
$150K Chicago/ANL seed funding for Braidwood site investigation
CLIC / ILC Collaboration for CFS works
Interaction Region Alternative Layouts
5th FCC Infrastructure & Operation meeting
FCC Civil Engineering update
Latest ILC tunnel cross section May 2017
Tunnelling under lake Geneva
Civil Engineering for FCC-eh IR
CLIC Civil Engineering Update
FCC Week 2019 Civil Engineering Summary
Graduation Project Bracing system for deep excavation.
Presentation transcript:

FHI 32: FCC tunnel layout and transferline update Tuesday, 9 February 2016 CE Updates: Comparison of 100km Intersecting and Non-Intersecting options New interpretation of geology C. Cook (SMB), J. Osborne (SMB),

Intersecting

Non-Intersecting

GADZ interpretations - Prealps

GADZ interpretations - Voirons

GADZ interpretations - Vuache

GADZ interpretations - Jura

Intersecting

Intersecting - New

Non-Intersecting

Non-Intersecting - New

Amberg Report Geological and Geotechnical conditions Risks applicable to FCC options. Basis of 5. and 6. First look at excavation methods for tunnel, shafts and caverns based on varying geological conditions Comparison of options Introduction and description of options Conclusion

3. Geological conditions

4. Handling main geological hazards Ground water Ground water in moraines unknown, boreholes to be used, shaft excavation methods vary (d-walls, piles) Tunnel: Pressure of water in fault zones too high, solution is to use sealing injection umbrellas around tunnel Tunnelling through Moraines Risk that moraine under Lake Geneva and Rhone is deeper than predicted => exploration boreholes, Tunnel Boring Machine (TBM) waterproof up to 20bar Karsts Probes ahead of tunnel to search for Karsts, fill karsts with concrete, mortar or cement. Drainage for karsts filled with water Hydrocarbons Prealpes, Jura and Mandallaz highest risk. Qualified expert (geologist/engineer specialising in natural gas explosions) Rock squeezing Highest risk in Prealpes due to high overburden and possible weaker rock => drill & blast (not TBM) recommended for these tunnel sections

5. Excavation methods Tunnel Molasse TBM best adapted & least expensive method Work rates of 600m/month seem realistic 22 months for an (averaged) 11km section between two points (2 mths for maintenance) Extra 15 months should be allowed between signing TBM contract & beginning of excavation Limestone (Jura, Mandallaz & Prealpes) Drill & blast method recommended Higher flexibility to react to rock squeezing, heavy water inflows, karsts and gas Good conditions – 10-12m/day ( m/month) Drill & blast fronts from both sides not too dissimilar in speed to single TBM drive over the same distance Drill & blast team (google images)

5. Excavation methods Experimental Caverns Excavation sequence based on ‘good’ geological conditions (stable rock) Support: rock bolts, lattice girders and reinforced shotcrete

5. Excavation methods Experimental Caverns Excavation sequence based on ‘moderate’ geological conditions (Flysch and soft clay rock) Support: micro piles, rock bolts, lattice girders and reinforced shotcrete

5. Excavation methods Experimental Caverns

5. Excavation methods Service and access caverns Service Caverns with a span of 20 m and Access Caverns with a span of 15 m excavated like the Experimental Caverns in partial sections (see subchapter 5.2.1). An important point for planning the location of the Service Cavern is the stability of the rock pillar between Experimental Cavern and Service Cavern (see Figure 29). This rock pillar has to transfer the additional burden of half of the two caverns and has to be probably 40 to 50 m wide. The necessary dimension can be determined only after exploring the geological conditions in this area.

5. Excavation methods Experimental Shafts If moraines is firm, cohesive or consolidated => conventional excavation. Lattice girder rings, shotcrete and steel mesh as support If loose or below water table => pile walls up to 25m deep, diaphragm walls >25m Through moraine layer Through molasse layer Drill & blast recommended. Support similar to moraines but less required

5. Excavation methods Access Shafts Excavation through moraines is the same as for the experimental shaft. For the molasse, shaft boring machines or drill and blast are possible. Drill & blast may prove the less risky choice (flexibility, previous projects failed with machine, non-specialised workfoce).

6. Comparison of FCC options Data

6. Comparison of FCC options Data

6. Comparison of FCC options Conclusion A shaft to shaft analysis of the two FCC 100 km options has been carried out and is based on the two longitudinal sections attached in the Appendices 1 and 2 “It can be concluded that the foreseen caverns and shafts, with their proposed dimensions, are possible to excavate under the given geological circumstances… it will become more a question of time and costs than constructability.” “neither engineering nor logistic limits are met although special equipment with limited availability is needed for certain structures.” “With the information available so far, no changes of the project, with respect to the given dimensions for shafts and caverns, are mandatory.” “it is strongly recommended to execute further geological and geotechnical investigations. Based on the results of these investigations, additional risks can be detected or currently defined risks can be adjusted for each option.” “A final recommendation of one of the two options is very difficult to make at this stage of the project and would lead to a premature decision based on insufficient data. However, if a decision had to be made by CERN at this stage based purely on the available data, the Intersecting Option would seem the better choice due to the avoidance of the Flysch section in the Pré-Alps with high overburden and squeezing potential. In addition, for this option, the excavation of the Experimental and Access Points are assumed to lie entirely in Moraine and Molasse with good rock conditions." Note: CE recommendation remains 93km Option 1. This was outside the scope for Amberg’s report

FCC Schematic - Single Comments from FHI? 6m diameter

FCC Schematic - Twin Comments from FHI? 4.5m diameter

Access Shaft PM54 12m diameter

Access Shaft Concept – double lift Diameter tbc Pressurised Stairwell Main lift (pressurised) Backup lift (pressurised)

Access Shaft Concept – magnet shaft Oblong, dimensions TBC Main lift (pressurised) Trémie Pressurised Stairwell