Presentation is loading. Please wait.

Presentation is loading. Please wait.

General meeting LAGUNA LAGUNA – Fréjus site

Similar presentations


Presentation on theme: "General meeting LAGUNA LAGUNA – Fréjus site"— Presentation transcript:

1 General meeting LAGUNA LAGUNA – Fréjus site
Geotechnical feasability (Rewiew of WP2 Munich January 26th-27th, 2009) March 30th.- April 2nd 2009, Wroclaw

2 CURRENT SITUATION: GENERAL PLAN
LSM Underground Laboratory Modane Road tunnel Railway tunnel Longitudinal section >1500 m rock overburden 6,6 km 6,2 km 12.8 km

3 Geotechnical parameters of rock mass
Unit weight kN/m3 Elastic modulus GPa Poisson’s ratio Friction angle 35/40° (lower/mean value) Peak cohesion kPa Residual cohesion kPa (short term) kPa (medium term) kPa (long term) Plastic strain % (for reach residual cohesion) Dilation angle 3°

4 Main characteristics of calc-schists
Time-dependent behaviour of rock mass (displacements) Tendency to wedge instability on roof Anisotropy of rock mass properties (effect of schistosity) Reduction of rock mass strength after failure No water circulation in the rock mass (OK for cavern stability and thermal losses during reservoir operation)

5 Cavern design LENA 221'000 m3 GLACIER 320'000 m3 MEMPHYS 558'000 m3
21.9 17 m 41.9 19 m 47.5 110 m D=76 m 70 m 25 m D=67 m D=35 m

6 Memphys – 3D model (FLAC)

7 Memphys – Displacements – Long term

8 Memphys – Failure zone – Long term

9 Memphys – Analysis of wedge stability

10 Large excavations at Frejus - Conclusions
The construction of the large excavations for the 3 detector types of Laguna is feasible at Frejus site. For Glacier it is possible to built a unique large tank. The division into 2 smaller tanks can reduce the total construction costs of the caverns. For Lena it is not necessary to have curved walls The final lining should be placed at least 2-3 months after the excavation in order to reduce the rock pressure in the long term (excavation from top to bottom, construction of final lining from bottom to top).

11 Interaction between tank and rock mass
The stability of the rock mass during excavation is ensured by anchors and reinforced shotcrete The definitive cavern is sustained by a concrete lining. Glacier needs a inner, independent tank. The rock loads are supported by the concrete lining and will not be transferred on the steel tank. The water from the rock mass can cause an external load on the imperious tank (even if apparently the rock appears dry). To avoid this type of load, it is necessary to design an external drainage system. The earthquake is not a problem for the steel tank, if there is not an active fault crossing the cavern (atypical situation).

12 Location LAGUNA Safety tunnel Road tunnel LAGUNA Railway tunnel

13 LAYOUT (top view) Access Tunnel Safety Tunnel Road Tunnel
Control room, offices, storage, power Safety Tunnel Electronics Air and water purification Electronics Road Tunnel Electronics

14 LAYOUT (side view) Safety Tunnel Road Tunnel Access Tunnel
Air and water purification Safety Tunnel Road Tunnel Electronics Electronics Control room, offices, storage, power Access Tunnel

15 Air and water purification
LAYOUT Access Tunnel Safety Tunnel Electronics Air and water purification Control room Storage Offices Power Electronics Cables, piping etc Electronics


Download ppt "General meeting LAGUNA LAGUNA – Fréjus site"

Similar presentations


Ads by Google