RPG: September 24, 2013 1 2014 Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.

Slides:



Advertisements
Similar presentations
Calista AVCP Regional Energy Plan. Preliminary Planning and Stakeholder Involvement Resource Inventory and Data Analysis Develop and Review Draft Energy.
Advertisements

Houston Region Import Capacity Project Planning for Reliable Power.
RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Regional Planning Group Project
Transmission Corridor Zone Designation Process Terrence O'Brien, CEC December 11, 2007 Energy Action Plan.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
System Strength Discussion
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014 Preliminary1.
ERCOT PUBLIC 8/19/ LTSA Scenario Results Updates August, 2014.
111 TAG Meeting June 8, 2015 Teleconference / Webinar FINAL.
Long Term Study Task Force Update to ETWG ERCOT Long-Term Study: Scenarios, New Software, and Emerging Technology Assumptions January 27, 2012.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
2015 RTP – Study Scope of Short Circuit Analysis RPG Meeting May 19,
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
ERCOT PUBLIC LTSA Introduction. ERCOT PUBLIC 2 Outline  Background  2016 LTSA Process  Summary of first LTSA Workshop  Topics and Speakers.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Kurten Switch Project ERCOT Board of Directors Bill Bojorquez System Planning December 13, 2005.
March 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Wholesale Market Subcommittee Texas Interconnection Long-Term Study Update Warren P. Lasher April 8, 2011.
November 12, 2010 Regional Planning Group Long-Term System Assessment Project Update Warren Lasher Manager, Long-Term Planning and Policy Jonathan Rose.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.
Jeff Billo Manager, ERCOT Transmission Planning Kenedy to Nixon to Seguin Line Upgrade Project Regional Planning Group (RPG) Review; ERCOT Independent.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
Long Term Study Task Force Update ERCOT Long-Term Study Scenarios January 13, 2012.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
ERCOT Independent Review
Economic Analysis Proposed Scope ERCOT RPG Meeting September 17, 2010.
C A L I F O R N I A E N E R G Y C O M M I S S I O N Integrated Energy Policy Report Workshop Landscape-Scale Environmental Evaluations for Energy Infrastructure.
ROS July 10, 2008 Meeting WOTF Update on ROS Action Plan Summary: EECP Step #2 (Feb.26 th, 2008) Mark Garrott WOTF Chair.
Long Term Study Transmission Results May 21 st, 2013.
ERCOT PUBLIC November RPG Meeting RTP – Study Scope November 20, 2015.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
ERCOT – MISO DC Tie Study Comments
Panhandle Renewable Energy Zone (PREZ) Study
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
CREZ Related Generation Interconnection Studies July 2008 Jeff Billo RPG meeting
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
August 24, 2007 ERCOT Regional Planning Group Meeting CREZ Transmission Optimization Study Warren Lasher System Assessment.
California Energy Action Plan December 7, 2004 Energy Report: 2004 and 2005 Overview December 7, 2004.
ERCOT PUBLIC LTSA Introduction. ERCOT PUBLIC 2 Outline  Background  2016 LTSA Process  2016 Scenario Development Process  2016 LTSA Schedule.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Response to TAC Questions on PGRR031 TAC– January 28, 2014 Jeff Billo, ERCOT 1.
ERCOT – MISO DC Tie Study Regional Planning Group November 20, 2015.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
2016 LTSA Update Doug Murray 6/21/2016. Agenda Introduction Scenario Retirement Process Scenario Summary Results Appendix.
Impact of not including proposed generators lacking RARF data in the planning models Planning Guide Section 6.9 Issues February 17, 2016.
1 ERCOT 2015 West Texas Study November 18, 2014 Jeff Billo.
4/16/2010 Regional Planning Group Meeting Long-Term Planning Study of the ERCOT Interconnection Warren Lasher Manager, System Assessment.
Subsynchronous Resonance Update Jeff Billo, Senior Manager ERCOT Transmission Planning February 3, 2016 Wholesale Market Subcommittee 1ERCOT Public.
RPG - 10/12/2007 Competitive Renewable Energy Zones (CREZ) Update Bill Bojorquez Vice President, System Planning.
Houston Import Study Update
LTSA Scenario Development Workshop
Transmission Planning in ERCOT- Overview
Compliance Report to ERCOT BOD December 2006
ERCOT 2009 Five-Year Transmission Plan Update
Director, Transmission Services
Warren Lasher Manager, Long-Term Planning and Policy
I-5 Corridor Reinforcement Project
Implementing the Transportation/Land Use Connection Program
Presentation transcript:

RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group

RPG: September 24, Senate Bill 20 (79 th Legislature, 1 st Called Session [2005]) requires that the PUCT and ERCOT study long-term system needs and report to the Legislature each even numbered year ERCOT has been conducting a Long-Term System Assessment (LTSA) on a biennial basis since , 2008, 2010 LTSAs focused on 10-year horizon Work on 2012 LTSA bolstered by grant from the Department of Energy –Process improvements implemented –New tools utilized –Scope expanded to 20-year horizon History

RPG: September 24, LTSA indicated a reliability need to increase import capability into the Houston area by 2018 –In 2009 Sharyland Utilities and CenterPoint Energy submitted import project proposals –ERCOT endorsed the Fayetteville-Zenith 345 kV project (cancelled in 2012 due to change in planning criteria) Valley Import Project, studied in 2011, used 2020 case from the 2010 LTSA to inform the project recommendation of which project alternative best met the long-term needs for south Texas Cross Valley 345 kV project, studied in 2011, used 2020 case from the 2010 LTSA to identify long-term needs in the area –Led to the recommendation to route Cross Valley 345 kV line near South McAllen substation for future 345/ 138 kV connection –2013 RTP preliminary results show need for this connection by 2018 How the LTSA has affected near-term analysis

RPG: September 24, LTSA indicated need for increased Houston import capability in all studied scenarios –Three TSPs proposed import projects into the Houston area this summer –Results from LTSA show need to consider long-term requirements for the area (see today’s Houston Import presentation) 2012 LTSA indicated potential for large wind capacity build out in the Texas Panhandle in multiple scenarios (exceeding existing design capacity) –In part, led to the initiation of the Panhandle Renewable Energy Zone study in early 2013 How the LTSA has affected near-term analysis cont.

RPG: September 24, Link near-term and long-term planning processes –Internal staff realignment: RTP and LTSA engineers now in same group –2014 LTSA will use similar study process, assumptions and tools as RTP ERCOT will select either UPLAN or PROMOD for both 2014 RTP and LTSA economic analyses Analysis beyond 10-year horizon showed value, but not all stakeholders were comfortable with 20-year horizon –Suggest studying years 10 and 15 (2024 and 2029) Continue to improve scenario development and assumptions –ERCOT will hold 1 to 3 workshops in October/ November –May hire consultant to facilitate workshops –Use more sensitivities to assumptions The Brattle Group report recommendations will be evaluated in the future Lessons learned from the 2012 LTSA and DOE Project

RPG: September 24, Provide a roadmap for the long-term transmission needs of the ERCOT System 2.Provide study cases for the use of near-term planners in the evaluation of large transmission additions to the ERCOT System 2014 LTSA Goals

RPG: September 24, Develop 6 to 8 scenarios for load/ generation development for 2024 and 2029 Select 3 to 5 of those scenarios for transmission build out –Start with final 2018 case from 2013 RTP –Reliability analysis performed using similar assumptions to RTP –Economic analysis Final report in December 2014 Formal scope document will be presented at next RPG meeting 2014 LTSA Scope Proposal

RPG: September 24, Comments or Questions?