TE-MPE-CP, RD, LHC Performance Workshop - Chamonix 2009 03-Feb-2009 1 R. Denz TE-MPE-CP on behalf of the QPS team QPS Upgrade and Re-commissioning.

Slides:



Advertisements
Similar presentations
Hyper Status and Preliminary Testing of the New Hyper Bus Fault Detector CP Work done by CP section Based on Slides from Knud DAHLERUP-PETERSEN.
Advertisements

LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
Target Controller Electronics Upgrade Status P. Smith J. Leaver.
TE-MPE-CP, RD, 03-Dec Quench Detection and Energy Extraction Systems R. Denz (Quench Detection), K. Dahlerup-Petersen (Energy Extraction Systems),
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
TE-MPE-EP, RD, 26-Jul Quench Heater Supervision for MB Status of System Integration R. Denz TE-MPE Technical Meeting July 26 th Acknowledgements:
CRYOGENICS AND POWERING
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
TE-MPE-EP, VF, 11-Oct-2012 Update on the DQLPU type A design and general progress. TE-MPE Technical Meeting.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
How to achieve higher redundancy of the UPS for QPS ? -The lack of redundancy concerns the supply lines from UPS to consumer but equally parts of the UPS.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
TE-MPE-EP, RD, 06-Dec QPS Data Transmission after LS1 R. Denz, TE-MPE-EP TIMBER PM WinCC OA Tsunami warning:
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
TE-MPE-CP, RD, 23-Nov Summary of Radiation Induced QPS Events in LHC 2010 R. Denz TE-MPE-CP.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Changes in QPS R. Denz, TE-MPE-EP MPP workshop Acknowledgements: K. Dahlerup-Petersen, V. Froidbise, S. Georgakakis, B. Magnin, C. Martin, J.
TE/MPE/EE J. Mourao T/MPE/EE 1 November 2012 LHC Machine Local protection Redundant Power supply (DQLPUR) & interface Module (DQLIM) progress status.
TE/MPE/EE J. Mourao T/MPE/EE 23 December 2012 LHC Machine Redundant Power supply (DQLPUR) & interface Module (DQLIM) assembling during LS1.
John Coughlan Tracker Week October FED Status Production Status Acceptance Testing.
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
TE-MPE-CP, RD, 09-June Enhanced Diagnostics & Supervision for Quench Heater Circuits R. Denz TE-MPE-CP.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
AT-MEI-PE, RD, LIUWG 31-JUL R. Denz AT-MEI-PE LHC Luminosity Upgrade Protection of the Inner Triplet, D1, Correctors and Superconducting Links/Leads.
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
Fabio Formenti - Feb. 25th, LHC enhanced Quench Protection System project Review committee meeting February 24 th –26 th 2009.
QPS R2E Status R2E Internal Meeting, October 24 th 2013Discussion 1 LS1 developments Digital Quench Protection insertion region magnets Delivery/installation.
LHC Enhanced Quench Protection System Review 24 – 26 February 2009.
TE-MPE-CP, RD, 06-Oct Radiation Induced Faults in QPS Systems during LHC run 2011 R. Denz TE-MPE Technical Meeting October 6 th.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
TE-MPE-EP New DQLPU type A Production of 1300 new protection units TE-MPE-EP, VF, 23-Nov-2012.
TE/MPE activities currently planed for YETS Reiner Denz, Knud Dalherup-Petersen, Markus Zerlauth & Bruno Puccio YETS coordination meeting.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
Quench Detection System R. Denz TE-MPE-EP on behalf of the QPS team.
1 J. Mourao (TE/MPE/CP) Enhanced DQHDS functionality  Status for 2011  Increase Magnet diagnostic capabilities  Our proposals.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
B.Puccio MPE Workshop for LS1 / 22 & 23 Nov Logistics for DYPB activities Bruno PUCCIO (TE/MPE)
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
MPP Workshop Status of Powering Interlocks I. Romera on behalf of MPE-MS MPP Workshop, 12 June 2015, I. Romera (TE-MPE)1.
TE-MPE-CP, RD, 12-Dec QPS - analysis of main problems, areas to target, possible improvements R. Denz, TE-MPE-CP Evian 2011.
TE-MPE-CP, RD, LHC risk review 06-Mar R. Denz TE-MPE-CP Radiation Hardness of Cold By-pass Diodes Acknowledgements: D. Hagedorn (former project.
Rutherford Appleton Laboratory September 1999Fifth Workshop on Electronics for LHC Presented by S. Quinton.
CERN TE-MPE-EP, RD, 09-April Quench Protection Systems (QPS) for the LHC R. Denz, TE-MPE-EP Acknowledgements: K. Dahlerup-Petersen, A. Siemko, J.
August 24, 2011IDAP Kick-off meeting - TileCal ATLAS TileCal Upgrade LHC and ATLAS current status LHC designed for cm -2 s 7+7 TeV Limited to.
TE-MPE-CP, RD, 28-Sep Problems with QPS DAQ Systems During LHC Operation, 1 st Results from 2010 CNRAD Tests R. Denz TE-MPE-CP.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
MPE LS1 workshop Summary Session 4 – Quench Detection R. Denz, D. E. Rasmussen.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
Summary of IAPP scientific activities into 4 years P. Giannetti INFN of Pisa.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
R. Denz, A. Gomez Alonso, AT-MEL-PM
LHC Enhanced Quench Protection System Review
Document Plan & Milestones WP7
Injectors BLM system: PS Ring installation at EYETS
Ideas and design concepts, and challenges
12 October 2009 RRB Plenary R.-D. Heuer
LV Safe Powering from UPS to Clients
Powering the LHC Magnets
MPE main activities planned for LS2
Detailed global view on protection and detection of the circuits
Quench detection electronics for the HL-LHC magnet circuits of the LHC
M. Zerlauth, I. Romera 0v1.
R. Denz, TE-MPE-EP Acknowledgements: J. Steckert
Presentation transcript:

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb R. Denz TE-MPE-CP on behalf of the QPS team QPS Upgrade and Re-commissioning

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade – rationale  : Non-destructive discovery of aperture symmetric quenches in LHC main dipoles –Late detection of a quench in a main dipole –Upgrade of existing protection system required in order to detect timely aperture symmetric quenches  : Incident in sector 3-4 –Extent the existing protection system in order to be able to detect and interlock potential problems in the magnet interconnections and main bus-bar splices

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade building blocks Phase 1: required for re-start of LHC Phase 2a: required for MB training to 7 TeV Phase 2b: required for MQ training to 7 TeV Phase 3: enhanced diagnostics + repair, test and re-test of QPS electronics in sector regular maintenance of QPS & EE systems

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade – aperture symmetric quenches  Safe detection of symmetric quenches by comparing total voltage drops across magnets –System can share the instrumentation cables with the suspicious splice detection system –Additional interlock cabling for triggering of quench heater power supplies required  Multiple magnet evaluation scheme for main dipoles minimizing number of provoked quenches –3+1 magnet reference (interleaved with next unit): 1 st and 2 nd quench  trigger quenching magnet 3 rd quench  trigger remaining magnet of the three connected triggers  Interleaved two magnet evaluation scheme for quads  System reacts as well on “normal” quenches  detection threshold must be slightly higher to clearly distinguish different cases (U TH = 200 mV, 10 ms) K. Dahlerup-Petersen

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb Symmetric quench detection layout

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb Symmetric quench detection electronics  New design based on flash FPGA  Analog input stages and A/D converters on magnet potential, evaluation logic on local crate potential  Basic design finished  prototype production on the way  Redundant system with interlocks wired in 1 out of 2 configuration  Type tests –Detection logic & reaction time –Noise immunity (EMC) –Radiation tolerance of components e.g. ADC converters –Communication interface J. Steckert

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade - suspicious splice detection  Provide a system to be able to detect and localise “bad splices” representing a potential risk for the LHC integrity in the LHC main circuits (RB, RQD and RQF)  A splice developing a resistance in the order of n  equivalent of 100  V or kA) is regarded as potentially dangerous at high current (  see presentation A. Verweij) –System should interlock the concerned circuits Baseline threshold U TH = 300  V, 10 s –System should provide data for enhanced diagnostics via the QPS supervision –System can only access the superconducting circuits via existing voltage taps routed to the IFS box connectors (diode voltage taps), there is no access to a single splice  New layer of protection electronics exceeding the original scope of QPS –Detection of non-recoverable faults  new procedures required

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb Suspicious splice detection system type DQQBS  Re-use of existing design for the protection of HTS leads in LHC –Solution endorsed by management after QPS review end of 2008 –1200 units installed in LHC (equipment code DQQDC) Very few hardware problems revealed during commissioning Stable operation once system has been commissioned  2016 new units required for upgrade –Only minor hardware changes Increased isolation strength of DC-DC converters Replacement of obsolete components –New firmware under development (already used for testing) –Upgrade covers so far RB, RQF and RQD circuits –Upgrade can be extended to cover insertion region magnets Re-cabling of existing current lead protection system or installation of additional equipment

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb Suspicious splice detection electronics  Design based on ADuC834 TM micro-converter with 24 Bit  ADC –Two input channels with ±12.5 mV and ±250 mV voltage range 2 nd channel used for inductive compensation connected to external 1:10 voltage divider shared with symmetric quench detection –Baseline detection threshold is 300  V (10 s integration time) Redundant system with interlocks wired in 1 out of 2 configuration  Radiation tests (CERN TCC2, CERN CNGS, PSI) promising –Devices will withstand radiation levels expected for mid dipole position –ADuC834 TM micro-converter, DC-DC converters, SRAM, instrumentation amplifiers, fieldbus couplers …  To make full use of the capabilities of the system dedicated powering cycles are required –Powering cycle form injection current up to 2 or 3 kA with intermediate steps every 200 A –Sampling frequency = 5 Hz –Offline analysis of acquired data  expected resolution < 1 n 

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb Feasibility tests with prototype units in sector 1-2 Z. Charifoulline, B. Flora

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade - integration of new QPS electronics into LHC  Local Protection Unit type S to be installed in the existing QPS rack type underneath dipole B in each LHC half cell –Protection electronics associated to circuits RB, RQD and RQF –Suspicious splice protection system (phase 1) –Symmetric quench protection system (phase 2) –Potential to earth measurement (phase 3) –Fieldbus coupler linking to QPS supervision (phase 1)  Crate will be connected to existing infrastructure –Acquiring signals from 4 dipoles and 2 quads –WorldFip fieldbus and QPS internal interlocks (patches required) –One crate per LHC half cell, 54/55 per sector  Crate will be powered via a dedicated AC-DC power supply –Power supply fed by existing 230 V 50 Hz single phase UPS  Impact on existing QPS electronics is minimized

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb Local protection unit type S – integration into dipole protection rack Local protection unit type S Power supply unit

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade - cabling  Cabling is one of the essential parts of the upgrade –Measurement cables –Interlock cables for quench heater power supply triggering Required by symmetric quench detection system –Local patches for fieldbus, interlock and powering (treated separately)  Use of existing cable trays – additional cable supports (CABLOFIL TM ) required in dispersion suppressor areas and to by-pass the jumpers –Half-cell 7 to 11 shared with beam instrumentation (courtesy BE-BI)  Exclusive use of magnet connectors D20 (MB) and D21(MQ)  Cabling requests (DIC) prepared by QPS team and submitted to EN-EL –Three levels of cross checking introduced in collaboration with BE-OP  Cables fully assembled and tested on the surface by contractor  Final checking after installation (layout, continuity and isolation) –Tools provided by ELQA team Careful checking of the cabling work is extremely important and needs adequate time allocated. Any non-conformity not revealed during these tests will cause inevitable delays at a later stage.

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade – basic cabling set-up (odd half-cell) G. Coelingh 240 km of cables (= Chamonix – Venezia) 4400 individual cables 7800 connectors 0 errors permitted Triggers Instrumentation MQ Instrumentation MB

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade - supervision  Supervision hardware –2100  2536 QPS fieldbus clients in LHC –Up to 60  75 per WorldFip segment –Up to 120  150 per front-end computer –Increased number of clients will require slight modifications of the QPS networks in the LHC tunnel  more repeaters and local patches  Supervision software –Three new equipment types associated to a new QPS controller type –~30000 new signals, no dead-bands on analog signals permitted –Increased data volume transmitted to LHC logging  Firmware development of new QPS controller type by TE-MPE-CP in close collaboration with EN-ICE  All other tasks performed by BE-CO and EN-ICE

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade – revised supervision layout

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade – status phase 1 electronics  Suspicious splice detection board (2500) and fieldbus coupler (500) –Technical specification and final manufacturing folder ready –Electronic components ordered and about 90% delivered –Purchase order for PCB production, circuit board assembly and test submitted to approval Pre-series expected for beginning of March Total before end of May (partial delivery in batches) –Functional test systems for circuit boards currently being commissioned  Local protection unit type S (450) –Technical specification to be sent out to firms in week 7  Power supply unit (500) –Final prototype testing, technical specification in preparation

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade – status phase 1 cabling  Cabling requests (DIC) for all sectors submitted to EN-EL  Cable assembly on the surface –Sector 4-5: completed and tested by contractor –Sector 5-6: 50% completed –Sector 2-3: cables cut  Installation of cable supports started in sector 4-5 and 5-6  Cabling of sector 4-5 to be started this week –Final testing of cables can start as soon a reasonable quantity is installed K. Dahlerup-Petersen

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb QPS upgrade – status phase 2 & 3  Cabling included in phase 1  Symmetric quench detection electronics –Prototype production to be launched soon –Prototype device is also required for validation of QPS supervision –Various type tests to be made Radiation PSI scheduled for mid March –Technical specification & procurement of components in April –Production in May / June  test & installation in July (earliest date)  Voltage to earth feeler –Design principle clear, further development as soon as resources are available (not on critical path)

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb Summary I  QPS update will enhance the diagnostic and protection capabilities significantly and provide a powerful tool for identifying potentially dangerous problems in the LHC superconducting circuits –Scanning of the superconducting circuits including the magnets (using already available tools) on a regular (weekly?) basis necessary –New systems need to be very carefully commissioned in order to guarantee proper function and limited number of false triggers  New QPS electronics is based on a modular design allowing installation and commissioning in three stages –Upgrade of the system to phase 2 and 3 does not require long interventions inside the LHC  The proper functioning of the new protection system depends strongly on the instrumentation and interlock cabling –Proper testing of all new cabling work is essential

TE-MPE-CP, RD, LHC Performance Workshop - Chamonix Feb Summary II  QPS update is on the critical path for the re-start of LHC –Suspicious splice detection must work prior to re-commissioning of LHC System can be realised based on existing QPS designs and infrastructures Still on time but no contingency reserve Tests with powered magnets end of 2008 proved feasibility –Development of symmetric quench detection system almost completed Prototype testing to be started soon  Production, installation and commissioning until re-start of LHC remains nevertheless challenging The members of the QPS team like to thank all their colleagues providing help during this challenging phase!