1 2010 ESI Alternate Economic Study Process E-RSC Meeting October 21, 2010.

Slides:



Advertisements
Similar presentations
Evaluation Independent Monitoring Presented at: LPSC Staffs Technical Conference and ESIs Bidders Conference for the Fall 2006 Limited-Term RFP September.
Advertisements

Parallel Flow Visualization/Mitigation Proposal
Al McBride MANAGER, AREA TRANSMISSION PLANNING Existing Import Interfaces: Transmission Transfer Capabilities and The Calculation of Tie Benefits DECEMBER.
Presented to PGDTF February 11, 2015
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Public Service Company of New Mexico
Systems Analysis and Design Feasibility Study. Introduction The Feasibility Study is the preliminary study that determines whether a proposed systems.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Congestion Management in a Market Environment 2 nd CIGRE / IEEE PES International Symposium San Antonio, Texas October 5, 2005 Kenneth W. Laughlin.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
1 Dale Osborn Midwest ISO February 27, Wisconsin Renewable Energy Summit Transmission Expansion Opportunities with Wind Energy.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
2001 South First Street Champaign, Illinois (217) Davis Power Consultants Strategic Location of Renewable Generation Based on Grid Reliability.
Economic Analyses of FPL’s New Nuclear Projects: An Overview Dr. Steven Sim Senior Manager, Resource Assessment & Planning Florida Power & Light Company.
George Bartlett Director, Transmission Operations Economic Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
1 Non-Transmission Alternatives to Reduce Local Congestion Costs Bill Bojorquez June 3, 2004.
ICT Strategic Transmission Plan (ISTEP) Review and Status Update Entergy Transmission Summit July 29, 2008 Astor Crown Plaza New Orleans, Louisiana Douglas.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
1 Update on the 2006 Transmission Study LPSC B&E Meeting Baton Rouge, LA November 29, 2006.
Water Supply Planning Initiative State Water Commission November 22, 2004.
Peak RCCo Performance Metrics Draft –November 2013.
Network Customer Meeting Access Metric Update November 16, 2006.
Lyndonville Electric Department Feasibility Analysis Review December 2,
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.
OSC Meeting April 27, Transmission Cost Allocation Overview.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
ISTEP Phase II Final Report Summary LTTIWG Meeting – January 27, 2009 Douglas Bowman, PE Lead Engineer, ICT Planning
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
AFC METHODOLOGY EMS USER GROUP SEP 12, 2004 AFC – New Developments EMS USER GROUP Sep
Economic Planning – Theory and Current Practice Dan Woodfin Director, System Planning Joint PLWG/CMWG Meeting 2/4/2011.
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
Search Engine Optimization © HiTech Institute. All rights reserved. Slide 1 What is Solution Assessment & Validation?
October 6, 2006 Public Stakeholder Review Portland, Oregon Conditional Firm.
1 Entergy Gulf States Louisiana, L.L.C. Proposed Transmission Reliability Projects.
1 Entergy Louisiana, Inc. (South) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
© ABB Group August 23,2010 | Slide 1 MBPC Study – 1 st Load Pocket Preliminary Results for Discussion only Entergy Regional State Committee (ERSC) Southwest.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
Long-Term Solution for Negative Generation Entergy Transmission AFC Stakeholder Meeting August 22, 2006.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
G 200 L 200 ISO NEW ENGLAND T H E P E O P L E B E H I N D N E W E N G L A N D ’ S P O W E R. Southwest Connecticut RFP Markets Committee November 14, 2003.
Coordinated Planning Concept (For Discussion Only) revised 11/30/04 07/01/04.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
ISTEP Update Transmission Planning Summit August 11, 2009 Crown Plaza Hotel New Orleans, LA.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
Response to TAC Questions on PGRR031 TAC– January 28, 2014 Jeff Billo, ERCOT 1.
Douglas Bowman, PE, PMP Project Manager Entergy Corporation New Projects and Processes Ensure Power Transfer for Northeast Arkansas Customers.
PJM© Market Efficiency RTEP Proposal Window PJM TEAC 1/9/2014 – Market Efficiency Presentation.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Calvert City Power I, L.L.C. (“Calvert”) Purpose of Meeting
Status Update for Reliability/Market Power Mitigation Assessment
Warren Lasher Manager, Long-Term Planning and Policy
Reliability Assessment Committee Proposal TSS Meeting
Status Update for Reliability/Market Power Mitigation Assessment
NWA Suitability Criteria
ISO New England System R&D Needs
Agenda Provide a recap of primary northern route alternatives for the MPRP Describe basis for selected route N5 Overview of analyses performed Description.
ITP20 Flowgate Selection Introduction
Excelsior Energy’s Mesaba Energy Project
Strategic Plan and Economic Upgrade Process
Presentation transcript:

ESI Alternate Economic Study Process E-RSC Meeting October 21, 2010

2 ESI Economic Study Process (ESP) l Background –Each year, in accordance with Attachment K to the Entergy OATT, the ICT identifies and performs a preliminary study of five economic transmission projects that may provide benefits to the users of the Entergy transmission system. –This process is known as the ICT Strategic Transmission Expansion Plan, or “ISTEP.” –In early 2009, ESI developed a study process, known as the ESI Economic Study Process, or ESP. –The purpose of the ESP was to take the five projects identified by the ISTEP each year, and any other projects identified by ESI, and to perform additional study and analysis to determine if any of these projects could be expected to provide benefits to the native load customers of the Entergy Operating Companies sufficient to justify building these projects. –The ESP, a seven to nine month process, involves production cost analysis of the proposed upgrades to determine whether the upgrades can reasonably be expected to produce benefits that merit proceeding with the project. –Using the ESP, ESI evaluated selected projects from the 2008 ISTEP that was released in January 2009.

3 ESI Economic Study Process l Background –The ICT released its 2009 ISTEP results in February u One of the projects – the Jackson Area projects – is already addressed in the Entergy Construction Plan. u Two of the projects – Central Arkansas and Baton Rouge/S. Miss. -- did not show any projected savings. u The other two projects – SC Ark/NE LA and Lake Charles – showed projected congestion cost reduction of $1M or less on an annual basis; the cost of these two projects was estimated at less than $10M * each. l New Process Development –ESI determined that it was appropriate to streamline its ESP for purposes of evaluating certain lower cost projects. –The result is a streamlined study process, termed the “Alternate Economic Study Process” (AESP) to evaluate potential economic projects the cost of which is estimated at $10M or less ISTEP Results Summary Project cost estimate developed by the ICT for the 2009 ISTEP report. *

4 ESI Economic Study Process l AESP –The AESP was developed to study projects that (based on the results presented by the ICT in its ISTEP report) meet certain criteria based on specific business principles. l AESP Guiding Principles –Use the Alternate Economic Study Process for transmission projects that cost $10 M or less (the full Economic Study Process will be used to evaluate other, more costly transmission projects). –Determine if economic projects can defer or eliminate future investments or reliability projects. –Qualitative Analysis will be used to evaluate the benefits of the projects. »Simplified economic analysis will be used. »Detailed generation cost simulations may be performed as needed. –Perform analysis to determine the impact of the project on historically constrained flowgates using operational simulations. Perform Alternate Economic Study Process In general, if the estimated cost of the proposed project is $10M or less AND the answer is “yes” for three of the five criteria questions, then the project qualifies for consideration in the Alternate Economic Study Process.

5 l Alternate Economic Study Process –Power flow studies using a variety of sensitivities will be performed to determine the impact of the proposed project on various system parameters: »Interface/Import Limits »Constraining flowgates »Benefit to planned Network Resources »Elimination or deferral of planned reliability projects –Identify historical issues that could potentially be mitigated by the transmission projects. –Sensitivities may be used to develop operational scenarios to simulate real time congestion. »TLR – LAP »Determine the benefit to existing Network Resources –Simplified economic analysis will be used along with detailed generation cost simulations (as needed). l Alternate Study Process Outcome –Summary of the potential benefits (if any) provided by the project with respect to various parameters (import limits, etc.) that impact system behavior. –Summary of project impact on planned resources and flowgate issues. –Study team will make recommendation regarding construction of the identified transmission projects. ESI Economic Study Process – Alternate Economic Study Process Development

6 ESI Alternate Economic Study Process Description l ESI Economic Study Process Criteria & Timeline –The Alternate Economic Study Process (AESP) is used only for evaluation of economic projects which construction cost is estimated to be less than $10M (the full Economic Study Process will be used to evaluate other, more costly transmission projects with greater potential benefits). –This process is divided in three phases and is designed to be completed within approximately five months. –The AESP is performed using mainly power flow models to determine the impact of the proposed transmission projects on: »Interface/Import limits »RMR unit requirements »Constraining flowgates »Historical TLRs and LAPs »Existing Network Resources »Planned Network resources »Deferral of planned reliability projects ~ 5 months ICT - ISTEP ProcessESI - AESP Process

ESI Alternate Economic Study Process Project Selection The ISTEP 2009 Projects are: 1. South Central Arkansas/Northeast Louisiana constraint 2. Central Arkansas Constraint 3. Lake Charles 230 kV Loop 4. Baton Rouge/South MS Constraint 5. Jackson Area (Approved Project) l Jackson area project is already being addressed in the Construction Plan l The cost of the proposed SC Ark/NE La upgrade is approximately $7.4M *; because the estimated construction cost is $10M or less, the AESP (not the full ESP) will be used to evaluate it. * Original project cost estimate included in the 2009 ISTEP report. During June 2010, ESI selected only the South Central Arkansas/Northeast Louisiana project (Project 1) to be evaluated as part of the AESP.

8 ESI Alternate Economic Study Process Project Selection l Project Selection ESI selected the following projects to be evaluated collectively using the AESP: –ISTEP Project 1 - South Central Arkansas / Northeast Louisiana Constraint »Critical flowgates identified are: u Sheridan-El Dorado 500kV FTLO Etta-McNeil 500kV (SHRELD_ETTMCN) u White Bluff-Sheridan 500kV FTLO Mabelvale-Sheridan 500kV (WBSHE_MABSHE) u Mabelvale-Sheridan 500kV FTLO White Bluff-Sheridan 500kV (MABSHE_WBSHE) u White Bluff-Keo 500kV FTLO Sheridan-Mabelvale 500kV (WBKEO_SHEMAB) * –ISTEP Project 2 - Central AR Constraint ** »Critical flowgate identified is: u Sheridan-Mabelvale 500kV FTLO White Bluff-Keo 500kV (SHRMAB_WBKEO) FG1 FG2 FG3 FG4 FG5 FG1 FG2 FG3 FG5 FG4 North-South flow South-North flow Proposed transmission upgrades do not effect flowgate FG4. ISTEP Project 2- Central Arkansas Constraint is considered due to common limiting element as shown for Project 1(i.e.Sheridan-Mabelvale 500kV line) * **

9 ESI Alternate Economic Study Process Project - Transmission Upgrades l Project 1 Description –The solution consist of upgrades to terminal equipment to the following lines: »Sheridan - El Dorado 500kV »White Bluff - Sheridan 500kV »Mabelvale - Sheridan 500kV * l Equipment upgrades & Total Project Cost estimate l Project impact on transmission line ratings Equipment LocationDescriptionTotal Project Cost Mabelvale 500kV SubstationReplace 3 breakers, 13 switches, 2 line traps $8,200,000** Sheridan 500kV SubstationReplace 11 switches, 6 line traps White Bluff 500kV SubstationReplace 5 switches, 2 line traps El Dorado 500kV SubstationReplace 1 switch, 2 line traps ** Revised t otal project cost is based on an Entergy Class 5 estimate. A Class 5 estimate is generally referred to as an order of magnitude estimate which is typically used for market studies, initial viability, alternative evaluations and project screening based on very general project scope description. Transmission LineCurrent Line RatingProposed Line RatingRating Increase Sheridan - El Dorado 500kV1732 MVA2598 MVA***50%*** White Bluff - Sheridan 500kV1732 MVA2598 MVA***50%*** Mabelvale – Sheridan 500kV1732 MVA2598 MVA***50%*** * This upgrade will also address the critical flowgate issue identified for Project 2. *** New transmission line ratings are contingent on the results of system stability studies.

10 ESI Alternate Economic Study Process Project Evaluation Criteria Description AESP Evaluation Results Meets Criteria A Interface / Import limit analysis Determine if the proposed projects increases the interface/import limit by at least 5% of the base case interface import limit. The proposed upgrades could potentially increase the Sheridan South Import limit by more than 5%. YES B Reliability Must Run (RMR) units requirements analysis Determine if the proposed project increases the RMR load trigger level thresholds by at least 5% of the MW capability of the RMR unit Not Applicable. NO C Constraining flowgates analysis Determine if the proposed project reduces the flow on the limiting element (LE) of other flowgates within the region by at least 5% of Rate A MVA limit of the LE of the flowgate. No Impact NO D TLR-LAP impact analysis Determine if the proposed project reduces the flow on the LE of the flowgate forcing the TLR or LAP by at least 5% of Rate A MVA limit of the LE of the flowgate. The proposed upgrades could potentially decrease by 30% the loading of the limiting elements for the following flowgates: 1)Sheridan-El Dorado 500kV FTLO Etta-McNeil 500kV 2)White Bluff-Sheridan 500kV FTLO Mabelvale-Sheridan 500kV 3)Mabelvale-Sheridan 500kV FTLO White Bluff-Sheridan 500kV 4)Sheridan-Mabelvale 500kV FTLO White Bluff-Keo 500kV YES E Benefit to existing network resources analysis Determine if the proposed project increases the FCITC of a transfer from the existing network resource to transmission system load (based on 1% OTDF) by a MW amount that is equivalent to 5% of the total MW capability of the existing network resource 1)The proposed upgrades could potentially increase the FCITC of a transfer from local area generation to transmission system load. As a result, local area generation redispatch during peak load scenarios could be reduced. YES F Benefit to planned network resources analysis Determine if the proposed project increases the FCITC of a transfer from the planned network resource to transmission system load (based on 1% OTDF) by a MW amount that is equivalent to 5% of the total MW capability of the planned network resource. 1)The proposed upgrades could potentially increase the FCITC of a transfer from a planned network resource to transmission system load during peak load off peak load scenarios. 2)The proposed upgrades could potentially increase the FCITC of a transfer from local area merchants to transmission system load during peak and during off peak load scenarios. YES G Elimination/Deferral of proposed reliability projects Ability to defer/eliminate planned transmission construction projects as defined in TBU’s construction plan. No Impact NO H Qualitative analysisThis will include an assessment of the ease of construction and evaluation of the confidence level of construction cost estimates. The transmission upgrades is expected to be in service within 1-2 years at a total project cost estimate of $8.2M. YES AESP Results Summary

11 ESI Alternate Economic Study Process Decisions l Final Decisions –Based on the AESP evaluation, a decision has been made to implement the following transmission upgrades: Upgrade LocationUpgrade Description Mabelvale 500kV SubstationReplace 3 breakers, 13 switches, 2 line traps Sheridan 500kV SubstationReplace 11 switches, 6 line traps White Bluff 500kV SubstationReplace 5 switches, 2 line traps El Dorado 500kV SubstationReplace 1 switch, 2 line traps