Presentation is loading. Please wait.

Presentation is loading. Please wait.

ITP20 Flowgate Selection Introduction

Similar presentations


Presentation on theme: "ITP20 Flowgate Selection Introduction"— Presentation transcript:

1

2 ITP20 Flowgate Selection Introduction
Timothy Miller July 21st, 2010 TWG Teleconference

3 Flowgate Simulation Impact
In the economic simulations flowgates are the only flow control mechanism Line limits are not heeded by default Penalties associated with an overload provide control Manage the economic dispatch Key to a reasonable economic solution Background warm-up information – why it’s important Flowgate list will be longer than that of the NERC IDC 270 monitored by Operations 500 needed by ITP processes Not related to the annual review – not even close Don’t dwell on economics

4 Selecting Reasonable Flowgates
Staff is developing flowgates based upon the ITP 20 Year Assessment Scope document Preferred outcomes Spreadsheet listing the flowgates Charts summarizing the simulated data Maps showing congestion The reason we are here today

5 Flowgate Selection Criteria

6 Flowgate Selection Criteria
Starting Point NERC Book of Flowgates Additional criteria 345 kV Contingencies 115+ kV Monitored Elements Evaluate 8,760 hours From the ITP scope: The initial flowgate list will be the then-current NERC Book of Flowgates (BoF) Flowgate studies will be run over 8760 hours (1 year) Flowgate studies will be performed on each future case For the flowgate analysis, contingencies 345 kV and up in SPP, including autotransformers stepping down from 345 kV and up, will be selected For the flowgate analysis, monitored elements 115 kV and up in SPP will be selected A minimum of one iteration will be performed in the flowgate study Unless other information is available, the flowgate ratings will be selected based upon the Rate A (normal rating) and Rate B (emergency rating) in the powerflow model. This analysis will focus on a 2030 economic model

7 Flowgate Selection Criteria
Additional criteria SPP devices and tie-lines 60 hour threshold Rate A & Rate B unchanged Three iterations From the ITP scope: The initial flowgate list will be the then-current NERC Book of Flowgates (BoF) Flowgate studies will be run over 8760 hours (1 year) Flowgate studies will be performed on each future case For the flowgate analysis, contingencies 345 kV and up in SPP, including autotransformers stepping down from 345 kV and up, will be selected For the flowgate analysis, monitored elements 115 kV and up in SPP will be selected A minimum of one iteration will be performed in the flowgate study Unless other information is available, the flowgate ratings will be selected based upon the Rate A (normal rating) and Rate B (emergency rating) in the powerflow model. This analysis will focus on a 2030 economic model

8 Unique Operational Flowgates

9 Unique Operational Flowgates
SPP-SPS interfaces Staff recommends redefining flowgate as individual OTDF flowgates due to extensive upgrades in place by 2030.

10 Unique Operational Flowgates
GGS Stability Interface Staff recommends continued use of this interface

11 Example Flowgate Simulation Data

12 Flowgate Example Results
Violations avoided by flowgate definition Before & After By Area By month

13 Effect of Adding Flowgates
Not Normalized for the number of lines in each area

14 Flowgate Example Results
Flowgate congestion Limit is respected Prices change Violations should be minimized by adding flowgates

15 Congestion by Shadow Price Impact
Data to be provided by SPP

16 Next Steps Staff to provide TWG draft results:
Top 10 congested flowgate summary Exhaustive flowgate spreadsheet Hours Congested & Avg. Shadow Price Results of contingency scans Requesting TWG endorsement of flowgates in August teleconference

17 Timothy Miller Planning Engineer 501-614-3357 tmiller@spp.org


Download ppt "ITP20 Flowgate Selection Introduction"

Similar presentations


Ads by Google