MIPO meeting 12/05/15. Exec summary Working group satisfied in integrity of absorber vessel and windows, pending review of reports – Proof test at 2.2.

Slides:



Advertisements
Similar presentations
Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
Advertisements

MICE OsC – 22 nd June 2010 Liquid-hydrogen system and absorber M Hills T Bradshaw M Courthold S Ishimoto W Lau I Mullacrane P Warburton.
MICE hydrogen review Commissioning, testing and operations.
Longitudinal Expansion of RFQ Vane Ends at Section-to-Section Interface.
GlueX Solenoid Recent progress and Coil cold tests Paul Brindza September 9, 2004.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
The issue: A non-standard thin window design  No closed form expression for maximum stress vs. volume pressure  FEA (finite element analysis): geometry.
Cooling Channel Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration.
MICE Safety Review Process and Schedule Elwyn Baynham Tom Bradshaw Iouri Ivaniouchenkov Columbia Meeting June 2003.
1 MICE Absorber working group Columbia, 13 June 2003 MICE Hydrogen System. Preliminary HAZOP. Elwyn Baynham, Tom Bradshaw and Iouri Ivaniouchenkov,
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
MICE Hydrogen System Implementation Tom Bradshaw Elwyn Baynham Iouri Ivaniouchenkov Jim Rochford.
MICE absorber and Window / flow Design Wing Lau, Giles Barr & Stephanie Yang Oxford University MICE Meeting Berkeley, Oct 2002.
Summary of the change request from KEK KEK suggested 4 changes to be made on the AFC. We have looked into the request carefully and discussed the implications.
Mucool cryo-design Christine Darve Fermilab/Beams Division/ Cryogenic Department 8/12/02.
MICE hydrogen review Summary of system hardware. System function To provide 22 litres of liquid hydrogen for use as a muon absorber within a superconducting.
The MICE vacuum system Presented by Mark Tucker at CM-39, 26 June 2014.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.
+ STAR HFT Upgrade – Installation and Integration Rahul Sharma Brookhaven National Laboratory.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Cavity support scheme options Thomas Jones 25/06/15 to 06/07/15 1.
MICE CC Test Status Ruben Carcagno 11/06/13 1. Cooldown Coil Temperature (calculated average in each of 8 coil segments) SC Transition (voltages across.
Stress and Cool-down Analysis Yun HE MLC Internal Review 9/5/2012Yun HE, MLC Internal Review1.
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
Agenda – Basics of cavity integration into CAST Introduction (M Davenport) Information exchange 2016 – Vacuum in cold bore – 2 cavities Cooling RF Cavities.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
CM 28 – 6 th October 2010 LH2 Infrastructure M Hills M Courthold T Bradshaw I Mullacrane P Warburton.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Safety Concept and Tests Fakultaet Maschinenwesen, Institut fuer Energietechnik, Bitzer-Stiftungsprofessur für Kaelte-, Kryo- und Kompressorentechnik Jülich,
MICE LH2 Absorber Safety Mary Anne Cummings Edgar Black (IIT) Abingdon, UK Oct. 30, 2003.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 120 May 7, 2009.
1 Small Coolers for MICE Michael A. Green University of Oxford Department of Physics Oxford OX1 3RH, UK MICE Collaboration Meeting RAL.
Spectrometer Solenoids MICO 194 Steve Virostek LBNL July 25, 2012.
Lab Activities: Chamber Baking & Mixing Station Flushing Claudio Curtis Dan PPS meeting 22 June, 2011.
LHCb-UT and Velo Upgrade Road to a system EDR in Q June 2015 Bart Verlaat 1.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
1 Liquid Hydrogen update CM33 S Watson P Warburton M Courthold.
Spectrometer Solenoid Prep Work at RAL and LBNL Steve Virostek Lawrence Berkeley National Lab Steve Virostek Lawrence Berkeley National Lab MICE VC May.
1 MICE absorbers work package MPB – 27/10/15 Mike Courthold Mark Tucker Phil Warburton Steve Watson.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
1 MICE Absorbers work package MPB – 17/04/15 RAL Tom Bradshaw Vicky Bayliss Mike Courthold Matt Hills Andy Nichols Roy Preece Mark Tucker Steve Watson.
1 MICE Hydrogen system Working group mtg – 01/09/14.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
FC Status CM39 1/20 June 2014 OXFORDRALDARESBURY V. BlackmoreV. BaylissT. Hartnett J. CobbT. BradshawS. Griffiths W. LauM. CourtholdI. Mullacrane R. PreeceA.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Working group meeting 07/05/15. Agenda Overview of review and current action list Relief system – Summary of problem – Details of analysis, testing and.
Spokesman's update.
Absorber progress MICE-ISIS review of the liquid hydrogen system will be held in early January; guidance from Nominated Engineers on the imported absorber.
Cryogenic behavior of the cryogenic system
MICE Hall Summer Workplan
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
Project Manager’s Report + DC/MoM Report
Introduction Jason Tarrant – Integration Engineering Step IV Removal
The 11T cryo-assembly: summary of design and integration aspects
IBBelle: Status Commissioning at MPP Transport to KEK
ISRC and LEBT Vacuum System Design
SuRf Lab: (STFC) VTF Infrastructure and Process
Overview of the TARGET Monolith Rough Vacuum
JLAB CHL 2K COLD BOX REPLACEMENT
Presentation transcript:

MIPO meeting 12/05/15

Exec summary Working group satisfied in integrity of absorber vessel and windows, pending review of reports – Proof test at 2.2 bar showed evidence of minor plastic deformation but measurements were within error bars of instrumentation – Burst test of safety window successfully completed, with the window failing at 7.66 bar, in line with expectations Working group satisfied with ability of revised relief system to limit pressure rise to below half of the window burst pressure Working group agreed that third HAZOP can be substituted with a formal change control procedure, completed retrospectively for the various system changes Absorber now fully installed in FC – Leak rate currently at 3 x mbar.l/s Installation took 2 weeks, longer than expected. This was due to the amount of MLI work and some problems with fitting the end flange. Having learned from this: – Dismantling the absorber would take 2 days – Re-assembly would take a week - 2 days preparatory work and 3 days to install in the FC – Although we haven’t found any indium leaks on this installation, any reinstallation schedule should take this into account – an extra week is suggested

Window testing Burst test Pneumatic test off-site Burst at 7.66 bar.g (110 psi) FEA for this window predicted 9.66 bar.g which is a 20% overestimate – this was anticipated We have two measured and analysed spare windows (#005 – absorber; #008 – safety 2) We have two further delivered windows but they have not had FEA carried out to date Proof test Absorber pressurised to 2.2 bar.g in FC#1 bore No measureable leak via sniff or pressure drop Laser used to measure distance from datum to centre of window at start and end of test – Displacement of 0.09mm (mean of 5 measurements each time) – Accuracy of laser stated as 0.5mm – Equivalent measurement to FC vessel resulted in similar mean displacement

Relief system revision Pressure rise on as-installed system calculated as between 5-8 bar – expected to be a bit optimistic Working group agreed on target of FoS of 2 - with window test results, this means an allowable pressure rise of 4.25 bar Proposed change to relief system uses the pumping line instead of a dedicated relief line – All large bore pipework – Will include a bypass burst disk for the turbo pump – Will also include relief valves in parallel with backing pump Pressure rise is now calculated at 4.3 bar and this is reckoned to be conservative now Proposal accepted and procurement now going ahead

Absorber installation Absorber installed – 4 blankets of MLI around vessel body – Half a blanket (5 layers) over windows – 2 blankets wrapped around pipes – 1 blanket wrapped around instrumentation cables – Excess cable coiled and hung using mylar ‘slings’ – no visible touches to warm surfaces Window flange to FC flange measurement of 265mm Problem encountered when trying to fit end flange; interference with pipes of around 10mm – Not understood at all – Quick fix solution of a stand-off flange cannibalised from the other FC works – Downside is the flange now sticks out beyond the FC envelope – bellows have to be fitted to FC first now Leak testing is still progressing but is looking very positive so far – 3x10 -8 mbar.l/s on a rough vacuum

Going forwards System hardware all agreed and understood in principle Orders (nearly) all placed and lead times are acceptable Lots of paperwork to complete but should be manageable by the end of June Desire to start cooling the absorber at the earliest opportunity – Depends on hose and cable installation schedules I will make a declaration of confidence in the system (i.e. recommend that first Step IV absorber run can revert to hydrogen) when the following is achieved: – Clear evidence that the system thermal performance is satisfactory (helium cooldown below 20K) – Significant progress on paperwork, including draft operating procedures – Good understanding of any remaining hydrogen infrastructure work (transfer line, bottle platform) I hope to be in a position to do this before the middle of June – This gives several weeks float before ultimate deadline of start of July for the planned installation of the LiH absorber