VOWTAP Progress Report VOWDA December 2, 2015. DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two.

Slides:



Advertisements
Similar presentations
EPC Contracting in a Demand Driven Market (The Trimble County 2 Contracting Experience) January 18, 2007.
Advertisements

New York City Department of Education Charter Matching – Facilities Upgrades/ Capital Improvements – FY 2014.
Ensure Vendor/Engineer of Choice Product Quality
November 19, 2013 Preparing a Successful RFP to get Desired Results.
EDDIE TERRILL AIR QUALITY DIVISION DEPT. OF ENVIRONMENTAL QUALITY AUGUST 21, 2014 EPA’s 111(d) Clean Power Plan Rule: A DEQ Perspective.
With the Genesee County Road Commission By Fred Peivandi, P.E. And Ken Johnson, P.E. Local Road Funding.
TRANSPORTATION PLANNING Session 06 Subject: S0012 / Introduction to Civil Engineering Year: 2007.
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
WELCOME TO THE PROCUREMENT SEMINAR Procurement and Contracts An Overview of Contract Administration.
FasTracks Moving Forward: Regional Transportation Plan (RTP) Amendment Staff Recommendation Phillip A. Washington and Team August 7, 2012.
Citizens Advisory Committee Quarterly Meeting Rick Clarke, Assistant GM – Capital Programs June 20, 2012.
Project Management Process Overview
CHIPPEWA FALLS AREA UNIFIED SCHOOL DISTRICT PROPOSED BUDGET.
OSF/ISD Project Portfolio Management Framework January 17, 2011.
Boreal Renewable Energy Development Ferriter Scobbo & Rodophele PC Outback Engineering Richard C. Gross, Inc. March 12, 2009 Notus Clean Energy LLC Wind.
Field Questions. –Asked by sub or GC when discrepancy in construction docs or existing site conditions Design change verification request Field information.
Chapter 2 Needs Identification. 2 Learning Objectives Review the project life cycle –identifying needs –proposing a solution –performing the project –terminating.
12-1 Project Management from Simple to Complex This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported.
The GSA Leasing Process. The Two Golden Rules for GSA Leases: Don't contact GSA! Don't contact the lessor! DO Contact your RPMD (GSA) realty specialist!
Indiana Hoosier Lottery Lottery Draw Witness Pre-Proposal Conference September 14, 2012 Stan Judson IDOA Strategic Sourcing Analyst.
Citizens Advisory Committee Quarterly Update Bill Van Meter, Assistant General Manager, Planning September 19, 2012.
Presented by: Masoud Shams Ahmadi February 2007 Enterprise Resource Planning (ERP) Selection Presented by: Masoud Shams Ahmadi
Workshops on Discussion Draft of Guidelines December 2014.
Talbot County Project Sunburst Talbot County Department of Parks & Recreation Private/Public Partnership July 12,
ERCOT PROGRESS REPORT Board of Directors Austin, Texas October 15, 2002.
Mr. Thilak de Silva. BSc. Eng., MSc, CEng, FIE(SL), FIET(UK), CITP(UK), MBCS(UK), MIEEE (USA) M.Sc. in IT - Year 1 Semester II
Federal Energy Regulatory Commission The Pre-Filing Process IRWA/AI January 13-14, 2009 IRWA/AI.
Transportation and Aging A Community Approach!. Why community engagement?  Knowledge – Aging is universal and all have information on transportation.
Silver Line Phase 1 – Status Report Status Overall Phase 1 Construction – 99% complete All Station at 98% complete except Wiehle – Reston East at 99% complete.
Slide 1 PAO MO75 M. Hugon D:/DATA/POWERPNT/HNML. 0107kickoffconcertedaction ADvanced Options for P&T ADOPT Thematic Network kick-off Meeting.
METROPOLITAN TRANSPORTATION COMMISSION Key Steps to Delivering Project 1.Lead agency submits final project scope, budget and schedule to MTC 2.MTC.
Introducing Project Management Update December 2011.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
American Recovery and Reinvestment Act of 2009 Energy Efficiency and Conservation Block Grant Program Small City and County Grant Kick-Off Meeting California.
Grants and Contracts Jim Butterfield and Kathy Blackwood October 5, 2004.
LIGO-G M Advanced LIGO Cost, Schedule and Management Gary H Sanders NSF Review of Advanced LIGO Caltech, June 11, 2003.
City Council Meeting December 15, 2015 Planning Division File No. CUP
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
Richland Creek Water Supply Program Contract for WTP and Pump Stations CMAR Services and Program Update Paulding County, Georgia Board of Commission Work.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
California Energy Commission Solicitation Process Presentation Presenter : Rachel Grant Kiley, Manager Contracts, Grants and Loans Office California Energy.
Implementing Program Management Standards at Duke Energy.
Multi-State Clean Energy RFP 1 To explore whether a multi-state procurement might attract larger-scale projects and transmission than single state procurements.
PORT OF TACOMA Capital Lumber Lease Extension Action Requested of Commission Authorize the Chief Executive Officer or his Designee to enter into a Lease.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Regional Water Reclamation Facility 23-MGD Expansion Project Joe Mouawad, P.E. Senior Director.
7 November 2006Program Management Basics Purdue FIRST Programs Slide 1 Program Management Basics Purdue FIRST Programs Chris Fultz Rolls-Royce Corporation.
State Home Construction Grant Program FY2016 Grant FundingGrant Program Timeline Grant Program Update.
PORT OF TACOMA Capital Lumber Lease Extension Action Requested of Commission Authorize the Chief Executive Officer or his Designee to enter into a Lease.
OTE Building PMG Report March 2, 2012 Rhonda Merchut 1.
Implementing Packaging and Printed Paper Stewardship Plan Southern Interior Waste Manager’s Association Annual Conference September 19, 2013.
Rob Connatser NSS Instrument Work Packages and XLPM.
André Hoddevik, Project Director Enlargement of the PEPPOL-consortium 2009.
USAID Afghanistan Engineering Support Program (ESP) Pre-Bid Meeting July 14, 2015.
Azusa Utility Board Meeting January 28, Power Resources Division Monthly Report Power Resource Update Power Consumption Comparison Wholesale Market.
Southeast Rail Extension FasTracks Monitoring Committee July 14, 2015.
Green Line Extension Project
Quail Valley Subarea 9, Phase 1 Sewer Award of Construction Contracts
Cottonwood Recycled Water Pipeline (West)
Civic Center Sports Field Study Session & Quarterly Update
Request for Proposal & Proposal
Eagle Programme : 4 Box Summary
Green Line Extension Project
1 Stadium Company Network. The Stadium Company Project Is a sports facility management company that manages a stadium. Stadium Company needs to upgrade.
Exit Capacity Substitution and Revision
Xoserve IX Refresh Customer Update 03/01/2019.
DSC ChMC CSS update 09th January 2019
Q2 Updates on 2019 Board Priorities
Q2 Updates on 2019 Board Priorities
HOME AFFAIRS IDENTIFICATION SYSTEM (hanis)
Step 3. Initiate Proposal
Presentation transcript:

VOWTAP Progress Report VOWDA December 2, 2015

DOE Grants VOWTAP Extension No Cost Time Extension until May 31, 2016 Conditional upon achievement of two milestones – Issue request for proposals for the fabrication and construction of VOWTAP and receive and formally evaluate bids. – Provide DOE a letter from Dominion’s Board or Authorized Representative stating it will submit a Cost Recovery Rider to the State Corporation Commission no later than July 31, 2016

Major Construction Request For Proposals Issued Transportation, Erection and Installation of the Inward Battered Guide Structure Foundations (IBGS) and Wind Turbine Generators (WTG) – 6 Bidders Final Design, Manufacture, Transportation, Installation, Horizontal Directional Drilling and Termination of the Export and Inter-array Cables – 4 Bidders Engaged K2 to provide lessons learned and review scope of work for RFPs Issued November 17, 2015 Responses due January 15, 2016

Additional Pricing Activities Scheduled for Q Request for Proposals for smaller work scopes – Foundation fabrication – On shore interconnection station equipment and installation Updated estimates from project partners and industry contacts for remaining VOWTAP scope – Instrumentation – Commissioning – Project Management Final compiled estimate will be reviewed by a third party

Q Develop and Issue major construction work RFPs Engaged a recognized 3 rd party offshore wind management company Develop optimal scope of work packages No later than May 1, 2016 Provide DOE with proof of milestone achievement RFP results and final estimate Dominion commitment letter regarding SCC submittal by July Q Issue small scope RFPs Develop final estimate based on results of all RFPs Analyze RFP results Revise project estimates and risk profile May 31, 2016 DOE supports funding for future budget periods Confirm DOE funding commitment Q Dominion Governance Approvals to Proceed Update stakeholders Prepare filing Achievable Schedule, Clearly Defined Milestones

Questions