September 2008 QSEC auction - Allocations Transmission Workstream 04.12.08.

Slides:



Advertisements
Similar presentations
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Advertisements

Commercial Arrangements For Gas Quality Service – Process UNC Transmission Workstream 23 rd April 2007.
Long Term Entry Capacity & User Commitment Transmission Workstream 7 th August 2008.
Exit Reform Review Transmission Workstream 07 January 2010.
UNC Modification Proposal 0116 Reform of the NTS Offtake Arrangements Transmission Workstream 5 th October 2006.
Moving the QSEC and AMSEC Auctions National Grid NTS, Transmission Workstream.
Modification 500 slides for Workgroup
The Treatment of “Spare / Sterilised” Capacity – follow up Draft for discussion purposes only.
Entry Capacity Release Methodology Statement Transmission Workstream, 4 th May 2006.
Long Term Entry Capacity & User Commitment Review Group th September 2008.
GRI NW Investment Workshop Chris Logue, European Policy Manager, 4 th June 2010 The Hague.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Transfer & Trades Special Transmission Workstream
RMTTSEC – Rolling Monthly Trade and Transfer System Entry Capacity Auction Transmission Workstream, 2 April 2009.
Capacity Release Processes and Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
Auctions recommendations GTE+ Capacity Product Coordination (CPC) Workshop on 26 November 2008 Matthew Hatch National Grid.
Flow Variations at Entry Transmission Workstream Martin Watson 1 st November 2007.
Entry Capacity Substitution Workshop 7 – 10 th February 2009.
Transfers and Trades Transmission Workstream
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Modification Proposal 0246: Quarterly NTS Entry Capacity User Commitment Chris Shanley.
Assignment of NTS Entry Capacity Transmission Workstream 06 November 2008.
UKL13950 UK Link Committee 14 th February 2008 COR880 Gemini 2008 Release (Summer)
Update on Entry Capacity Substitution Transmission Workstream 6 th March 2008 Summary of consultation responses.
Entry Capacity Substitution Workshop 2 7 th May 2008 Substitution Example.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Review of Entry Capacity and the Appropriate Allocation of Financial Risk Review Group th Sept 2008.
Initial Thoughts on the Release of Non Obligated NTS System Entry Capacity Transmission Workstream 3 rd April 2008.
Optimisation of Entry Capacity Strawman Transmission Workstream 4 th May 2006.
Entry Capacity Substitution Workshop 3 11 th June 2008 Substitution Example.
Implementation of Trades and Transfers National Grid NTS 5 th June 2008.
Fundamental review of entry charging principles UNC Transmission Workstream - 6 th August 2009.
Transmission workstream 6 April Overview of TPCR Third Consultation UNC transmission workstream – 6 April Mark Feather.
Entry Capacity Substitution Workshop 4 9 th July 2008 Entry Capacity Substitution Methodology Statement: Discussion Paper.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th March 2009.
Facilitating Release of Non-obligated Entry Capacity Draft – for discussion purposes only 22 November 2007.
Entry Capacity Substitution: Discussion Document Transmission Workstream 7 th August 2008 Initial Analysis of Responses.
Proposal to adjust investment lead times Transmission Workstream 4 th May 2006.
DRSEC Update Transmission Workstream 06 November 2008.
Trades and Transfers Workshop, 6 th November 2007.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
Mod Entry Capacity Transfers Transmission Work Stream, 5 April 2007.
Transfers and Trades Special Transmission Workstream
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Exit Capacity Release Methodology Statement
Entry Capacity Overrun price calculation
Transmission Workstream, 01 October 2009
CMP Transparency Requirements
Non-approved draft Transmission Workstream, 6th December 2007
Introduction of Code Contingency Guidelines Document
Transmission Workstream, 2nd March 06
Entry Capacity - update
DRSEC Update August 4th 2009.
Capacity Methodology Statements: Impact of Mod 452
NTS Entry Charging Review Update
Capacity Methodology Statements
Exit Capacity Substitution and Revision
Development of Entry Capacity Substitution
QSEC auction timetable
Modification 501 slides for Workgroup
Introduction of Code Contingency Guidelines Document
Review of Trade and Transfer Winter 09/10
Mod 230: QSEC and AMSEC Timings
Modification Proposal 0133 – “Introduction of AMTSEC auction”
Optimisation of Entry Capacity Modification Proposal
IECR Incremental Step Size
Review Group 221: Review of Questions from Session 2
Modification 0043 – Limitation on offering for sale unsold capacity
Entry Capacity Transfers - Constrained Period
Presentation transcript:

September 2008 QSEC auction - Allocations Transmission Workstream

2 Introduction  Following November workstream, some Shippers expressed an interest in the 2008 QSEC allocation results  Aggregate results were published 14 November on Gemini, National Grid website and via Joint Office  Now taking the opportunity to run through these results and answer any questions you may have

3 Quick reminder - QSEC bidding  Demand driven price  Auction can close early if stability groups remain unchanged between interim bid windows – difficult to predict when this will happen  This year’s auction closed after interim bid window 2  Price Step (P0) = 90% baseline – minus anything sold in previous auctions + any unsold incremental  Price Steps P1 to P20 = Incremental Capacity offered (Available NTS Entry Capacity)  Incremental prices are based on the long run incremental cost of providing additional capacity above the obligated level

4 Allocations Overview ASEP Total Allocated (kWh) Revenue (£) Cleared Price Step Clearing Price Lowest Price Highest Price Avonmouth219,803,25020,031P Bacton5,218,997,44139,666,749P Barrow2,179,490,00013,779,413P Burton Point 100,743,3229,198P Cheshire6,524,648,800595,821P Dynevor264,524,55024,109P Hatfield Moor Stor. 259,200,000655,273P

5 Allocations Overview (cont…) ASEP Total Allocated (kWh) Revenue (£) Cleared Price Step Clearing Price Lowest Price Highest Price Hole House6,399,923,044584,415P Hornsea19,620,000159,805P Grain1,291,200,000706,444P Partington219,803,25020,031P St Fergus1,691,670,28658,409,444P Teesside1,991,246,19115,090,587P Theddlethorpe359,579,0602,692,577P

6 Incremental Capacity Release - Caythorpe  Incremental signal received for 90 GWh  Obligated incremental until Dec 2015  Obligated Incremental allocated at price step P6 = p/kwh  After 5 years Obligated Incremental then becomes baseline  April 2020 to December 2024 allocated at P0 (along with some individual quarters earlier on in the transaction period)  Total revenue received = £19,305,720

7 Non Obligated Incremental Capacity Release - Easington  Allocations made of both Baseline and non obligated capacity  Aggregate Volume of Capacity sold 1,284,329,102 kWh  Total Revenue received - £11,297,469  Baseline Capacity Sold  1,060,599,012 kWh  Revenue - £8,984,488  Incremental signal received for some quarters :  Where NPV test not passed, National Grid can choose to release non obligated incremental inline with UNC section B2.6 (a) (iii)  National Grid released non-obligated incremental capacity at Easington in Q1 2011, Q1 2012, Q1 2013, Q and Q  Total sold - 223,730,079 kWh  Revenue - £2,312,981

8 Conclusion  Currently the next QSEC auction should be held, in accordance with Code, in September 2009  2 UNC modification have been raised on Auction timing:  Modification Proposal 0230 is seeking to change this so that the next QSEC auction would be held in March 2010  Modification Proposal 230A seeks to maintain existing September QSEC Auction in September 2009 prior to transition to a March 2010 Auction  Full guide to the QSEC auction is available on National Grid’s website with contact details for the Capacity Auctions team and also for independent consultants, should you wish to obtain advice on bidding strategies  All of the information in today’s presentation is taken from the aggregate QSEC results published on National Grid’s website ANY QUESTIONS?