PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.

Slides:



Advertisements
Similar presentations
PHENIX WEEKLY PLANNING 1/4/2007 Don Lynch. 1/4/207 Weekly Planning Meeting 2.
Advertisements

PHENIX WEEKLY PLANNING 6/7/2007 Don Lynch. 6/7/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day No More Planned Remove.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 4/20/06 Don Lynch. Safety We have lost a whole week of running because of a violation of procedure and not because of the accident.
PHENIX WEEKLY PLANNING 11/30/06 Don Lynch. 11/16/06 Weekly Planning Meeting 2 PHENIX END OF SHUTDOWN PARTY Celebrating the successful installation of.
6/6/ PHENIX WEEKLY PLANNING 6/6/2013 Don Lynch Note: No PHENIX planning meeting this week due to end of run party. Feel free to discuss safety and.
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 10/05/06 Don Lynch. 10/05/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
Technical Support /4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.
1/9/ PHENIX WEEKLY PLANNING Jan. 9, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
4/10/ PHENIX WEEKLY PLANNING April 10, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 7/31/06 Don Lynch. 7/31/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameDurationStart_DateFinish_Date PHENIX Shutdown.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 PHENIX WEEKLY PLANNING December 3, 2015 Carter Biggs.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
3/6/ PHENIX WEEKLY PLANNING March 6, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 3/09/06 Don Lynch. BLM Test BLM Test Installation He Bags.
PHENIX WEEKLY PLANNING 3/23/06 Don Lynch. MPC Electronics MPC rack installed without cards. Cards to be installed As available and as access time is available.
1 PHENIX WEEKLY PLANNING January 21, 2016 Carter Biggs.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
4/24/ PHENIX WEEKLY PLANNING April 24, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 10/20/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
4/17/ PHENIX WEEKLY PLANNING April 17, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 10/12/06 Don Lynch. 10/12/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
5/8/ PHENIX WEEKLY PLANNING May 8, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
PHENIX WEEKLY PLANNING 1/24/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
Preparations for Run 6 Don Lynch February 13, 2006.
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
PHENIX WEEKLY PLANNING 10/26/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch.
2/27/ PHENIX WEEKLY PLANNING Feb. 27, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
PHENIX WEEKLY PLANNING 3/30/06 Don Lynch. This Week MPC air flow started BLM source test HBD transparency monitor hutch work and cable tray 1 st MPC Card.
1 11/25/2010 PHENIX WEEKLY PLANNING 11/25/2010 Don Lynch.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 8/24/06 Don Lynch. 8/24/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameDurationStart_DateFinish_Date PHENIX Shutdown.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
PHENIX WEEKLY PLANNING 2/16/06 Don Lynch. Prep for Run 6 Completed.
Presentation transcript:

PHENIX WEEKLY PLANNING 2/9/06 Don Lynch

Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines dried [DONE] MuTr HV & LV repairs and tests [DONE] Install Lampshades on MMS [DONE] Receive MPC South (Received 1/8/06) Prepare EC for move to IR (carpenters) [DONE] Re-install seismic restraints on WC [DONE] Prepare MPC South (install LED’s, bench elec. tests) [DONE] Uninstall TOF West Installation platform [DONE] Install MPC South [DONE] Install HBD rack (lower only) [DONE] Move MUID collar to IR [DONE] Install MPC cable tray [DONE]

Remove upper HBD I-beams, use fg unistrut for now [DONE] EC roll in Carpenters to do platforms [DONE] Pink sheets [DONE] MPC South installation [DONE] CM area sweep for magnet test [DONE] Magnet tests [DONE] Continue blue sheets [DONE] Connect EC Services [DONE] Install shield wall [DONE] DC repairs [DONE] Move MMS North [DONE] Install MUID collar [DONE] Fabricate BLM Test Diode holders [in process] Fabricate RXNP Mag Test Fixture [DONE] Complete CM area HBD plumbing [DONE] Prep Schedule for Run 6

Week of Feb. 6 – Feb. 10, 2006 RXNP magnet tests [ready?] Install plug door [DONE] Start of PHENIX watch shifts [started] Start flammable gas flow Blue ring ready for beam Feb. 6, limited IR access [beam circulating] All up commissioning [in process] Start of Run Party [tomorrow] Week of Feb. 13- Feb. 17, 2006 Yellow ring ready for beam All up commissioning Week of Feb. 21 – Feb. 24, 2006 (Pres. Day Holiday 1/20/06) Install Beam Loss Monitor Install MPC electronics on eyebrow Start of run shifts Week of Feb. 27 – Mar. 4 Start physics runs Prep Schedule for Run 6

Completed Tasks

Remaining Tasks MPC test and fix MPC dry air supply manidfold RXNP detector PMT magnet tests –Fabricate test fixture –Run tests BLM test –Fabricate fixture –Install for run –Un-install when HBD is installed Start flammable gas Start of Run party Beam in yellow ring Start recording physics New LN2 Dewar for BBC cooling gas (replacing dry air) Install HBD (~March-April prototype and/or ~May ½ final design)

MPC Installation MPC electronics to be on top of MuTr rack on eyebrow Electronics not ready yet

RXNP PMT in magnetic field tests Photo-multiplier Tubes (PMT’s) PMT’s

Beam Loss Monitor Tests 3 BLM’s 2 Chipmunks 2 stripixel detector samples 16 diodes (8 small, 8 large) 2 thermorecorder buttons Diode Holder

Other Projects TOF West No further work until next shutdown HBD A ll gas work inside IR to be completed prior to end of shutdown Will need new He bags? Plan for installation of ½ final detector late in run 6 using lower rack only Plan B – install prototype during run 6 Need to design & fabricate cable support structure for prototype and final design Bridge Utilities No water until next summer. Shutoff valves to be closed and posted until manifolds are tested MPC North New enclosure & fixture design to be based on lessons learned from south installation RXNP No design info yet?

HBD Prototype Mounting Prototype can not use final design mounting due to differences in location of connectors and other basic design differences. Final HBD design is not yet fixed. Prototype mounting to be fabricated from fg unistrut.

LN 2 Storage Dewar for BBC Acme Cryogenics 6000 Gallon vessel 23’ long x 10’4” high, 7’ wide footprint 219psig MAWP, we would set MOP to 125psig. Original Mfr.: Linde, NB #6363 ser.#206 Remanufactured by Chart

LN 2 Supply Acquire ASME NB certified 6000 gal LN 2 Dewar CA internal cryo and mechanical safety review Modify gas pad layout to accommodate dewar Install dewar on pad LN2 dewar to be located on south side of pad beyond CO2 unit shown here

LN 2 Storage Dewar for BBC LN 2 Vessel to go here

New Gas Pad Design. Dimensions and access to be added. Estimated weight of 6000 gallon tank 30 tons when full, 10 tons when empty. Experimental safety review required. LN 2 Storage Dewar for BBC

C-A Tasks Current Tasks Support for LN 2 dewar installation General run support Tasks for Shutdown 2006 Install access platforms from EC top north and MMS Replace emergency fan louvres Rewire/add IR ceiling lights on emergency power Replace WC sliding platform hoisting cables Analyze/balance rack water distribution Mixing house exhaust fan maintenance

Shutdown 2006 We expect a short shutdown with a full plate of work June ’06: end run 5, prep for start of shutdown, prep EC for move to AH July ’06: TOF West installation, HBD installation Aug. ’06: MPC North installation, RXNP installation Sep. ’06: Detector subsystems maintenance, roll EC in, prep for run 6 Oct. ’06: Start of Run 6 Get your special requests in early! Links for weekly planning meeting slides, long term planning and other technical info can be found from the web site:

PHENIX Engineering & Tech Support Web Pages Links for weekly planning meeting slides, long term planning and other technical info can be found from the web site: