PHENIX WEEKLY PLANNING 8/24/06 Don Lynch. 8/24/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameDurationStart_DateFinish_Date PHENIX Shutdown.

Similar presentations


Presentation on theme: "PHENIX WEEKLY PLANNING 8/24/06 Don Lynch. 8/24/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameDurationStart_DateFinish_Date PHENIX Shutdown."— Presentation transcript:

1 PHENIX WEEKLY PLANNING 8/24/06 Don Lynch

2 8/24/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameDurationStart_DateFinish_Date PHENIX Shutdown '06145 days5/1/200612/12/2006 Pre Shutdown Tasks60 days5/1/2006DONE End of Run 60 days6/27/2006DONE Shutdown Preparations16 days6/27/2006DONE Detector Upgrades47 days7/19/20069/29/2006 Planned electrical power outage5 days7/24/2006DONE Subsystem maint/repair tasks47 days7/19/20069/22/2006 Building and infrastructure tasks113 days5/1/200610/31/2006 E carriage roll in & setup14 days10/9/200610/27/2006 RHIC Cooldown Begins0 days10/27/2006 Run Prep25 days12/1/2006 Shutdown Concluded0 days12/1/2006

3 8/24/06 Weekly Planning Meeting 3 Prior To Shutdown Pre Shutdown Tasks 60 days Mechanical design For RXNP4 wksComplete HBD cable mangement4 wksComplete Receive TOF West detectors from VU0 daysComplete TOF West pre-installation tests (hi bay)4 wksComplete Design mounting/install'n for MPC N6 wksComplete Order/fabricate parts for RXNP/HBD/MPC N12 wksComplete Modify TEC connectors2 wksComplete Design piping route for Bridge water1 wkComplete Work Permits1 wkComplete End of Run 60 days Run Ended

4 8/24/06 Weekly Planning Meeting 4 Shutdown Prep Shutdown Preparations16 days6/26/20067/18/2006 Purge gas from all detectors2 daysDone End of Run party0 daysDone DAQ tests (no Flam. Gas)3 daysDone Open up & prep1 dayDone Open rolling door1 dayDone Remove rolling wall and plug doors1 wkDone Take down EC access ladder & fold platforms1 dayDone Prepare EC for move to AH3 daysDone Remove beampipe collar1 dayDone Move MMS full south and restrain1 dayDone Retract and remove EC to AH2 daysDone Install 12 ton cart on tracks1 dayDone Move beampipe collar to AH1 dayDone Install decking1 dayDone

5 8/24/06 Weekly Planning Meeting 5 Detector Upgrades TOF West-- DesignDone Purchased/procured partsDone Fabricated partsDone Assembly at 510Done Work permitDone Mechanical InstallationDone PHENIX mechanical survey offsets (adjustments completed no further adjustment reasonably feasible)Done Electrical-- HV/LV/Signal Cable routing & connectingDone Modify/upgrade rack-- electronics18-Jul15-Sep cooling water18-Jul1-Sep Testing18-Jul15-Sep

6 8/24/06 Weekly Planning Meeting 6 Detector Upgrades RXNP-- DesignDone Purchased/procured partsDone Fabricated parts-- PMT CoversDone Fan coversDone Assembly: 8 quadrants-- South detectorDone North detectorDone Pre-Survey: 8 quadrantsDone Mechanical Installation: South detector, North detector, cable trays-- South detectorDone North detectorDone Cable traysDone Installation survey25-Aug

7 8/24/06 Weekly Planning Meeting 7 Detector Upgrades RXNP (Cont’d) Electrical Installation -- HV/signal/optical routing and connecting 28-Aug29-Aug Rack installation -- Mechanical Installation 30-Aug2-Sep Water hookup 4-Sep8-Sep Power hookup 4-Sep8-Sep Cable connections 4-Sep8-Sep Safety systems 4-Sep8-Sep Grounding 4-Sep8-Sep Testing 30-Aug1-Oct Project Closeout 27-Oct1-Dec

8 8/24/06 Weekly Planning Meeting 8 Detector Upgrades HBD -- DesignDone Purchased/procured partsDone Fabricated partsDone Assembly-- West and East detectors at Stony Brook18-Jul15-Sep electronics racks at PHENIX30-Aug1-Sep cable trays at PHENIXDone movable cable traysDone Fixed cable traysDone Pre-Survey: West and East detectors at Stony Brook-- West detector24-Aug East detector18-Sep19-Sep Scribe centerline marks on upper and lower ibeams25-Aug Mechanical Installation: West and East detectors in IR-- West detector30-Aug1-Sep East detector20-Sep22-Sep West moveable cable trays5-Sep6-Sep East moveable cable trays25-Sep26-Sep Fixed cable traysDone

9 8/24/06 Weekly Planning Meeting 9 Detector Upgrades HBD -- Installation survey -- Set up equipment for West detector 7-Sep Adjust location of West detector 8-Sep Set up equipment for East detector 27-Sep Adjust location of East detector 28-Sep Electrical Installation HV/signal/LV routing and connecting 11-Sep6-Oct Rack installation and connection 30-Aug8-Sep Mechanical Installation 30-Aug8-Sep Water hookup 30-Aug8-Sep Power hookup (Mike Rau) 30-Aug8-Sep Cable connections 30-Aug8-Sep Safety systems 30-Aug8-Sep Grounding 30-Aug8-Sep Testing 9-Sep13-Oct Gas system -- Final piping 30-Aug13-Oct IR distibution panel and monitoring hardware 30-Aug13-Oct Gas house controls and monitoring system 30-Aug31-Oct Monitoring hutch controls, monitoring and piping 30-Aug13-Oct Other: Cooling, Heating, Flash Lamp: design/review/fabrication/installation ???

10 8/24/06 Weekly Planning Meeting 10 HBD at Stony Brook More pictures of the HBD at Stony Brook can be found at: http://picasaweb.google.com/jkamin/HBD

11 8/24/06 Weekly Planning Meeting 11 Detector Upgrades MPC N Design Done Purchased/procured parts Done Fabricated parts -- Detector Parts Done Go-No Go gauge Done Assembly -- Pre assembly/fit up at UI Done Pre assembly/fit up at PHENIX Done electronics racks at PHENIX 11-Sep15-Sep Mechanical Installation: Detector sextants 5-Sep8-Sep cable trays 11-Sep12-Sep Installation survey 15-Sep Electrical Installation HV/signal/LV routing and connecting 18-Sep22-Sep Rack installation and connection 25-Sep29-Sep Mechanical Installation 25-Sep29-Sep Power hookup 25-Sep29-Sep Cable connections 25-Sep29-Sep Safety systems 25-Sep29-Sep Grounding 25-Sep29-Sep Testing 2-Oct13-Oct Project Closeout 27-Oct1-Dec

12 8/24/06 Weekly Planning Meeting 12 MPC N at BNL MPC N Rack goes here oriented with long edge vertical 18” cable tray to be replaced with 6” tray shifted 12” to the north on this face of MUID rack

13 8/24/06 Weekly Planning Meeting 13 Subsystems IV. Existing Detector Maintenance EMCal WC maintenance and repairDone EC maintenance& repairDone DC HV/LV patch panelDone West Wire repairs18-Sep22-Sep MuTr Prepare work permits for MMS and MMNDone Remove SE vertical lampshadeDone Remove SE bias lampshadeDone Troubleshoot shorts in MMSDone Repair shortsDone Troubleshoot and repair Repair MMS and MMN HV/FEE’s etc.Done Reinstall SE bias lampshadeDone Reinstall SE vertical lampshadeDone Closeout workpermit9-Oct

14 8/24/06 Weekly Planning Meeting 14 Subsystems (continued) IV. Existing Detector Maintenance MPC S Prepare work permitDone Remove cables for accessDone Remove top 2 octants for reworkDone Rework/repairs on removed octantsDone Reinstall top octants24-Aug Reinstall wiringSep 26 Closeout work permit9-Oct TEC Machine slots in fittingsDone Maintenance and repairs on TEC electronics31-Jul15-Sep BBC Remove BBC South andDone Remove BBC North5-Sep Maintenance and repairs23-Aug22-Sep Reinstall BBC North25-Sep Reinstall BBC South26-Sep MuID30-Oct3-Nov

15 8/24/06 Weekly Planning Meeting 15 Infrastructure Work CAD/RHIC PHENIX infrastucture related mechanical and electrical support Emergency remote breaker installation Done Summer Sunday review platform and safety rails Done Bridge Water supply vertical piping rework Done Replace emergency fan louvres -- Rewire/Add IR ceiling lights on emergency power -- Replace WC sliding platform hoisting cables -- Mixing House exhaust fan maintenance -- Raw materials storage container painting and doors Done Roof leak repairs -- He Bags 1-Aug31-Oct Bridge protective runners Done

16 8/24/06 Weekly Planning Meeting 16 He Bags

17 8/24/06 Weekly Planning Meeting 17 2006 Shutdown Wrapup/Run 7 Prep East carriage roll in & setup Prepare EC for move to IR 9-Oct13-Oct EC Roll in 16-Oct17-Oct Connect EC services 18-Oct24-Oct Install EC Ladder 25-Oct26-Oct Install EC rear access & ext. 26-Oct27-Oct MuID Commissioning 30-Oct3-Nov RHIC Cooldown Begins 27-Oct Move MMS full North 27-Oct Install beam pipe collar 30-Oct Rebuild Rolling door 31-Oct6-Nov Install Plug Door & steel platform 6-Nov Close rolling door 7-Nov Pink Sheeting & Blue Sheeting 8-Nov21-Nov Start Flammable Gas Flow 22-Nov All Up Commissioning 27-Nov1-Dec Beam in yellow ring 22-Nov29-Nov Beam in blue ring 29-Nov5-Dec RHIC beam conditioning 5-Dec12-Dec Shutdown Concluded 12-Dec

18 8/24/06 Weekly Planning Meeting 18 Next Week RXNP Final Survey RXNP cable installation to bridge RXNP LED fiber installation HBD west installation HBD west final survey HBD west cable installation to bridge and to LV/signal rack TEC repairs BBC S repairs ?

19 8/24/06 Weekly Planning Meeting 19 Tier I knocks 1. Flammable material in the tech shop stored in boxes should be placed in the chemical cabinet 2.The following housekeeping issues must be corrected: a.Boxes stored in the tech shop must be emptied and stored properly. b.Storing material between the building and shielding (Electronics Area) is not considered a storage area and should be removed. c. Storing gas tanks and holders under the wood steps outside is not allowed and should be removed. d. Cardboard on floor behind PHENIX experiment should be removed. e. 1008F wiring found outside and should be relocated. 3.The PHENIX facility has numerous 4" openings that are not in compliance with OHSA standard. The standard allows 4" holes but not openings that are 4" wide by 8 - 10 feet long. All of the grating system needs to have fillers placed in these large openings

20 8/24/06 Weekly Planning Meeting 20 4. In the PHENIX highbay area there is a sink and water pump in front of a disconnect that needs to be relocated per OHSA 5.The PHENIX laser is not secured. A key was left in the power supply and the door is open. Remove the laser key and secure the area as required. 6.The PHENIX gas storage facility has three (3) small isobutene cylinders not secured. A gas storage sign is on the ground. Also a gas cylinder rack is all rusted (behind the carbon dioxide dewar) that needs to be replaced. In addition, the 5,200 gallon dewar does not have a "label" on it identifying its contents 7.In the PHENIX gas storage facility there is a 5,200 gallon dewar that has a manufacturer plate on it stating that this dewar is rated and designed to hold hydrogen. However, it is believed that the content of this large dewar is nitrogen, which is 14 times the density of hydrogen. This dewar requires the manufacturer to supply legal documentation stating that it is capable of holding 5,200 gallons of nitrogen. This document must be provided to the C-AD ESH Coordinator. Tier I knocks

21 8/24/06 Weekly Planning Meeting 21 Links for the shutdown schedule as well as weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found from the web site: http://www.phenix.bnl.gov/WWW/INTEGRATION/ME&Integration/DRL_SSint-page.htm Where To Find PHENIX Technical Info