Balanced Portfolio 1 Project Original Cost Estimate Q3 2012 Latest Update Cost Variance% Change Sooner - Cleveland 345 kV $33,530,000$58,906,000$59,880,000$26,350,00078.6%

Slides:



Advertisements
Similar presentations
Transmission Expansion Kansas Wind and Renewable Energy Conference Topeka, KS September 23, 2008.
Advertisements

Project Development Process (PDP) Structures. PDP – Three Project Levels Major Project ~ 14 Steps Major Project ~ 14 Steps Minor Project ~ 10 Steps Minor.
Bob Smith, P.E. Region 1 Benjamin Acimovic, P.E., Region 1
Change Order Missouri Local Programs How to Complete a Change Order & Get it Approved.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
TRB BRT Workshop July 22, 2008 ECTP Project Oversight Grantee Perspective.
SPP.org 1. Draft Business as Usual Plan SPP.org 3 Wind - Business as Usual.
Preparing a Post Bid Report Preparing a Post Bid Report NYS OGS Design & Construction Group Cost Control.
SPP.org 1. Economic Portfolio Update – CAWG Meeting – AEP Offices, Dallas August 27, 2008.
Wind Energy Update October 6, OG&E’s Commitment to Wind Energy (2007) Make Oklahoma a national leader in renewable energy Mission Accomplished!
Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee October 9, 2012.
FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.
North Mankato Load Serving study Xcel Energy Great River Energy.
SPP.org 1. Priority Project Update Bruce Rew Vice President, Engineering.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
Midwest Energy, Inc. Transmission Planning and Expansion
Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development December 14, 2005 Introduction Neil Millar, vice-president, Transmission.
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
Indefinite Delivery/ Indefinite Quantity (IDIQ) Jorge A. Rueda.
Africa Geospatial Forum Geospatial Empowering Utilities.
Engineering & Buildings Procurement Seminar.
IMPERIAL VALLEY CONFERENCE July 21, SOLICITATION RENEWABLES PORTFOLIO STANDARD.
Jan 13, 2012 RPG Meeting El Campo – Vanderbilt 69 kV Project – Status report Ehsan Ur Rehman Planning Engineer ERCOT.
Presented by Amanda Winn and Paula Gustafson June 14, 2011.
COMPLIANCE WITH GRANT IMPLEMENTATION PROCEDURES TxDot Grant Fund Project.
Remarks will print on the completed form Generate Quantity Book Entry Generate Pay Quantity.
1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.
Pasadena Water and Power APPROVE A PROJECT CONTINGENCY AMOUNT OF $2,500,000 FOR EXISTING CONTRACTS RELATED TO THE LOCAL GENERATION REPOWERING PROJECT -
Katy Freeway 40 mile section of IH 10 from downtown Houston to the Brazos River Constructed in the 1960’s Design capacity of 79,200 vehicles per day –Pavement.
Progress Report on Construction Projects of Rajarata University of Sri Lanka as at 30 th June 2015.
Arizona ACC Biennial Transmission Assessment Navajo Transmission Project Update May 22, 2008 Presentation by Ben Hoisington Project Administrator, DPA.
March 9, 2011 Report on Construct & Equip Wells (Moniter, 6400 South, 1330 East)
RTF Pump VFD Provisional Standard Protocol Regional Technical Forum June 18, 2013.
How to Review a SAR (Key attributes of a good SAR) October 2007 DAMIR Conference Dana Harrison (703)
Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
Integrated Risk Management 36 – Month Final Status Report Christian DeVoll, Risk Management Specialist June 2013.
1 Module 6, Part 3: PPE (Property, Plant and Equipment) 1. Costs to Capitalize 2. Depreciation 3. Asset Sale or Impairment 4. Disclosure 5. Ratios.
2 Preliminary  Pre-Design & Design  Prior to Bid Letting  For funding allocation and bid comparison Final  Construction  Post Award  For contractor.
Request For Qualifications (RFQ) Missouri Local Programs How to Complete the RFQ & Get it Advertised.
02/13/2009 RPG Wind Interconnection Survey Dan Woodfin Director, System Planning.
Option for an Enhanced SPP Regional Project Review Process Presentation to the Regional State Committee January 24, 2011 Lisa M. Barton SVP American Electric.
Toll Bridge Seismic Retrofit Program Project Schedule and Budgets.
OCTOBER 2, 2013 Maine 2013 Outage Coordination Redacted Copy.
May 15, 2009 Regional Planning Group CREZ Implementation Study Update Warren Lasher Manager, System Assessment.
Distribution Statement A: Approved for Public Release; Distribution is unlimited Project Manager for Maneuver Ammunition Systems, ATTN: SFAE-AMO-MAS, Picatinny,
Balanced Portfolio Update PCWG August 28,
Britannia Village Flood Control Project Report Back to RVCA Board of Directors – Dec 16, 2010 after attendance at Community Meeting of November 30, 2010.
Fundamentals of Project Control Chapter 11 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project.
Civil Engineering Surveying Roy Frank. Basic Route Survey and Design 1.Concept for Route 2.Reconnaissance Study 1.Small scale mapping of region (1”-500’
Douglas Bowman, PE, PMP Project Manager Entergy Corporation New Projects and Processes Ensure Power Transfer for Northeast Arkansas Customers.
3 CDBG Disaster Recovery Waterway Debris Program Wednesday, January 13, 2010.
R ENEWABLE E NERGY IN T EXAS Jess Totten Public Utility Commission of Texas 1.
S-Curve The Calculations, Parameters and Formulas.
Wolf Creek School Division No.72. Why do we adjust the spring budget? Alberta Education requirement of a budget update. This is an information only item.
100% REAL EXAM QUESTIONS ANSWERS CCP Certified Cost Professional
Warren Lasher Manager, Long-Term Planning and Policy
Cambrian School District Project Update June 4, 2015 Board of Trustees Meeting Jason Vann, CFO Will Robertson, Kramer Project Development Co.
Financing Land Development Projects
Construction Approach and Productivity Issues
Reconciling December.
Pre-contract Planning and Practice
Classroom Enclosure – Phase II Bonnie Beard Agriculture Center
Estimating Capital Costs
Dominion Investments in Virginia
Capital Appeal Pledges and Contributions
Control Procurement - I
Presentation to LEP Performance and Investment Committee 16 May 2018
Presentation transcript:

Balanced Portfolio 1 Project Original Cost Estimate Q Latest Update Cost Variance% Change Sooner - Cleveland 345 kV $33,530,000$58,906,000$59,880,000$26,350, % Seminole - Muskogee 345 kV $129,000,000$161,700,000 $32,700, % Tuco - Woodward 345 kV $227,727,500$328,733,021$328,645,462$101,917, % Iatan - Nashua 345 kV $54,444,000$64,800,000 $10,356, % Spearville - Post Rock - Axtell 345 kV $236,557,015$224,000,000 ($12,557,015)-5.3% Swissvale - Stilwell Tap 345 kV $2,000,000 $1,922,840($77,160)-3.9% Gracemont Substation $8,000,000$15,200,000$15,966,210$7,966, % Total $691,258,515$855,339,021$857,002,071$165,743, %

Tuco - Stateline 345 kV Ckt 1 (SPS) 2 Original Cost Estimate In-Service Date Latest Cost Estimate Cost Variance % Change Expenditure to Date % of Latest Estimate $122,597,500 5/19/2014$170,247,072$47,649, %$4,195,8222.5% Percentage of Completion Material Procurement7%Environmental Studies50% Construction0%Engineering38% Siting and Routing95%Permit Status35% Cost Estimate Increase Justifications CREZ projects in same area elevating ROW costs30% 13% increase in line length (178 to miles)30% 43% increase in number of corner/angle structures30% Switch from in-house engineering and construction to consultants and contractors10% Potential Future Cost Increase Factors Increased costs of purchasing easements (due to recent awards for CREZ projects) Number of corner/angle structures may increase for minor route adjustments Labor/material costs could increase due to steel/aluminum price fluctuations and availability of contract labor In-service date may change due to length of time to acquire easements Final Pedestrian survey could cause archeological or biological mitigation requirements

Tuco 345/230 kV Transformer Ckt 2 (SPS) 3 Original Cost Estimate In-Service Date Latest Cost Estimate Cost Variance % Change Expenditure to Date % of Latest Estimate $11,250,000* 3/31/2013$15,498,390$4,248, %$7,086, % Percentage of Completion Material Procurement7%Environmental StudiesN/A Construction25%Engineering85% Siting and RoutingN/APermit StatusN/A Cost Estimate Increase Justifications None provided Potential Future Cost Increase Factors None mentioned *SPS estimate at time of Modified NTC issuance