Overview WP14 Developments Hardware  Interferometry on the spare TDIs, planned to be installed Christmas stop 2015/2016. Final acceptance tests ongoing.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

12/03/2013MPP Workshop Annecy Update on Beam Failure Scenarios Jan Uythoven Thanks to: T.Baer, R.Schmidt, J.Wenninger, D.Wollmann, M.Zerlauth, other MPP.
LHC 18 & 19 April 2015 At 450 GeV with bumps, no increased MUFO activity. Beam screen 15R8 warming up to 80 K, ongoing for the day 09:00: Orbit studies.
FCC-hh Injection and Extraction
Impedance of new ALICE beam pipe Benoit Salvant, Rainer Wanzenberg and Olga Zagorodnova Acknowledgments: Elias Metral, Nicolas Mounet, Mark Gallilee, Arturo.
Beam Dumping System – Failure Scenarios Brennan Goddard, CERN AB/BT How the dump system can fail Catalogue of primary failures Failure classes and protection.
New ALICE Beam Pipe: Injection Protection C. Bracco on Behalf of ABT/BTP Acknowledgment: M. Giovannozzi.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
The LHC injection systems located in points 2 and 8 are comprised of several elements common to the LHC ring and the downstream ends of the TI 2 and TI.
1 Flux concentrator for SuperKEKB Kamitani Takuya IWLC October.20.
MKI Erratics: Hardware and Electronics Related Aspects M.J. Barnes Acknowledgements: A.Antoine, R.A. Barlow, P. Burkel, E. Carlier, N. Magnin, V. Mertens.
LHC 1 st August :34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in.
Summary of Week 30 G. Arduini, J. Wenninger Main aims: “Adiabatically” increase peak luminosity by emittance reduction Luminosity production.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
Scrubbing Run: TDI, MKI and MKE interlocks Chiara Bracco, Jan Uythoven ABT/BTP Acknowledgments: T. Baer, M. Barnes, E. Carlier.
Outcome of HBW damper Review of W. Hofle LIU-SPS HBW damper review LIU SPS Coordination,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
1 Fast kicker study Machine Time 2011/10/18~10/29(2 weeks) TB meeting 2011/01/14 T.Naito.
LIU-SPS e-cloud contribution to TDR Electron cloud meeting, 17/02/20141 o First draft by end of February Between 5 to 10 max pages per chapter, refer.
LHC beam dump, injection system and other kickers B.Goddard, with input from L.Ducimetière, W.Bartmann, V.Mertens, J.Borburgh, M.Barnes, C.Bracco, V.Senaj,
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Beam absorbers for Machine Protection at LHC and SPS
ALICE sensitivity to background and injection failures with the smaller aperture A. Di Mauro TREX meeting, 31/07/2014.
Preparation for Circulating Beam - Part II Collimators (40') Oliver Aberle o Breakdown of tests foreseen in preparation for beam o Equipment folder: tests.
HL-LHC WP14 2 nd meeting: Intercepting devices and failure cases to be studied Anton Lechner, Jan Uythoven.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
HP-PS beam acceleration and machine circumference A.LachaizeLAGUNA-LBNO General meeting Paris 18/09/13 On behalf of HP-PS design team.
MPP Workshop: Injection System C. Bracco on behalf of ABT Acknowledgments: STI, ABP, BI,LHC and SPS OP.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16.
V. Kain AB/OP1Chamonix XV What is required to safely fill the LHC? V.Kain AB/OP Input from: B.Goddard, M.Jonker, Y.Kadi, R.Losito, V.Mertens, B.Puccio,
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
LINAC4 ADVISORY COMMITTEE
Surviving an Asynchronous Beam Dump?
The LHC Beam Dumping System
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Introduction: FCC beam dumping system
SPS extraction, transfer lines, injection
Case Study - Group 2 FCC-ee Top-Up Injection
Thermo-mechanical simulations jaws + tank
WP14 Coordination meetings
LHC Risk Review: Kicker Magnet Reliability
FCC hh dump kicker - switch topologies and impact on beam
Safe Injection into the LHC V.Kain AB/CO
FCC-hh injection group 7
Pros and cons interleaving the filling of the LHC
Safe Injection into the LHC V.Kain AB/CO
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
CERN, Geneva, Switzerland PAC 2003 – Portland, Oregon, USA
2017 CAS Erice case study: Design of a beam dumping system for FCC
Scrubbing progress - 10/12/2012
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
LHC Beam Operations Past, Present and Future
LHC Morning Meeting - G. Arduini
CLIC damping rings working plan towards the CDR
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
IP8 aperture measurements (07:30-10:30)
Kicker and RF systems for Damping Rings
FOLLOW-UP FOR THE TDI = LHC injection beam stopper
Kicker specifications for Damping Rings
Another Immortal Fill….
Acknowledgements: Alain Antoine, Nicolas Magnin & Volker Mertens
Specifications for the XFEL Beam Switchyard Kickers
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Thursday 10:00 Fill 1986 in stable beams.
Presentation transcript:

Overview WP14 Developments Hardware  Interferometry on the spare TDIs, planned to be installed Christmas stop 2015/2016. Final acceptance tests ongoing.  MKI coating of ceramic chamber & cooling  see talk M.Barnes Studies  Discussed in many informal meetings (12x)  Mainly concerning injection protection 1 WP14 Developments, Jan Uythoven HL-LHC WP14, 7/11/2014

Time Line Injection protection for LIU beams  To be installed in LS2  Studies presently ongoing: This Meeting  Aim to have a protection layout by the end of 2014 Injection kickers MKI  Proto-type or dummy to be installed, possibly / latest LS2 Beam Dumping System related items  To be installed in LS3  Studies to start once injection protection studies done 2 WP14 Developments, Jan Uythoven HL-LHC WP14, 7/11/2014

Injection protection: main topics of studies Survival of absorbers = TDI for 1  impact of 288 bunches BCMS beam  Presentation by F.Lorenzo Maciariello  Possibly limit the number of bunches per injection, V.Kain in Chamonix Common studies TCDI (LIU) and TDI. HiRadMat tests foreseen Search for new materials, HiRadMat tests Protection of D1  Presentation N.Shetty  Mask TCDD not effective enough for grazing beams  Aperture constraints mask: F.Velotti Impact on auxiliary absorbers TCLIA and TCLIB: F.Velotti  To be followed by Q6 protection studies ZDC Aperture ALICE  A.Lechner TDI in multi modules  TDIS (Segmented)  Impedance vs. mechanical stability and heating  Meetings with ABP impedance team. Defined cases being studied. 3 WP14 Developments, Jan Uythoven HL-LHC WP14, 7/11/2014 IP

Beam Parameters: a moving target LIU parameters 20 September 2013: LHC Deliverable Report D1.3, table 10, from RLIUP meeting, October 2013: HL-LHC parameter list ‘today’ from Webpage: 4 WP14 Developments, Jan Uythoven HL-LHC WP14, 7/11/2014 N bunch [10 11 p/b)  x,y Standard BCMS N bunch [10 11 p/b)  x,y Standard BCMS N bunch [10 11 p/b)  x,y Standard BCMS2.3< 2.0* * “For the BCMS scheme emittances down to 1.4 um have already been achieved at LHC injection which might be used ….”

Injection failure modes Injection kicker failures protected by  Beam Energy Tracking System: always the correct voltage on the MKI  Erratic re-triggering of dump switch in case of erratic on main switch  An MKI pulse as short as possible to limit number of stored bunches possibly affected Worst failures modes – for the absorber AND protection: 1  impact or grazing  Injected beam: Break down in magnet at 70 % of magnet length  one magnet at 140 % kick strength  system kick at 110 %, which is grazing impact of 288 bunches Idem break down at 30 % of magnet length  90 % system kick  Stored beam Switch erratic followed by re-triggering: 159 bunches ‘flat top’ at large angle plus sweep of bunches during rise and fall time of pulse Timing error: 288 bunches at full impact plus additional swept bunches  Both beams simultaneously In the case of a timing error: 288 bunches top TDI jaw, plus 288 bunches (plus some swept) on the lower jaw. Full impact  not critical. Not for jaw survival nor for magnet protection (D1). 5 WP14 Developments, Jan Uythoven HL-LHC WP14, 7/11/2014