City of Winnipeg SOUTHWESTERN RAPID TRANSIT CORRIDOR Bidder Meeting October 16 th, 2009.

Slides:



Advertisements
Similar presentations
CONSTRUCTION DRILLING INC.
Advertisements

Cofferdam.
CONSTRUCTION DRILLING INC. SPECIALIZING IN UNIQUE DRILLING AND CUT-OFF WALL SOLUTIONS.
PILE FOUNDATION.
LRFD Design of Shallow Foundations
Investigation of Consolidation Promoting Effect by Field and Model Test for Vacuum Consolidation Method Nagasaki University H.Mihara Y.Tanabasi Y.Jiang.
Design of Mat Foundations
Foundations and basements
Foundations Excavations
Foundations. Feature common to bridge and building structures Deep vs. shallow Safely transfer dead and live loads with acceptable levels of settlement.
Foundations. Foundation supports weight of structure –Includes soil and rock under foundation –Building construction described by foundation type Slab.
AASHTO LRFD Section 11 Abutments, Piers, and Walls
G3 – Environmental Geomechanics (Dr Sam Yuen)
Foundation Fundamentals GSD 6204 Building Technology Harvard Graduate School of Design.
SHALLOW FOUNDATIONS Spread footings Mat (Raft) foundations Square
PILE FOUNDATION BY-.
FOOTINGS.
SOIL, GEOTECHNICAL ENGINEERING AND FOUNDATION ENGINEERING
CE 120 Introduction to Civil Engineering
CE 120 Introduction to Civil Engineering
Pad Foundation Lectured by: Ms. Noorhidayah Sunarti
Lecture 11 Advance Design of RC Structure Retaining walls
TOPIC 2: TYPES OF FOUNDATION
Foundation Engineering CE 483
FOUNDATION.
CM413 Soil Mechanics Course Lecturer: Prof.Dr. Hassan Abd Ellatif Course Assistant: Eng: Shimaa Shaaban.
SUBJECT NAME: FOUNDATION ENGINEERING SUBJECT CODE: CE 1306
Chapter 2b Foundations Shallow & Deep Foundations.
Homebush Bay Rail Link l 700 lineal metres of precast concrete arch l 9 different profiles.8 x 2.5 to 19 x 8 l 900 units. l Reinforced soil with precast.
Mata kuliah: S0892 – Ground Improvement Method Tahun: 2010 Case Study Session
C ONTACT STRESS IN CIVIL ENGINEERING. Introduction 1 Skyscrapers Bridges Dams How are these constructions supported? Why are all these large constructions.
Details of Construction Lecture-2 “Shallow Foundation”
Abstract *Our project is about ( Foundation Design of Al- Maslamani Mall) which is located in the village of Beit Eba – Nablus governorate. *The total.
Department of Civil Engineering,
AN INTEGRATED DESIGN CONCEPT … … FROM UNDERGROUND UP TO THE TOP ODOTECHNIKI LTD CONSULTING ENGINEERS Address: 59, 3 rd September Str.
BCM 210 Foundation Issues- Fall 2000 refer to Allen Text
4.4 SOIL NAILING SOIL NAILING IS A REINFORCEMENT METHOD TO REINFORCE THE GROUND WITH STEEL BARS OR STEEL BARS IN GROUT FILLED HOLES. IT IS MAINLY USED.
1 Foundations and retaining walls.
GEOTECHNICAL ENGINEERING ECG 503 LECTURE NOTE 10 TOPIC : 3
Modern GROUND IMPROVEMENT TECHNIQUES FOR HIGHWAYS
Figure 2.1 Sequence of site analysis. Barry's Introduction to Construction of Buildings, Second Edition, by Stephen Emmitt and Christopher A. Gorse. ©
Foundation Loads Dead Load Live Load Wind Load
BEARING CAPACITY OF SOIL Session 3 – 4
BUILDING CONSTRUCTION
COFFERDAMS.
SOIL MECHANICS AND FOUNDATION ENGINEERING-II (CE 311)
Foundation Failure. Foundation movement may result from a wide range of factors, which can include: Shrinking or swelling of clays caused by changes in.
SITE INVESTIGATION ARUN MUCHHALA ENGINEERING COLLEGE-DHARI
Foundation types and uses
GLE/CEE 330: Soil Mechanics Introduction to Foundation Engineering
FOUNDATIONS.
BULDING CONSTRUCTION ( )
ANT11 Presentation, October, 10-13, 2011 David Vardiman Project Engineer Geotechnical Design and Excavation 1 Sanford Lab at Homestake, Lead, SD 4850L.
DIAPHRAGM WALLS.
BUILDING CONSTRUCTION
INSTITUTE OF TECHNOLOGY
A REPORT ON PRACTICAL TRAINING CONDUCTED AT PUBLIC WORK DEPARTMENT(PWD),KOTA FROM 15/6/2011 TO 14/7/2011 Submitted to: Mr. Rajneesh Sharma HOD {Civil Dep.}
SHALLOW FOUNDATIONS BY, Babariya Ashish Gondaliya Ronak Gondaliya akshay Javiya hardik
Design of Rockery Retaining Walls
Soil MECHANICS AND FOUNDATION ENGINEERING-II (CE 311) [6] Types of Foundations 1437-Summer SaMeH.
EAG346-Sem II 2014/2015 Lesson 2.
Foundations.
Arch205 Materials and building construction 1 foundation
CONSTRUCTION METHODS & TECHNOLOGY
4th Annual Construction Law Summit
Arch205 building construction foundation
GEOTECHNICAL ENGINEERING ECG 503 LECTURE NOTE 10 TOPIC : 3
REVISION 1 1. Foundations.
N.N.Som Consulting Geotechnical Engineer
Graduation Project Bracing system for deep excavation.
Presentation transcript:

City of Winnipeg SOUTHWESTERN RAPID TRANSIT CORRIDOR Bidder Meeting October 16 th, 2009

Site Location

Field Investigations - Klohn Krippen (2003) - Geotechnical 4 deep test holes, 1 shallow Groundwater monitoring Laboratory testing –AECOM (2009) - Geotechnical 2 deep test holes ( rock coring) Groundwater monitoring Laboratory testing –AECOM (2009) – Hydrogeological Two test wells drilling Field pump tests

Location of Test Holes TW 2 TW 1

Soil Stratigraphy

Field and Lab Results

Groundwater Conditions –Clay : 2 m below ground, Elv. 231 m –Bedrock/Till : Elv. 224 to 226 m –Impact on: Excavation stability Global stability Seepage

Geotechnical Concerns – Foundation type – Rebound, heave and settlement – Retaining walls – Base heave – Temporary shoring and excavation plan

Bearing capacity and foundation type – Raft foundation – Design based on the concept of floating foundation – Bearing capacity and settlement pressure are defined

Rebound, Heave and Settlement

Retaining walls - Reinforced Concrete U-shaped section - Reinforced Concrete Cantilever wall - Coulomb Theory - Design for surcharge from compaction during construction - Design for live load surcharge from Cooper E90 loading -

Clay Till/Bedrock FS = W clay / γ w h Base heave h W clay

TYPICAL EXTREME HISTORICAL

Temporary shoring and Excavation plan – Cut and cover construction – Staged construction, Stage I and II – Site constrains: Limited space Utilities Private property Proximity to CN tracks – Excavations plan include: Open excavation Cantilever / Braced Shoring Combination of shoring and open excavation

Temporary shoring and Excavation plan – Excavation configurations Open Excavation, up to 6 m cut Other geometry < 6m cut

Temporary shoring and Excavation plan – Excavation configurations Braced Shoring up to 9.5 m ~ Min ~ 5

Temporary shoring and Excavation plan – Excavation configurations Combination of Braced Shoring and Open excavation m bench 5 m Crane pad varies 5 m Min. varies 7 Max.

Temporary shoring and Excavation plan Lateral Loads from Surcharge

Temporary shoring and Excavation plan Base Instability : analogous to bearing capacity

Global Stability - Stress – stability coupled finite element analysis - Locally acceptable soil parameters - Account for excavation unloading - Model train loading - Design objective FS = 1.30

Stability output

Stress-Deformation Analysis

Performance Monitoring Program Instrumentation will be installed to monitor – Displacement of railway tracks – Displacement of shoring system – Horizontal subsoil displacement – Excavation heave – Groundwater levels

THANK YOU